MANERI RESIDENCY
by Natasha Dcosta · Patankar Park, Sindhudurg
Possession: MANERI RESIDENCY is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900013413. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about MANERI RESIDENCY?
How the possession date of MANERI RESIDENCY has moved
15 June 2023
Completion date given when the project was registered
14 June 2024
Extended at the builder's request (MahaRERA application EXT52900016804)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, During our registration for RERA, date of completion as mentioned in the certificate is 15/06/2023. But at present, having completed about 70 % of the work, we are temporarily out of India. We have not taken any booking…” Read the full reason
“Respected Sir/Madam, During our registration for RERA, date of completion as mentioned in the certificate is 15/06/2023. But at present, having completed about 70 % of the work, we are temporarily out of India. We have not taken any bookings until this date, and are completing the project at our own cost and therefore we request for an extension to be considered.”
Source: MANERI RESIDENCY’s extension records on MahaRERA (P52900013413), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MANERI RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900013413
- Status
- Completed
- Builder
- Natasha Dcosta
- Location
- Patankar Park, Sindhudurg · 416512
- Project type
- Residential / Group Housing
- Registered on
- 5 Oct 2017
- Completion date at registration
- June 2023
- Latest completion date
- June 2024
- Delay so far
- 12 months
- Homes
- 8
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MANERI RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MANERI RESIDENCY | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANERI RESIDENCY every month.
MANERI RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: MANERI RESIDENCY (4 floors)
- Land: 560 sq m (about 0.1 acres) · sanctioned built-up 546 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MANERI RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MANERI RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MANERI RESIDENCY
What is the possession date of MANERI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MANERI RESIDENCY in Patankar Park, Sindhudurg is 14 June 2024 — 12 months later than 15 June 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for MANERI RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MANERI RESIDENCY's builder has filed on MahaRERA, the official one, is 14 June 2024, already 12 months later than the 15 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MANERI RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), MANERI RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 14 June 2024, giving the reason "Respected Sir/Madam, During our registration for RERA, date of completion as mentioned in the certificate is 15/06/2023. But at present, having completed about 70 % of the work, we are temporarily out of India. We have not taken any bookings until this date, and are completing the project at our own cost and therefore we request for an extension to be considered.".
What is the RERA number of MANERI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MANERI RESIDENCY in Patankar Park, Sindhudurg is P52900013413.
Is MANERI RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MANERI RESIDENCY is registered as P52900013413 and its status is "Completed".
What is the construction status of MANERI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MANERI RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on MANERI RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MANERI RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is MANERI RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MANERI RESIDENCY is registered on MahaRERA as P52900013413, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MANERI RESIDENCY's possession date changes?
The latest dates are on MANERI RESIDENCY's MahaRERA page (P52900013413). GharKundli's Kundli Watch sends a free WhatsApp update on MANERI RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MANERI RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), MANERI RESIDENCY has one building filed: MANERI RESIDENCY with 4 floors.
How big is the land of MANERI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MANERI RESIDENCY stands on 560 sq m of land (about 0.1 acres), with 546 sq m of sanctioned built-up area.
Where can I read reviews of MANERI RESIDENCY?
Google Maps has reviews of MANERI RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MANERI RESIDENCY?
MANERI RESIDENCY by Natasha Dcosta is in Patankar Park, Sindhudurg (pincode 416512), Maharashtra, and is registered on MahaRERA as P52900013413, per GharKundli's check of MahaRERA records.
How many homes are in MANERI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), MANERI RESIDENCY has 8 homes in 1 tower registered on MahaRERA.
When was MANERI RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MANERI RESIDENCY was registered on MahaRERA on 5 October 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MANERI RESIDENCY?
No court cases are listed for MANERI RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of MANERI RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Natasha Dcosta.
Check it yourself on MahaRERA
- How to check the possession date of MANERI RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dodamarg
- VEENAS DREAM HOME
- HADIKARS APPAJI PLAZA
- YOG ANAND
- SATERI TOWERS
- BLISS AQUA
- ALTURA
- AXIS BLUES
- AXIS YOG VILLAS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.