Samartha Swayambhu Tirth

by Shree Samartha Construction · BKG Road, Sindhudurg 416602Also near Kankavli, Bijali Nagar, Ambe AliRegistered on MahaRERA as “Swayambhu Tirth”

What’s in the report? →

Possession date of Samartha Swayambhu Tirth (MahaRERA P52900005123): 31 July 2019, and it has already passed. It has 22 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52900005123. Status: In abeyance (on hold by MahaRERA).

Source: MahaRERA website — records for P52900005123, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2019) has passed.

What do you want to know about Samartha Swayambhu Tirth?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Samartha Swayambhu Tirth

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900005123
Status
In abeyance (on hold by MahaRERA)
Builder
Shree Samartha Construction
Location
BKG Road, Sindhudurg · 416602
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
July 2019
Homes
22
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Samartha Swayambhu Tirth, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sawayambhu Tirth0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Samartha Swayambhu Tirth every 1–2 months.

Samartha Swayambhu Tirth: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Samartha Swayambhu Tirth →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Samartha Swayambhu Tirth: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Samartha Swayambhu Tirth

What is the possession date of Samartha Swayambhu Tirth?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Samartha Swayambhu Tirth in BKG Road, Sindhudurg is 31 July 2019. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Samartha Swayambhu Tirth?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Samartha Swayambhu Tirth's builder has filed on MahaRERA, the official one, is 31 July 2019, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Samartha Swayambhu Tirth?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Samartha Swayambhu Tirth in BKG Road, Sindhudurg is P52900005123.

Is Samartha Swayambhu Tirth registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Samartha Swayambhu Tirth is registered as P52900005123 and its status is "In abeyance (on hold by MahaRERA)".

What is the current construction status of Samartha Swayambhu Tirth? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Samartha Swayambhu Tirth's status on MahaRERA is "In abeyance (on hold by MahaRERA)". As filed by the builder, slab work on Sawayambhu Tirth is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Samartha Swayambhu Tirth have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Samartha Swayambhu Tirth safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Samartha Swayambhu Tirth is registered on MahaRERA as P52900005123, its MahaRERA status is "In abeyance (on hold by MahaRERA)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Samartha Swayambhu Tirth?

Samartha Swayambhu Tirth isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Samartha Swayambhu Tirth?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Samartha Swayambhu Tirth: gharkundli.com/tools/property-cost-calculator

Has Samartha Swayambhu Tirth received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Samartha Swayambhu Tirth isn't completed: its MahaRERA status is "In abeyance (on hold by MahaRERA)", with 31 July 2019 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Samartha Swayambhu Tirth uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Samartha Swayambhu Tirth was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Samartha Swayambhu Tirth's possession date changes?

The latest dates are on Samartha Swayambhu Tirth's MahaRERA page (P52900005123). GharKundli's Kundli Watch sends a free WhatsApp update on Samartha Swayambhu Tirth every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Samartha Swayambhu Tirth have?

According to GharKundli's check of MahaRERA records (updated November 2026), Samartha Swayambhu Tirth has one building filed: Sawayambhu Tirth with 6 floors.

How big is the land of Samartha Swayambhu Tirth?

According to GharKundli's check of MahaRERA records (updated November 2026), Samartha Swayambhu Tirth stands on 830 sq m of land (about 0.2 acres), with 990 sq m of sanctioned built-up area and 90 sq m of recreational open space.

What are the reviews of Samartha Swayambhu Tirth?

Google Maps has reviews of Samartha Swayambhu Tirth written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Samartha Swayambhu Tirth?

Samartha Swayambhu Tirth by Shree Samartha Construction is in BKG Road, Sindhudurg, pincode 416602 (near Kankavli, Bijali Nagar, Ambe Ali), Maharashtra, and is registered on MahaRERA as P52900005123, per GharKundli's check of MahaRERA records. Its land is filed as 159 A - 37,40,45,49 and 231A - 93. GharKundli lists all 73 MahaRERA projects in Kankavli (416602).

How many flats are in Samartha Swayambhu Tirth?

According to GharKundli's check of MahaRERA records (updated November 2026), Samartha Swayambhu Tirth has 22 homes in 1 tower registered on MahaRERA.

When was Samartha Swayambhu Tirth registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Samartha Swayambhu Tirth was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Does Samartha Swayambhu Tirth have any legal issues or court cases?

No court cases are listed for Samartha Swayambhu Tirth on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Samartha Swayambhu Tirth?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shree Samartha Construction.

Other projects in Kankavli

All 73 projects in Kankavli (416602) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.