Skip to content
GharKundli

Waterfront

by SATYENDRA SURESH VAIDYA · Markandi, Ratnagiri 415605Also near Chiplun, Kaviltali, Bazarpeth

What’s in the report? →

Possession date of Waterfront (MahaRERA P52800014670): 23 June 2022, moved from 28 May 2021 (13 months later), and it has already passed. It has 10 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800014670. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52800014670, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (June 2022) has passed.

What do you want to know about Waterfront?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Waterfront has moved

  1. 28 May 2021

    Completion date given when the project was registered

  2. 23 December 2021

    Extended at the builder's request (MahaRERA application EXT52800008769)

    Reason the builder gave MahaRERA: “Due to COVID-19 Pendamic and slack market”
  3. 23 June 2022

    Revised completion date on MahaRERA

Source: Waterfront’s extension records on MahaRERA (P52800014670), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Waterfront

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800014670
Status
Lapsed (registration period ended)
Builder
SATYENDRA SURESH VAIDYA
Location
Markandi, Ratnagiri · 415605
Project type
Others
Registered on
20 Dec 2017
Completion date at registration
May 2021
Latest completion date
June 2022
Delay so far
13 months
Homes
10
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Waterfront, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WATERFRONT0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Waterfront every 1–2 months.

Waterfront: buildings, flats and land, as filed on MahaRERA

  • Buildings: WATERFRONT (5 floors)
  • Land: 310 sq m (about 0.1 acres) · sanctioned built-up 593 sq m
  • Boundaries filed include: MUNICIPAL ROAD
  • Land, as filed: CTS- 4327, 4328, 4329 H.NO 225-H1-4-1-B-2, 225-H1-8-B-2,225-F1-B
  • Map: the location the builder filed on MahaRERA · Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Waterfront →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Waterfront: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Waterfront

What is the possession date of Waterfront?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Waterfront in Markandi, Ratnagiri is 23 June 2022 — 13 months later than 28 May 2021, the date given at registration. That date has already passed.

The date has already moved 13 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Waterfront?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Waterfront's builder has filed on MahaRERA, the official one, is 23 June 2022, already 13 months later than the 28 May 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Waterfront extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront's builder applied to MahaRERA to extend the completion date once: to 23 December 2021, giving the reason "Due to COVID-19 Pendamic and slack market".

What is the RERA number of Waterfront?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Waterfront in Markandi, Ratnagiri is P52800014670.

Is Waterfront registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront is registered as P52800014670 and its status is "Lapsed (registration period ended)".

What is the current construction status of Waterfront? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on WATERFRONT is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Waterfront have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Waterfront safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront is registered on MahaRERA as P52800014670, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 13 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Waterfront?

Waterfront isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Waterfront?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Waterfront: gharkundli.com/tools/property-cost-calculator

Has Waterfront received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 23 June 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Waterfront?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (23 June 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Waterfront uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Waterfront was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Waterfront's possession date changes?

The latest dates are on Waterfront's MahaRERA page (P52800014670). GharKundli's Kundli Watch sends a free WhatsApp update on Waterfront every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Waterfront have?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront has one building filed: WATERFRONT with 5 floors.

How big is the land of Waterfront?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront stands on 310 sq m of land (about 0.1 acres), with 593 sq m of sanctioned built-up area.

What are the reviews of Waterfront?

Google Maps has reviews of Waterfront written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Waterfront?

Waterfront by SATYENDRA SURESH VAIDYA is in Markandi, Ratnagiri, pincode 415605 (near Chiplun, Kaviltali, Bazarpeth), Maharashtra, and is registered on MahaRERA as P52800014670, per GharKundli's check of MahaRERA records. Its boundaries filed there include MUNICIPAL ROAD. Its land is filed as CTS- 4327, 4328, 4329 H.NO 225-H1-4-1-B-2, 225-H1-8-B-2,225-F1-B. GharKundli lists all 170 MahaRERA projects in Chiplun (415605).

How many flats are in Waterfront?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront has 10 homes in 1 tower registered on MahaRERA.

When was Waterfront registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Waterfront was registered on MahaRERA on 20 December 2017. GharKundli did not find a title report on the land on file there.

Does Waterfront have any legal issues or court cases?

No court cases are listed for Waterfront on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Waterfront?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SATYENDRA SURESH VAIDYA.

Other projects in Chiplun (415605)

All 170 projects in Chiplun (415605) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.