Diksha Park Phase 4
by Sudhir Dashrath Jadhav · Janavli, Sindhudurg 416602Also near Bijali Nagar, Ambe Ali
What’s in the report? →Possession: Diksha Park Phase 4 (MahaRERA P52900019394) is marked completed on MahaRERA. It has 32 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52900019394. Status: Completed.
Source: MahaRERA website — records for P52900019394, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Diksha Park Phase 4?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Diksha Park Phase 4
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52900019394
- Status
- Completed
- Builder
- Sudhir Dashrath Jadhav
- Location
- Janavli, Sindhudurg · 416602
- Project type
- Residential / Group Housing
- Registered on
- 29 Jan 2019
- Completion date at registration
- March 2022
- Latest completion date
- March 2022
- Homes
- 32
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Diksha Park Phase 4, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Diksha Park Phase 4 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Diksha Park Phase 4 every 1–2 months.
Diksha Park Phase 4: buildings, flats and land, as filed on MahaRERA
- Buildings: Diksha Park Phase 4 (4 floors)
- Land: 3,300 sq m (about 0.8 acres) · sanctioned built-up 1,775 sq m · recreational space 238 sq m
- Land, as filed: 3012
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Diksha Park Phase 4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Diksha Park Phase 4: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Diksha Park Phase 4
What is the possession date of Diksha Park Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Diksha Park Phase 4 in Janavli, Sindhudurg is 26 March 2022.
Is the builder's possession date different from the MahaRERA date for Diksha Park Phase 4?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Diksha Park Phase 4's builder has filed on MahaRERA, the official one, is 26 March 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Diksha Park Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Diksha Park Phase 4 in Janavli, Sindhudurg is P52900019394.
Is Diksha Park Phase 4 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 is registered as P52900019394 and its status is "Completed".
What is the current construction status of Diksha Park Phase 4? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4's status on MahaRERA is "Completed". As filed by the builder, slab work on Diksha Park Phase 4 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Diksha Park Phase 4 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Diksha Park Phase 4 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 is registered on MahaRERA as P52900019394, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Diksha Park Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Diksha Park Phase 4?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Diksha Park Phase 4: gharkundli.com/tools/property-cost-calculator
Has Diksha Park Phase 4 received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Diksha Park Phase 4 completed?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 is marked completed on MahaRERA, and the completion date filed there is 26 March 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Has Diksha Park Phase 4 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Diksha Park Phase 4 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Diksha Park Phase 4's possession date changes?
The latest dates are on Diksha Park Phase 4's MahaRERA page (P52900019394). GharKundli's Kundli Watch sends a free WhatsApp update on Diksha Park Phase 4 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Diksha Park Phase 4 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 has one building filed: Diksha Park Phase 4 with 4 floors.
How big is the land of Diksha Park Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 stands on 3,300 sq m of land (about 0.8 acres), with 1,775 sq m of sanctioned built-up area and 238 sq m of recreational open space.
What are the reviews of Diksha Park Phase 4?
Google Maps has reviews of Diksha Park Phase 4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Diksha Park Phase 4?
Diksha Park Phase 4 by Sudhir Dashrath Jadhav is in Janavli, Sindhudurg, pincode 416602 (near Bijali Nagar, Ambe Ali), Maharashtra, and is registered on MahaRERA as P52900019394, per GharKundli's check of MahaRERA records. Its land is filed as 3012. GharKundli lists all 73 MahaRERA projects in Kankavli (416602).
How many flats are in Diksha Park Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 has 32 homes in 1 tower registered on MahaRERA.
When was Diksha Park Phase 4 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Diksha Park Phase 4 was registered on MahaRERA on 29 January 2019. GharKundli did not find a title report on the land on file there.
Does Diksha Park Phase 4 have any legal issues or court cases?
No court cases are listed for Diksha Park Phase 4 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Diksha Park Phase 4?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sudhir Dashrath Jadhav.
Check it yourself on MahaRERA
- How to check the possession date of Diksha Park Phase 4
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kankavli (416602)
- Anant Pride
- Kamat Vishwa - 2
- Shree Sadan
- Raj & SV Homes
- Royal Enclave
- Maitri Garden
- Adinath Residency
- Galaxy Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.