Kripalu Heights
by SUNIL MANOHARLAL PURI · Lanja, Ratnagiri
Possession date of Kripalu Heights: 31 July 2026, moved from 31 March 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52800053631. Status: Lapsed (registration period ended). Its completion date has moved from March 2025 to July 2026: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Kripalu Heights?
GharKundli’s full report on Kripalu Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800053631
- Status
- Lapsed (registration period ended)
- Builder
- SUNIL MANOHARLAL PURI
- Location
- Lanja, Ratnagiri · 416701
- Project type
- Others
- Registered on
- 21 Nov 2023
- Completion date at registration
- March 2025
- Latest completion date
- July 2026
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 33
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Kripalu Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Kripalu Heights | 100% | 50% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Kripalu Heights: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Kripalu Heights every month.
Kripalu Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Kripalu Heights (4 floors, 73 units)
- Car parking: 10 open
- Land: 2,060 sq m (about 0.5 acres) · sanctioned built-up 3,673 sq m
- Boundaries filed include: National Highway 66 Mumbai
The builder’s record and reviews
Sunil Manoharlal Puri has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 4 complaints on MahaRERA across 1 project.
Read Google reviews of Kripalu Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Kripalu Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Kripalu Heights
What is the possession date of Kripalu Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Kripalu Heights in Lanja, Ratnagiri is 31 July 2026 — 12 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Kripalu Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Kripalu Heights's builder has filed on MahaRERA, the official one, is 31 July 2026, already 12 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Kripalu Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Kripalu Heights in Lanja, Ratnagiri is P52800053631.
Is Kripalu Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kripalu Heights is registered as P52800053631 and its status is "Lapsed (registration period ended)".
What is the construction status of Kripalu Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Kripalu Heights's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Kripalu Heights is 50% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Kripalu Heights have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Kripalu Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Kripalu Heights is registered on MahaRERA as P52800053631, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Kripalu Heights's possession date changes?
The latest dates are on Kripalu Heights's MahaRERA page (P52800053631). GharKundli's Kundli Watch sends a free WhatsApp update on Kripalu Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Kripalu Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Kripalu Heights has one building filed: Kripalu Heights with 4 floors and 73 units.
How much parking does Kripalu Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 open car parking spaces for Kripalu Heights.
How big is the land of Kripalu Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Kripalu Heights stands on 2,060 sq m of land (about 0.5 acres), with 3,673 sq m of sanctioned built-up area.
What is the track record of Kripalu Heights's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sunil Manoharlal Puri has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 4 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Kripalu Heights?
Google Maps has reviews of Kripalu Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Kripalu Heights?
Kripalu Heights by SUNIL MANOHARLAL PURI is in Lanja, Ratnagiri (pincode 416701), Maharashtra, and is registered on MahaRERA as P52800053631, per GharKundli's check of MahaRERA records. Its boundaries filed there include National Highway 66 Mumbai.
How many homes are in Kripalu Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Kripalu Heights has 33 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Kripalu Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Kripalu Heights was registered on MahaRERA on 21 November 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Kripalu Heights?
No court cases are listed for Kripalu Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Kripalu Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUNIL MANOHARLAL PURI, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Kripalu Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Ratnagiri →
Other projects in pincode 416701
- HAJI ABDUL GAFUR COMPLEX
- SARVADA HEIGHTS
- MORYA RESIDENCY
- Elite Park
- DESAI BUILDING
- SHREE KRUSHNANAND SARASWATI
- Aashirwad
- LANJA CITY PRIDE PHASE I
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.