HORIZONE VIEW IX
by NASIR ABDUL REHMAN KHOT · Near Shree Datta Agency, Ratnagiri
Possession date of HORIZONE VIEW IX: 30 April 2027, moved from 30 November 2023 (37 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800034378, and currently active. Its completion date has moved from November 2023 to April 2027: 37 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about HORIZONE VIEW IX?
How the possession date of HORIZONE VIEW IX has moved
30 November 2023
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA27012619582)
Reason the builder gave MahaRERA:
“I state that after the COVID-19 pandemic, I faced serious financial difficulties and internal challenges, due to which the project work had to be completely stopped. After overcoming these issues, I have now restarted the construction work…” Read the full reason
“I state that after the COVID-19 pandemic, I faced serious financial difficulties and internal challenges, due to which the project work had to be completely stopped. After overcoming these issues, I have now restarted the construction work and am sincerely working towards completing the remaining work within the next 10 months.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: HORIZONE VIEW IX’s extension records on MahaRERA (P52800034378), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on HORIZONE VIEW IX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800034378
- Status
- Registered and active
- Builder
- NASIR ABDUL REHMAN KHOT
- Location
- Near Shree Datta Agency, Ratnagiri · 415605
- Project type
- Residential / Group Housing
- Registered on
- 4 Apr 2022
- Completion date at registration
- November 2023
- Latest completion date
- April 2027
- Delay so far
- 37 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 29
- Sold or booked
- 52%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of HORIZONE VIEW IX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| HORIZON VIEW 09 | 100% | 100% | 50% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- HORIZON VIEW 09: covers 4 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on HORIZONE VIEW IX every month.
HORIZONE VIEW IX: buildings, flats and land, as filed on MahaRERA
- Buildings: HORIZON VIEW 09 (4 floors, 29 units)
- Car parking: 2 open
- Land: 1,280 sq m (about 0.3 acres) · sanctioned built-up 1,428 sq m
The builder’s record and reviews
Nasir Abdul Rehman Khot has 3 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 16 months late). No complaints on MahaRERA.
Read Google reviews of HORIZONE VIEW IX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
HORIZONE VIEW IX: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about HORIZONE VIEW IX
What is the possession date of HORIZONE VIEW IX?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HORIZONE VIEW IX in Near Shree Datta Agency, Ratnagiri is 30 April 2027 — 37 months later than 30 November 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for HORIZONE VIEW IX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date HORIZONE VIEW IX's builder has filed on MahaRERA, the official one, is 30 April 2027, already 37 months later than the 30 November 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of HORIZONE VIEW IX extended?
According to GharKundli's check of MahaRERA records (updated October 2026), HORIZONE VIEW IX's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "I state that after the COVID-19 pandemic, I faced serious financial difficulties and internal challenges, due to which the project work had to be completely stopped. After overcoming these issues, I have now restarted the construction work and am sincerely working towards completing the remaining work within the next 10 months.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of HORIZONE VIEW IX?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HORIZONE VIEW IX in Near Shree Datta Agency, Ratnagiri is P52800034378.
Is HORIZONE VIEW IX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HORIZONE VIEW IX is registered as P52800034378 and its status is "Registered and active".
What is the construction status of HORIZONE VIEW IX?
According to GharKundli's check of MahaRERA records (updated October 2026), HORIZONE VIEW IX's status on MahaRERA is "Registered and active". As filed by the builder, slab work on HORIZON VIEW 09 is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does HORIZONE VIEW IX have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is HORIZONE VIEW IX safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), HORIZONE VIEW IX is registered on MahaRERA as P52800034378, its completion date has moved 37 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if HORIZONE VIEW IX's possession date changes?
The latest dates are on HORIZONE VIEW IX's MahaRERA page (P52800034378). GharKundli's Kundli Watch sends a free WhatsApp update on HORIZONE VIEW IX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does HORIZONE VIEW IX have?
According to GharKundli's check of MahaRERA records (updated October 2026), HORIZONE VIEW IX has one building filed: HORIZON VIEW 09 with 4 floors and 29 units.
How much parking does HORIZONE VIEW IX have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 2 open car parking spaces for HORIZONE VIEW IX.
How big is the land of HORIZONE VIEW IX?
According to GharKundli's check of MahaRERA records (updated October 2026), HORIZONE VIEW IX stands on 1,280 sq m of land (about 0.3 acres), with 1,428 sq m of sanctioned built-up area.
What is the track record of HORIZONE VIEW IX's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Nasir Abdul Rehman Khot has 3 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 16 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of HORIZONE VIEW IX?
Google Maps has reviews of HORIZONE VIEW IX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is HORIZONE VIEW IX?
HORIZONE VIEW IX by NASIR ABDUL REHMAN KHOT is in Near Shree Datta Agency, Ratnagiri (pincode 415605), Maharashtra, and is registered on MahaRERA as P52800034378, per GharKundli's check of MahaRERA records.
How many homes are in HORIZONE VIEW IX?
According to GharKundli's check of MahaRERA records (updated October 2026), HORIZONE VIEW IX has 29 homes in 1 tower registered on MahaRERA, and 52% of them are sold or booked.
When was HORIZONE VIEW IX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), HORIZONE VIEW IX was registered on MahaRERA on 4 April 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on HORIZONE VIEW IX?
No court cases are listed for HORIZONE VIEW IX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of HORIZONE VIEW IX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NASIR ABDUL REHMAN KHOT.
Check it yourself on MahaRERA
- How to check the possession date of HORIZONE VIEW IX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Ratnagiri →
Other projects in Chiplun
- SONAL LAXMI VILLAGE
- SHARDA ENCLAVE
- RAMCHANDRA PARK ‘D’ WING’
- SHREE SAMARTH SANKUL PHASE-2
- EVERGREEN TOWER
- APARANT PRIME
- CITY LANDMARK
- SHANTI APARTMENT
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.