The Midtwon
by Sanjay Lakhmichand Gangwani · Sangli
Possession: The Midtwon is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P53100001824. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about The Midtwon?
How the possession date of The Midtwon has moved
30 June 2018
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT53100002490)
Reason the builder gave MahaRERA: “revised sanction and part completion of the project was obtained on Dtd. 05/07/2018”
31 August 2022
Extended at the builder's request (MahaRERA application EXT53100012311)
Reason the builder gave MahaRERA:
“Total Midtown Building Is completed having builtup area 2227.82 Sq.Mtr and allowable Builtup area is 2639 Sq.mtr. We have obtained completion certificate on 19/07/2021. we have increased builtup area as per the FSI in same project so the pr…” Read the full reason
“Total Midtown Building Is completed having builtup area 2227.82 Sq.Mtr and allowable Builtup area is 2639 Sq.mtr. We have obtained completion certificate on 19/07/2021. we have increased builtup area as per the FSI in same project so the proposed completion date is extended. The project completion date increased due to additional builtup area consumed as per permissible area .”
Source: The Midtwon’s extension records on MahaRERA (P53100001824), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Midtwon
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P53100001824
- Status
- Completed
- Builder
- Sanjay Lakhmichand Gangwani
- Location
- Sangli · 416416
- Project type
- Others
- Registered on
- 29 Jul 2017
- Completion date at registration
- June 2018
- Latest completion date
- August 2022
- Delay so far
- 50 months
- Homes
- 60
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of The Midtwon, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| The MIdtown | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Midtwon every month.
The Midtwon: buildings, flats and land, as filed on MahaRERA
- Buildings: The MIdtown (7 floors)
- Land: 1,300 sq m (about 0.3 acres) · sanctioned built-up 2,228 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of The Midtwon →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Midtwon: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about The Midtwon
What is the possession date of The Midtwon?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Midtwon in Sangli is 31 August 2022 — 50 months later than 30 June 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for The Midtwon?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Midtwon's builder has filed on MahaRERA, the official one, is 31 August 2022, already 50 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Midtwon extended?
According to GharKundli's check of MahaRERA records (updated November 2026), The Midtwon's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2020, giving the reason "revised sanction and part completion of the project was obtained on Dtd. 05/07/2018"; to 31 August 2022, giving the reason "Total Midtown Building Is completed having builtup area 2227.82 Sq.Mtr and allowable Builtup area is 2639 Sq.mtr. We have obtained completion certificate on 19/07/2021. we have increased builtup area as per the FSI in same project so the proposed completion date is extended. The project completion date increased due to additional builtup area consumed as per permissible area .".
What is the RERA number of The Midtwon?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Midtwon in Sangli is P53100001824.
Is The Midtwon registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Midtwon is registered as P53100001824 and its status is "Completed".
What is the construction status of The Midtwon?
According to GharKundli's check of MahaRERA records (updated November 2026), The Midtwon's status on MahaRERA is "Completed". As filed by the builder, slab work on The MIdtown is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does The Midtwon have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is The Midtwon safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), The Midtwon is registered on MahaRERA as P53100001824, its MahaRERA status is "Completed", its completion date has moved 50 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if The Midtwon's possession date changes?
The latest dates are on The Midtwon's MahaRERA page (P53100001824). GharKundli's Kundli Watch sends a free WhatsApp update on The Midtwon every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Midtwon have?
According to GharKundli's check of MahaRERA records (updated November 2026), The Midtwon has one building filed: The MIdtown with 7 floors.
How big is the land of The Midtwon?
According to GharKundli's check of MahaRERA records (updated November 2026), The Midtwon stands on 1,300 sq m of land (about 0.3 acres), with 2,228 sq m of sanctioned built-up area.
Where can I read reviews of The Midtwon?
Google Maps has reviews of The Midtwon written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is The Midtwon?
The Midtwon by Sanjay Lakhmichand Gangwani is in Sangli (pincode 416416), Maharashtra, and is registered on MahaRERA as P53100001824, per GharKundli's check of MahaRERA records.
How many homes are in The Midtwon?
According to GharKundli's check of MahaRERA records (updated November 2026), The Midtwon has 60 homes in 1 tower registered on MahaRERA.
When was The Midtwon registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Midtwon was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on The Midtwon?
No court cases are listed for The Midtwon on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of The Midtwon?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sanjay Lakhmichand Gangwani.
Check it yourself on MahaRERA
- How to check the possession date of The Midtwon
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 416416
All 127 projects in Sangli (416416) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.