Possession date of HAWANA PARK: 30 April 2028, moved from 30 December 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800026181, and currently active. Its completion date has moved from December 2024 to April 2028: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about HAWANA PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HAWANA PARK has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 31 December 2027

    Extended at the builder's request (MahaRERA application EA28102518188)

    Reason the builder gave MahaRERA: “I unable to complete the project within original due date to some financial issues & non-availability of building material. Hence I request to extend the date of completion of project till 31st December 2027.”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: HAWANA PARK’s extension records on MahaRERA (P52800026181), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HAWANA PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800026181
Status
Registered and active
Builder
JALIL HASANMIYA NANDGAONKAR
Location
Jogele, Ratnagiri · 415712
Project type
Residential / Group Housing
Registered on
27 Aug 2020
Completion date at registration
December 2024
Latest completion date
April 2028
Delay so far
36 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
53
Sold or booked
82%
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of HAWANA PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A0%0%0%0%
BUILDING B0%0%0%0%
BUILDING C0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING A: covers 5 floors
  • BUILDING B: covers 4 floors
  • BUILDING C: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HAWANA PARK every month.

HAWANA PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A (5 floors, 21 units) · BUILDING B (4 floors, 13 units) · BUILDING C (5 floors, 19 units)
  • Land: 1,916 sq m (about 0.5 acres) · sanctioned built-up 2,338 sq m
  • Boundaries filed include: NAGARPANCHAYAT ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of HAWANA PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HAWANA PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HAWANA PARK

What is the possession date of HAWANA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HAWANA PARK in Jogele, Ratnagiri is 30 April 2028 — 36 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for HAWANA PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HAWANA PARK's builder has filed on MahaRERA, the official one, is 30 April 2028, already 36 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HAWANA PARK extended?

According to GharKundli's check of MahaRERA records (updated October 2026), HAWANA PARK's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "I unable to complete the project within original due date to some financial issues & non-availability of building material. Hence I request to extend the date of completion of project till 31st December 2027.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of HAWANA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HAWANA PARK in Jogele, Ratnagiri is P52800026181.

Is HAWANA PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HAWANA PARK is registered as P52800026181 and its status is "Registered and active".

What is the construction status of HAWANA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), HAWANA PARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does HAWANA PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is HAWANA PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), HAWANA PARK is registered on MahaRERA as P52800026181, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HAWANA PARK's possession date changes?

The latest dates are on HAWANA PARK's MahaRERA page (P52800026181). GharKundli's Kundli Watch sends a free WhatsApp update on HAWANA PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HAWANA PARK have?

According to GharKundli's check of MahaRERA records (updated October 2026), HAWANA PARK has 3 buildings filed: BUILDING A with 5 floors and 21 units; BUILDING B with 4 floors and 13 units; BUILDING C with 5 floors and 19 units.

How big is the land of HAWANA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), HAWANA PARK stands on 1,916 sq m of land (about 0.5 acres), with 2,338 sq m of sanctioned built-up area.

Where can I read reviews of HAWANA PARK?

Google Maps has reviews of HAWANA PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HAWANA PARK?

HAWANA PARK by JALIL HASANMIYA NANDGAONKAR is in Jogele, Ratnagiri (pincode 415712), near Dapoli, Maharashtra, and is registered on MahaRERA as P52800026181, per GharKundli's check of MahaRERA records. Its boundaries filed there include NAGARPANCHAYAT ROAD.

How many homes are in HAWANA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), HAWANA PARK has 53 homes in 3 towers registered on MahaRERA, and 82% of them are sold or booked.

When was HAWANA PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HAWANA PARK was registered on MahaRERA on 27 August 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on HAWANA PARK?

No court cases are listed for HAWANA PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of HAWANA PARK?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JALIL HASANMIYA NANDGAONKAR, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Ratnagiri →

Other projects in Dapoli

All 71 projects in Dapoli (415712) →

Other projects by JALIL HASANMIYA NANDGAONKAR

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.