by Kokan Builders & Contractor · Lanja, RatnagiriAlso near Kondye

Possession: Belwalkar Shopping Center is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800004500. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Belwalkar Shopping Center?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Belwalkar Shopping Center has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT52800001434)

    Reason the builder gave MahaRERA: “Our entire Project work is on the verge of completion Hence with your permission, we would like to extend our Project completion date upto 31-12-2019 Thank You in advance for your consideration Thanks Regards Taj Mujawar”
  3. 15 July 2021

    Extended at the builder's request (MahaRERA application EXT52800011128)

    Reason the builder gave MahaRERA: “We have Completed Our Project in March 2020 and applied for Occupancy with Nagar Panchayat Lanja, Ratnagiri. Due To Covid Pandamic we got the Occupancy Certificate from Nagar Panchayat Lanja in the Month of July 2021.”
  4. 15 January 2022

    Revised completion date on MahaRERA

Source: Belwalkar Shopping Center’s extension records on MahaRERA (P52800004500), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Belwalkar Shopping Center

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800004500
Status
Completed
Builder
Kokan Builders & Contractor
Location
Lanja, Ratnagiri · 416701
Project type
Commercial
Registered on
9 Aug 2017
Completion date at registration
December 2018
Latest completion date
January 2022
Delay so far
37 months
Homes
102
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Belwalkar Shopping Center, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Belwalkar Shopping Center100%100%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Belwalkar Shopping Center every month.

Belwalkar Shopping Center: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Belwalkar Shopping Center →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Belwalkar Shopping Center: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Belwalkar Shopping Center

What is the possession date of Belwalkar Shopping Center?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Belwalkar Shopping Center in Lanja, Ratnagiri is 15 January 2022 — 37 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Belwalkar Shopping Center?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Belwalkar Shopping Center's builder has filed on MahaRERA, the official one, is 15 January 2022, already 37 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Belwalkar Shopping Center extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Belwalkar Shopping Center's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2019, giving the reason "Our entire Project work is on the verge of completion Hence with your permission, we would like to extend our Project completion date upto 31-12-2019 Thank You in advance for your consideration Thanks Regards Taj Mujawar"; to 15 July 2021, giving the reason "We have Completed Our Project in March 2020 and applied for Occupancy with Nagar Panchayat Lanja, Ratnagiri. Due To Covid Pandamic we got the Occupancy Certificate from Nagar Panchayat Lanja in the Month of July 2021.".

What is the RERA number of Belwalkar Shopping Center?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Belwalkar Shopping Center in Lanja, Ratnagiri is P52800004500.

Is Belwalkar Shopping Center registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Belwalkar Shopping Center is registered as P52800004500 and its status is "Completed".

What is the construction status of Belwalkar Shopping Center?

According to GharKundli's check of MahaRERA records (updated November 2026), Belwalkar Shopping Center's status on MahaRERA is "Completed". As filed by the builder, slab work on Belwalkar Shopping Center is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Belwalkar Shopping Center have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Belwalkar Shopping Center safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Belwalkar Shopping Center is registered on MahaRERA as P52800004500, its MahaRERA status is "Completed", its completion date has moved 37 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Belwalkar Shopping Center's possession date changes?

The latest dates are on Belwalkar Shopping Center's MahaRERA page (P52800004500). GharKundli's Kundli Watch sends a free WhatsApp update on Belwalkar Shopping Center every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Belwalkar Shopping Center have?

According to GharKundli's check of MahaRERA records (updated November 2026), Belwalkar Shopping Center has one building filed: Belwalkar Shopping Center with 6 floors.

How big is the land of Belwalkar Shopping Center?

According to GharKundli's check of MahaRERA records (updated November 2026), Belwalkar Shopping Center stands on 2,175 sq m of land (about 0.5 acres), with 2,530 sq m of sanctioned built-up area.

Where can I read reviews of Belwalkar Shopping Center?

Google Maps has reviews of Belwalkar Shopping Center written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Belwalkar Shopping Center?

Belwalkar Shopping Center by Kokan Builders & Contractor is in Lanja, Ratnagiri (pincode 416701), near Kondye, Maharashtra, and is registered on MahaRERA as P52800004500, per GharKundli's check of MahaRERA records. Its boundaries filed there include Mumbai Goa Highway.

How many homes are in Belwalkar Shopping Center?

According to GharKundli's check of MahaRERA records (updated November 2026), Belwalkar Shopping Center has 102 homes in 1 tower registered on MahaRERA.

When was Belwalkar Shopping Center registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Belwalkar Shopping Center was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Belwalkar Shopping Center?

No court cases are listed for Belwalkar Shopping Center on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Belwalkar Shopping Center?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Kokan Builders & Contractor.

Other projects in pincode 416701

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.

Belwalkar Shopping Center, Lanja, Ratnagiri: MahaRERA status, possession & complaints