by Infinity Buildcon · Malvan, Sindhudurg

Possession date of Takshashila: 1 April 2025, moved from 25 December 2021 (40 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52900014542. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (April 2025) has passed.

What do you want to know about Takshashila?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Takshashila has moved

  1. 25 December 2021

    Completion date given when the project was registered

  2. 1 April 2025

    Extended at the builder's request (MahaRERA application EXT52900016494)

    Reason the builder gave MahaRERA:
    “Due to COVID 19 Sindhudurg was declared in Red Zone and was not Possible to work as labors where outsourced from outside. Hence Site was Closed for the Period of 14 Months. Wing B and Wing C is already completed and occupance certificate da…” Read the full reason“Due to COVID 19 Sindhudurg was declared in Red Zone and was not Possible to work as labors where outsourced from outside. Hence Site was Closed for the Period of 14 Months. Wing B and Wing C is already completed and occupance certificate dated 24/05/2019 from Tehsildar, Malvan and both wings are ready for possession but till date we are able to sell only 2 Units in Wing C only. We are unable to get more bookings due to market condition. Due to financial crunch and to complete remaining work of Wing A (zero sold inventory) we have applied for extension of project.”

Source: Takshashila’s extension records on MahaRERA (P52900014542), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Takshashila

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52900014542
Status
Lapsed (registration period ended)
Builder
Infinity Buildcon
Location
Malvan, Sindhudurg · 416606
Project type
Residential / Group Housing
Registered on
12 Dec 2017
Completion date at registration
December 2021
Latest completion date
April 2025
Delay so far
40 months
Homes
102
Towers
3
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Takshashila, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Takshashila C100%100%100%95%
Takshashila B0%100%100%100%
Tashashila A0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Takshashila every month.

Takshashila: buildings, flats and land, as filed on MahaRERA

  • Buildings: Takshashila C (6 floors) · Takshashila B (4 floors) · Tashashila A (4 floors)
  • Land: 4,000 sq m (about 1.0 acres) · sanctioned built-up 3,921 sq m · recreational space 400 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Takshashila →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Takshashila: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Takshashila

What is the possession date of Takshashila?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Takshashila in Malvan, Sindhudurg is 1 April 2025 — 40 months later than 25 December 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Takshashila?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Takshashila's builder has filed on MahaRERA, the official one, is 1 April 2025, already 40 months later than the 25 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Takshashila extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Takshashila's builder applied to MahaRERA to extend the completion date once: to 1 April 2025, giving the reason "Due to COVID 19 Sindhudurg was declared in Red Zone and was not Possible to work as labors where outsourced from outside. Hence Site was Closed for the Period of 14 Months. Wing B and Wing C is already completed and occupance certificate dated 24/05/2019 from Tehsildar, Malvan and both wings are ready for possession but till date we are able to sell only 2 Units in Wing C only. We are unable to get more bookings due to market condition. Due to financial crunch and to complete remaining work of Wing A (zero sold inventory) we have applied for extension of project.".

What is the RERA number of Takshashila?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Takshashila in Malvan, Sindhudurg is P52900014542.

Is Takshashila registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Takshashila is registered as P52900014542 and its status is "Lapsed (registration period ended)".

What is the construction status of Takshashila?

According to GharKundli's check of MahaRERA records (updated November 2026), Takshashila's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Takshashila have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Takshashila safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Takshashila is registered on MahaRERA as P52900014542, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 40 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Takshashila's possession date changes?

The latest dates are on Takshashila's MahaRERA page (P52900014542). GharKundli's Kundli Watch sends a free WhatsApp update on Takshashila every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Takshashila have?

According to GharKundli's check of MahaRERA records (updated November 2026), Takshashila has 3 buildings filed: Takshashila C with 6 floors; Takshashila B with 4 floors; Tashashila A with 4 floors.

How big is the land of Takshashila?

According to GharKundli's check of MahaRERA records (updated November 2026), Takshashila stands on 4,000 sq m of land (about 1.0 acres), with 3,921 sq m of sanctioned built-up area and 400 sq m of recreational open space.

Where can I read reviews of Takshashila?

Google Maps has reviews of Takshashila written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Takshashila?

Takshashila by Infinity Buildcon is in Malvan, Sindhudurg (pincode 416606), Maharashtra, and is registered on MahaRERA as P52900014542, per GharKundli's check of MahaRERA records.

How many homes are in Takshashila?

According to GharKundli's check of MahaRERA records (updated November 2026), Takshashila has 102 homes in 3 towers registered on MahaRERA.

When was Takshashila registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Takshashila was registered on MahaRERA on 12 December 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Takshashila?

No court cases are listed for Takshashila on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Takshashila?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Infinity Buildcon, which has 4 other projects registered on MahaRERA.