ANANDVAN

by MILESTONE BUILDERS · near arya hotel wanlesswadi, SangliAlso near Miraj, District Court Sangli

Possession date of ANANDVAN: 28 June 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P53100053274, and currently active. Its completion date is now June 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about ANANDVAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ANANDVAN has moved

  1. 28 February 2027

    Completion date given when the project was registered

  2. 28 June 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ANANDVAN’s extension records on MahaRERA (P53100053274), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ANANDVAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P53100053274
Status
Registered and active
Builder
MILESTONE BUILDERS
Location
near arya hotel wanlesswadi, Sangli · 416414
Project type
Residential / Group Housing
Registered on
23 Oct 2023
Completion date at registration
February 2027
Latest completion date
June 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
58
Sold or booked
41%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of ANANDVAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RESIDENTIAL BUILDING AND ROW HOUSES A AND B100%100%75%0%

Commencement certificate (CC), as filed on MahaRERA

  • RESIDENTIAL BUILDING AND ROW HOUSES A AND B: covers BASEMENT+GF+8

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANANDVAN every month.

ANANDVAN: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of ANANDVAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ANANDVAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ANANDVAN

What is the possession date of ANANDVAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for ANANDVAN in near arya hotel wanlesswadi, Sangli is 28 June 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ANANDVAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ANANDVAN's builder has filed on MahaRERA, the official one, is 28 June 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of ANANDVAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of ANANDVAN in near arya hotel wanlesswadi, Sangli is P53100053274.

Is ANANDVAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ANANDVAN is registered as P53100053274 and its status is "Registered and active".

What is the construction status of ANANDVAN?

According to GharKundli's check of MahaRERA records (updated November 2026), ANANDVAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RESIDENTIAL BUILDING AND ROW HOUSES A AND B is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does ANANDVAN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is ANANDVAN safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), ANANDVAN is registered on MahaRERA as P53100053274, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if ANANDVAN's possession date changes?

The latest dates are on ANANDVAN's MahaRERA page (P53100053274). GharKundli's Kundli Watch sends a free WhatsApp update on ANANDVAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ANANDVAN have?

According to GharKundli's check of MahaRERA records (updated November 2026), ANANDVAN has one building filed: RESIDENTIAL BUILDING AND ROW HOUSES A AND B with 10 floors and 58 units.

How big is the land of ANANDVAN?

According to GharKundli's check of MahaRERA records (updated November 2026), ANANDVAN stands on 2,324 sq m of land (about 0.6 acres), with 4,406 sq m of sanctioned built-up area.

Where can I read reviews of ANANDVAN?

Google Maps has reviews of ANANDVAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ANANDVAN?

ANANDVAN by MILESTONE BUILDERS is in near arya hotel wanlesswadi, Sangli (pincode 416414), near Miraj, District Court Sangli, Maharashtra, and is registered on MahaRERA as P53100053274, per GharKundli's check of MahaRERA records.

How many homes are in ANANDVAN?

According to GharKundli's check of MahaRERA records (updated November 2026), ANANDVAN has 58 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.

When was ANANDVAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), ANANDVAN was registered on MahaRERA on 23 October 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on ANANDVAN?

No court cases are listed for ANANDVAN on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of ANANDVAN?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MILESTONE BUILDERS.

All projects with possession due in 2027 in Sangli →

Other projects in Miraj

All 11 projects in District Court Sangli (416414) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.