YUGANT PARK
by NADIR KAMRUDDIN RAKHANGE · Dapoli, Ratnagiri
Possession: YUGANT PARK is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800012839. Status: Completed. Its completion date has moved from December 2019 to April 2028: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about YUGANT PARK?
How the possession date of YUGANT PARK has moved
25 December 2019
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT52800011060)
Reason the builder gave MahaRERA:
“NON AVAILABILITY OF SAND AND OTHER BUILDING MATERIAL ETC , due to the covid 19 the project is badly affected and supply of material in the rural area was not in proper manner. We need extension in this project because there are 20 units whi…” Read the full reason
“NON AVAILABILITY OF SAND AND OTHER BUILDING MATERIAL ETC , due to the covid 19 the project is badly affected and supply of material in the rural area was not in proper manner. We need extension in this project because there are 20 units which are unsold and without extension number we are not able to sold that units. once the units are sold then it will help us to complete the project at the earliest. Hence it is our humble request to you to grant us extension till 31st December 2025”31 December 2027
Extended at the builder's request (MahaRERA application EA06022619746)
Reason the builder gave MahaRERA:
“due to the covid 19 the project is badly affected and supply of material in the rural area was not in proper manner. We need extension in this project because there are 20 units which are unsold and without extension number we are not able…” Read the full reason
“due to the covid 19 the project is badly affected and supply of material in the rural area was not in proper manner. We need extension in this project because there are 20 units which are unsold and without extension number we are not able to sold that units. once the units are sold then it will help us to complete the project at the earliest. Hence it is our humble request to you to grant us extension till 31st December 2027”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: YUGANT PARK’s extension records on MahaRERA (P52800012839), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on YUGANT PARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800012839
- Status
- Completed
- Builder
- NADIR KAMRUDDIN RAKHANGE
- Location
- Dapoli, Ratnagiri · 415712
- Project type
- Residential / Group Housing
- Registered on
- 7 Sep 2017
- Completion date at registration
- December 2019
- Latest completion date
- April 2028
- Delay so far
- 96 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 56
- Sold or booked
- 71%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of YUGANT PARK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A WING | 100% | 100% | 95% | 95% |
| B WING | 100% | 100% | 95% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- A WING: covers gr floor + 1st to 3rd Floor
- B WING: covers Ground+3 Floors
Latest CC order on MahaRERA: dated 11/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on YUGANT PARK every month.
YUGANT PARK: buildings, flats and land, as filed on MahaRERA
- Buildings: A WING (5 floors, 28 units) · B WING (5 floors, 28 units)
- Car parking: 29 covered
- Land: 2,702 sq m (about 0.7 acres) · sanctioned built-up 3,642 sq m · recreational space 275 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of YUGANT PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
YUGANT PARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about YUGANT PARK
What is the possession date of YUGANT PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for YUGANT PARK in Dapoli, Ratnagiri is 30 April 2028 — 96 months later than 25 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for YUGANT PARK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date YUGANT PARK's builder has filed on MahaRERA, the official one, is 30 April 2028, already 96 months later than the 25 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of YUGANT PARK extended?
According to GharKundli's check of MahaRERA records (updated October 2026), YUGANT PARK's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "NON AVAILABILITY OF SAND AND OTHER BUILDING MATERIAL ETC , due to the covid 19 the project is badly affected and supply of material in the rural area was not in proper manner. We need extension in this project because there are 20 units which are unsold and without extension number we are not able to sold that units. once the units are sold then it will help us to complete the project at the earliest. Hence it is our humble request to you to grant us extension till 31st December 2025"; to 31 December 2027, giving the reason "due to the covid 19 the project is badly affected and supply of material in the rural area was not in proper manner. We need extension in this project because there are 20 units which are unsold and without extension number we are not able to sold that units. once the units are sold then it will help us to complete the project at the earliest. Hence it is our humble request to you to grant us extension till 31st December 2027". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of YUGANT PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of YUGANT PARK in Dapoli, Ratnagiri is P52800012839.
Is YUGANT PARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), YUGANT PARK is registered as P52800012839 and its status is "Completed".
What is the construction status of YUGANT PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), YUGANT PARK's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does YUGANT PARK have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is YUGANT PARK safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), YUGANT PARK is registered on MahaRERA as P52800012839, its MahaRERA status is "Completed", its completion date has moved 96 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if YUGANT PARK's possession date changes?
The latest dates are on YUGANT PARK's MahaRERA page (P52800012839). GharKundli's Kundli Watch sends a free WhatsApp update on YUGANT PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does YUGANT PARK have?
According to GharKundli's check of MahaRERA records (updated October 2026), YUGANT PARK has 2 buildings filed: A WING with 5 floors and 28 units; B WING with 5 floors and 28 units.
How much parking does YUGANT PARK have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 29 covered car parking spaces for YUGANT PARK.
How big is the land of YUGANT PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), YUGANT PARK stands on 2,702 sq m of land (about 0.7 acres), with 3,642 sq m of sanctioned built-up area and 275 sq m of recreational open space.
Where can I read reviews of YUGANT PARK?
Google Maps has reviews of YUGANT PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is YUGANT PARK?
YUGANT PARK by NADIR KAMRUDDIN RAKHANGE is in Dapoli, Ratnagiri (pincode 415712), Maharashtra, and is registered on MahaRERA as P52800012839, per GharKundli's check of MahaRERA records.
How many homes are in YUGANT PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), YUGANT PARK has 56 homes in 2 towers registered on MahaRERA, and 71% of them are sold or booked.
When was YUGANT PARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), YUGANT PARK was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on YUGANT PARK?
No court cases are listed for YUGANT PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of YUGANT PARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NADIR KAMRUDDIN RAKHANGE.
Check it yourself on MahaRERA
- How to check the possession date of YUGANT PARK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 415712
- Mangal Mahalaxmi
- CITY PRIDE
- HAWANA PARK
- Mangal Kalash
- SAI SADAN
- HADI RESIDENCY
- SIDDHATANU LANDMARK
- Durvankur
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.