MORYA RESIDENCY
by MANOJ VASANT MAHADIK · Lanja, RatnagiriAlso near Kondye
Possession date of MORYA RESIDENCY: 30 June 2026, moved from 30 June 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52800026050. Status: In abeyance (on hold by MahaRERA).
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (June 2026) has passed.
What do you want to know about MORYA RESIDENCY?
How the possession date of MORYA RESIDENCY has moved
30 June 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA29062501847)
Reason the builder gave MahaRERA: “Applied for Occupancy Certificate, process is taking time so need few more days for it.”
Source: MORYA RESIDENCY’s extension records on MahaRERA (P52800026050), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MORYA RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800026050
- Status
- In abeyance (on hold by MahaRERA)
- Builder
- MANOJ VASANT MAHADIK
- Location
- Lanja, Ratnagiri · 416701
- Project type
- Residential / Group Housing
- Registered on
- 12 Aug 2020
- Completion date at registration
- June 2025
- Latest completion date
- June 2026
- Delay so far
- 12 months
- Homes
- 32
- Sold or booked
- 71%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of MORYA RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MORYA RESIDENCY | 100% | 100% | 100% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- MORYA RESIDENCY: covers 5 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MORYA RESIDENCY every month.
MORYA RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: MORYA RESIDENCY (6 floors, 32 units)
- Land: 1,226 sq m (about 0.3 acres) · sanctioned built-up 1,322 sq m · recreational space 1,226 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Manoj Vasant Mahadik has 5 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA.
Read Google reviews of MORYA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MORYA RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MORYA RESIDENCY
What is the possession date of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MORYA RESIDENCY in Lanja, Ratnagiri is 30 June 2026 — 12 months later than 30 June 2025, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for MORYA RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MORYA RESIDENCY's builder has filed on MahaRERA, the official one, is 30 June 2026, already 12 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MORYA RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Applied for Occupancy Certificate, process is taking time so need few more days for it.".
What is the RERA number of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MORYA RESIDENCY in Lanja, Ratnagiri is P52800026050.
Is MORYA RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA RESIDENCY is registered as P52800026050 and its status is "In abeyance (on hold by MahaRERA)".
What is the construction status of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA RESIDENCY's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work on MORYA RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MORYA RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MORYA RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA RESIDENCY is registered on MahaRERA as P52800026050, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MORYA RESIDENCY's possession date changes?
The latest dates are on MORYA RESIDENCY's MahaRERA page (P52800026050). GharKundli's Kundli Watch sends a free WhatsApp update on MORYA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MORYA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA RESIDENCY has one building filed: MORYA RESIDENCY with 6 floors and 32 units.
How big is the land of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA RESIDENCY stands on 1,226 sq m of land (about 0.3 acres), with 1,322 sq m of sanctioned built-up area and 1,226 sq m of recreational open space.
What is the track record of MORYA RESIDENCY's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Manoj Vasant Mahadik has 5 projects on MahaRERA since 2020, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 10 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of MORYA RESIDENCY?
Google Maps has reviews of MORYA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MORYA RESIDENCY?
MORYA RESIDENCY by MANOJ VASANT MAHADIK is in Lanja, Ratnagiri (pincode 416701), near Kondye, Maharashtra, and is registered on MahaRERA as P52800026050, per GharKundli's check of MahaRERA records.
How many homes are in MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA RESIDENCY has 32 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.
When was MORYA RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MORYA RESIDENCY was registered on MahaRERA on 12 August 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on MORYA RESIDENCY?
No court cases are listed for MORYA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MORYA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MANOJ VASANT MAHADIK, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MORYA RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Ratnagiri →
Other projects in pincode 416701
- HAJI ABDUL GAFUR COMPLEX
- SARVADA HEIGHTS
- Kripalu Heights
- Elite Park
- DESAI BUILDING
- SHREE KRUSHNANAND SARASWATI
- Aashirwad
- LANJA CITY PRIDE PHASE I
Other projects by MANOJ VASANT MAHADIK
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.