The Willows Phase 1

by ORIGIN REALTORS LLP (Ravi) · Gaurav Valley, Thane 401107Also near Mira Road East, Village Ghodbunder, Vinay Nagar

What’s in the report? →

Possession date of The Willows Phase 1 (MahaRERA P51700027028): 31 December 2027, moved from 30 June 2022 (66 months later). It has 18 homes, 56% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700027028, and currently active.

Source: MahaRERA website — records for P51700027028, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about The Willows Phase 1?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of The Willows Phase 1 has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51700012558)

    Reason the builder gave MahaRERA: “The work is only partly left for completion”
  3. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700027687)

    Reason the builder gave MahaRERA:
    “1. The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. The Parliamentary General election – 2024 & Maharashtra Assembly election - 2024 caused the halt to construction…” Read the full reason“1. The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. The Parliamentary General election – 2024 & Maharashtra Assembly election - 2024 caused the halt to construction activities due to the absence of Staff. 3. The promoter was not able to procure the skilled labour for the construction due to unfavourable labour market, whereby the labour migrated to their home state to exercise their electoral franchise. 4. Sales figures have been consistently lower than expected, impacting the revenue needed to fund ongoing construc…”
  4. 31 December 2027

    Extended at the builder's request (MahaRERA application EA14042620635)

    Reason the builder gave MahaRERA:
    “1. The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous and illegal. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unav…” Read the full reason“1. The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous and illegal. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unavoidable delay in the construction and completion of the project. 2. The Promoter has suffered severe financial constraints on account of adverse and unforeseen economic conditions prevailing in the Indian real estate sector which have materially affected the execution of the project. 3.The overall slowdown in the real estate market, coupled with shortage…”

Source: The Willows Phase 1’s extension records on MahaRERA (P51700027028), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Willows Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700027028
Status
Registered and active
Builder
ORIGIN REALTORS LLP
Location
Gaurav Valley, Thane · 401107
Project type
Residential / Group Housing
Registered on
10 Nov 2020
Completion date at registration
June 2022
Latest completion date
December 2027
Delay so far
66 months
Homes
18
Sold or booked
56%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of The Willows Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
The Willows100%100%41%0%

Commencement certificate (CC), as filed on MahaRERA

  • The Willows: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Willows Phase 1 every 1–2 months.

The Willows Phase 1: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 4 finished, all within the promised date; 16 still being built, 9 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects.

Read Google reviews of The Willows Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Willows Phase 1: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about The Willows Phase 1

What is the possession date of The Willows Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Willows Phase 1 in Gaurav Valley, Thane is 31 December 2027 — 66 months later than 30 June 2022, the date given at registration.

The date has already moved 66 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for The Willows Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Willows Phase 1's builder has filed on MahaRERA, the official one, is 31 December 2027, already 66 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The Willows Phase 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2024, giving the reason "The work is only partly left for completion"; to 31 December 2025, giving the reason "1. The promoter has suffered from financial difficulties due to adverse economic condition in the Indian Real Estate Market. 2. The Parliamentary General election – 2024 & Maharashtra Assembly election - 2024 caused the halt to construction activities due to the absence of Staff. 3. The promoter was not able to procure the skilled labour for the construction due to unfavourable labour market, whereby the labour migrated to their home state to exercise their electoral franchise. 4. Sales figures have been consistently lower than expected, impacting the revenue needed to fund ongoing construc…"; to 31 December 2027, giving the reason "1. The Commencement Certificate (CC) granted in respect of the project was subsequently found to be erroneous and illegal. Consequently, all projects undertaken by Ravi Developments were restrained from proceeding further, resulting in unavoidable delay in the construction and completion of the project. 2. The Promoter has suffered severe financial constraints on account of adverse and unforeseen economic conditions prevailing in the Indian real estate sector which have materially affected the execution of the project. 3.The overall slowdown in the real estate market, coupled with shortage…".

What is the RERA number of The Willows Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Willows Phase 1 in Gaurav Valley, Thane is P51700027028.

Is The Willows Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1 is registered as P51700027028 and its status is "Registered and active".

What is the current construction status of The Willows Phase 1? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on The Willows is 100% done and internal work 41%. GharKundli's full report compares construction progress with the deadline.

Does The Willows Phase 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is The Willows Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1 is registered on MahaRERA as P51700027028, its completion date has moved 66 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in The Willows Phase 1?

The Willows Phase 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in The Willows Phase 1?

For a flat in The Willows Phase 1 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has The Willows Phase 1 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1 is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has The Willows Phase 1 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for The Willows Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if The Willows Phase 1's possession date changes?

The latest dates are on The Willows Phase 1's MahaRERA page (P51700027028). GharKundli's Kundli Watch sends a free WhatsApp update on The Willows Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Willows Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1 has one building filed: The Willows with 4 floors and 18 units.

How much parking does The Willows Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for The Willows Phase 1.

How big is the land of The Willows Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1 stands on 1,150 sq m of land (about 0.3 acres), with 808 sq m of sanctioned built-up area and 185 sq m of recreational open space.

What is the track record of The Willows Phase 1's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Ravi Developments (a group of 9 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 4 finished, all within the promised date; 16 still being built, 9 past the promised date (typically 22 months late); 5 lapsed. 181 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.

What are the reviews of The Willows Phase 1?

Google Maps has reviews of The Willows Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of The Willows Phase 1?

The Willows Phase 1 by ORIGIN REALTORS LLP (Ravi) is in Gaurav Valley, Thane, pincode 401107 (near Mira Road East, Village Ghodbunder, Vinay Nagar), Maharashtra, and is registered on MahaRERA as P51700027028, per GharKundli's check of MahaRERA records. Its land is filed as 27/5/6/7. GharKundli lists all 323 MahaRERA projects in Mira Road East (401107).

How many flats are in The Willows Phase 1, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1 has 18 homes in 1 tower registered on MahaRERA, and 56% of them are sold or booked.

When was The Willows Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Willows Phase 1 was registered on MahaRERA on 10 November 2020. GharKundli did not find a title report on the land on file there.

Does The Willows Phase 1 have any legal issues or court cases?

No court cases are listed for The Willows Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of The Willows Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ORIGIN REALTORS LLP, the company Ravi files this project under.

All projects with possession due in 2027 in Thane →