Shree Krishnaleela Apartment
by ISHWARDAS SAKHARAM KUBAL · Gavanpada, Sindhudurg 416606Also near Malvan
What’s in the report? →Possession date of Shree Krishnaleela Apartment (MahaRERA P52900011582): 12 May 2022, moved from 31 December 2018 (41 months later), and it has already passed. It has 9 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900011582. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52900011582, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (May 2022) has passed.
What do you want to know about Shree Krishnaleela Apartment?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shree Krishnaleela Apartment has moved
31 December 2018
Completion date given when the project was registered
12 May 2021
Extended at the builder's request (MahaRERA application EXT52900005693)
Reason the builder gave MahaRERA:
“Due to road work by municipal council the access road to the site was closed hence material could not reach on site. Further due to market slow down there is no sale of flats leading to shortage of cash flow thereby leading to delay in cons…” Read the full reason
“Due to road work by municipal council the access road to the site was closed hence material could not reach on site. Further due to market slow down there is no sale of flats leading to shortage of cash flow thereby leading to delay in construction activity of the building. However we request you to grant us an extension and we assure you that the work will be completed within the new proposed completion date.”12 May 2022
Revised completion date on MahaRERA
Source: Shree Krishnaleela Apartment’s extension records on MahaRERA (P52900011582), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shree Krishnaleela Apartment
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900011582
- Status
- Lapsed (registration period ended)
- Builder
- ISHWARDAS SAKHARAM KUBAL
- Location
- Gavanpada, Sindhudurg · 416606
- Project type
- Residential / Group Housing
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2018
- Latest completion date
- May 2022
- Delay so far
- 41 months
- Homes
- 9
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shree Krishnaleela Apartment, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE KRISHNALEELA APARTMENT | 100% | 80% | 15% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Krishnaleela Apartment every 1–2 months.
Shree Krishnaleela Apartment: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE KRISHNALEELA APARTMENT (4 floors)
- Land: 415 sq m (about 0.1 acres) · sanctioned built-up 414 sq m
- Land, as filed: 523 HISSA 8B
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shree Krishnaleela Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shree Krishnaleela Apartment: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shree Krishnaleela Apartment
What is the possession date of Shree Krishnaleela Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shree Krishnaleela Apartment in Gavanpada, Sindhudurg is 12 May 2022 — 41 months later than 31 December 2018, the date given at registration. That date has already passed.
The date has already moved 41 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Shree Krishnaleela Apartment?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Krishnaleela Apartment's builder has filed on MahaRERA, the official one, is 12 May 2022, already 41 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shree Krishnaleela Apartment extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment's builder applied to MahaRERA to extend the completion date once: to 12 May 2021, giving the reason "Due to road work by municipal council the access road to the site was closed hence material could not reach on site. Further due to market slow down there is no sale of flats leading to shortage of cash flow thereby leading to delay in construction activity of the building. However we request you to grant us an extension and we assure you that the work will be completed within the new proposed completion date.".
What is the RERA number of Shree Krishnaleela Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shree Krishnaleela Apartment in Gavanpada, Sindhudurg is P52900011582.
Is Shree Krishnaleela Apartment registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment is registered as P52900011582 and its status is "Lapsed (registration period ended)".
What is the current construction status of Shree Krishnaleela Apartment? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREE KRISHNALEELA APARTMENT is 80% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.
Does Shree Krishnaleela Apartment have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Shree Krishnaleela Apartment safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment is registered on MahaRERA as P52900011582, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 41 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shree Krishnaleela Apartment?
Shree Krishnaleela Apartment isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Shree Krishnaleela Apartment?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shree Krishnaleela Apartment: gharkundli.com/tools/property-cost-calculator
Has Shree Krishnaleela Apartment received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 12 May 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Shree Krishnaleela Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (12 May 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Shree Krishnaleela Apartment uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Shree Krishnaleela Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shree Krishnaleela Apartment's possession date changes?
The latest dates are on Shree Krishnaleela Apartment's MahaRERA page (P52900011582). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Krishnaleela Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shree Krishnaleela Apartment have?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment has one building filed: SHREE KRISHNALEELA APARTMENT with 4 floors.
How big is the land of Shree Krishnaleela Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment stands on 415 sq m of land (about 0.1 acres), with 414 sq m of sanctioned built-up area.
What are the reviews of Shree Krishnaleela Apartment?
Google Maps has reviews of Shree Krishnaleela Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shree Krishnaleela Apartment?
Shree Krishnaleela Apartment by ISHWARDAS SAKHARAM KUBAL is in Gavanpada, Sindhudurg, pincode 416606 (near Malvan), Maharashtra, and is registered on MahaRERA as P52900011582, per GharKundli's check of MahaRERA records. Its land is filed as 523 HISSA 8B. GharKundli lists all 32 MahaRERA projects in Malvan (416606).
How many flats are in Shree Krishnaleela Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment has 9 homes in 1 tower registered on MahaRERA.
When was Shree Krishnaleela Apartment registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Shree Krishnaleela Apartment was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Does Shree Krishnaleela Apartment have any legal issues or court cases?
No court cases are listed for Shree Krishnaleela Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Shree Krishnaleela Apartment?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ISHWARDAS SAKHARAM KUBAL.
Check it yourself on MahaRERA
- How to check the possession date of Shree Krishnaleela Apartment
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Malwan
- Shivsrushti
- Dattatray Residency
- Ayaans Ambary
- Horizon Grande Wing K
- Athang Ganga
- Sunsmit Vedic Village
- Athang Laxmi
- Sea Meridian
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.