Skip to content
GharKundli

CITY PRIDE

by YAKUB HASSAN KHOT · Camp Dapoli, Ratnagiri

Possession date of CITY PRIDE: 30 April 2028, moved from 1 May 2025 (31 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800020915. Status: In abeyance (on hold by MahaRERA). Its completion date has moved from May 2025 to April 2028: 31 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about CITY PRIDE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of CITY PRIDE has moved

  1. 1 May 2025

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA04102518018)

    Reason the builder gave MahaRERA:
    “Due to the promoter’s health issues and complete lack of bookings, the project suffered severe financial constraints, which adversely affected cash flow and construction progress. Additionally, the project incurred losses due to natural cal…” Read the full reason“Due to the promoter’s health issues and complete lack of bookings, the project suffered severe financial constraints, which adversely affected cash flow and construction progress. Additionally, the project incurred losses due to natural calamities such as cyclones and floods in the Dapoli region, further impacting the overall timeline. During this period, the building plans were also revised and additional FSI was sanctioned, resulting in the addition of 5 units, which required revision of layouts and approvals. Owing to these factors and the absence of any sales, the overall project execut…”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: CITY PRIDE’s extension records on MahaRERA (P52800020915), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on CITY PRIDE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800020915
Status
In abeyance (on hold by MahaRERA)
Builder
YAKUB HASSAN KHOT
Location
Camp Dapoli, Ratnagiri · 415712
Project type
Residential / Group Housing
Registered on
17 May 2019
Completion date at registration
May 2025
Latest completion date
April 2028
Delay so far
31 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
42
Sold or booked
2%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of CITY PRIDE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
CITY PRIDE100%100%50%0%

Commencement certificate (CC), as filed on MahaRERA

  • RESIDENTIAL BUILDING: covers 5 floors
  • RESIDENTIAL BUILDING: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on CITY PRIDE every month.

CITY PRIDE: buildings, flats and land, as filed on MahaRERA

  • Buildings: CITY PRIDE (5 floors, 42 units) · RESIDENTIAL BUILDING (5 floors) · RESIDENTIAL BUILDING (5 floors)
  • Land: 1,310 sq m (about 0.3 acres) · sanctioned built-up 2,641 sq m
  • Boundaries filed include: NAGARPANCHAYAT ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of CITY PRIDE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

CITY PRIDE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about CITY PRIDE

What is the possession date of CITY PRIDE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for CITY PRIDE in Camp Dapoli, Ratnagiri is 30 April 2028 — 31 months later than 1 May 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for CITY PRIDE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date CITY PRIDE's builder has filed on MahaRERA, the official one, is 30 April 2028, already 31 months later than the 1 May 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of CITY PRIDE extended?

According to GharKundli's check of MahaRERA records (updated October 2026), CITY PRIDE's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Due to the promoter’s health issues and complete lack of bookings, the project suffered severe financial constraints, which adversely affected cash flow and construction progress. Additionally, the project incurred losses due to natural calamities such as cyclones and floods in the Dapoli region, further impacting the overall timeline. During this period, the building plans were also revised and additional FSI was sanctioned, resulting in the addition of 5 units, which required revision of layouts and approvals. Owing to these factors and the absence of any sales, the overall project execut…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of CITY PRIDE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of CITY PRIDE in Camp Dapoli, Ratnagiri is P52800020915.

Is CITY PRIDE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CITY PRIDE is registered as P52800020915 and its status is "In abeyance (on hold by MahaRERA)".

What is the construction status of CITY PRIDE?

According to GharKundli's check of MahaRERA records (updated October 2026), CITY PRIDE's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work on CITY PRIDE is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does CITY PRIDE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is CITY PRIDE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), CITY PRIDE is registered on MahaRERA as P52800020915, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has moved 31 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if CITY PRIDE's possession date changes?

The latest dates are on CITY PRIDE's MahaRERA page (P52800020915). GharKundli's Kundli Watch sends a free WhatsApp update on CITY PRIDE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does CITY PRIDE have?

According to GharKundli's check of MahaRERA records (updated October 2026), CITY PRIDE has 3 buildings filed: CITY PRIDE with 5 floors and 42 units; RESIDENTIAL BUILDING with 5 floors; RESIDENTIAL BUILDING with 5 floors.

How big is the land of CITY PRIDE?

According to GharKundli's check of MahaRERA records (updated October 2026), CITY PRIDE stands on 1,310 sq m of land (about 0.3 acres), with 2,641 sq m of sanctioned built-up area.

Where can I read reviews of CITY PRIDE?

Google Maps has reviews of CITY PRIDE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is CITY PRIDE?

CITY PRIDE by YAKUB HASSAN KHOT is in Camp Dapoli, Ratnagiri (pincode 415712), Maharashtra, and is registered on MahaRERA as P52800020915, per GharKundli's check of MahaRERA records. Its boundaries filed there include NAGARPANCHAYAT ROAD.

How many homes are in CITY PRIDE?

According to GharKundli's check of MahaRERA records (updated October 2026), CITY PRIDE has 42 homes in 3 towers registered on MahaRERA, and 2% of them are sold or booked.

When was CITY PRIDE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), CITY PRIDE was registered on MahaRERA on 17 May 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on CITY PRIDE?

No court cases are listed for CITY PRIDE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of CITY PRIDE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is YAKUB HASSAN KHOT.

All projects with possession due in 2028 in Ratnagiri →

Other projects in pincode 415712

All 77 projects in Dapoli (415712) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.