Aristone Enviro Affinity

by Aristone Developers · Gaurav City, Thane 401107Also near Bhayander WestRegistered on MahaRERA as “ENVIRO AFFINITY”

What’s in the report? →

Possession date of Aristone Enviro Affinity (MahaRERA P51700028265): 31 December 2028, moved from 30 June 2025 (42 months later). It has 141 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700028265, and currently active.

Source: MahaRERA website — records for P51700028265, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Aristone Enviro Affinity?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Aristone Enviro Affinity has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA11072502052)

    Reason the builder gave MahaRERA:
    “The project experienced a change in the layout plan consequently, additional time was required to prepare and submit the revised layout for approval. The process of obtaining approval from the competent authority involved multiple stages of…” Read the full reason“The project experienced a change in the layout plan consequently, additional time was required to prepare and submit the revised layout for approval. The process of obtaining approval from the competent authority involved multiple stages of review and compliance, which contributed to the delay.”

Source: Aristone Enviro Affinity’s extension records on MahaRERA (P51700028265), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Aristone Enviro Affinity

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700028265
Status
Registered and active
Builder
Aristone Developers
Location
Gaurav City, Thane · 401107
Project type
Residential / Group Housing
Registered on
18 Feb 2021
Completion date at registration
June 2025
Latest completion date
December 2028
Delay so far
42 months
Homes
141
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Aristone Enviro Affinity, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ENVIRO AFFINITY100%33.33%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • ENVIRO AFFINITY: covers 24 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Aristone Enviro Affinity every 1–2 months.

Aristone Enviro Affinity: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Aristone Developers has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 8 months late). No complaints on MahaRERA.

Read Google reviews of Aristone Enviro Affinity →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Aristone Enviro Affinity: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Aristone Enviro Affinity

What is the possession date of Aristone Enviro Affinity?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Aristone Enviro Affinity in Gaurav City, Thane is 31 December 2028 — 42 months later than 30 June 2025, the date given at registration.

The date has already moved 42 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Aristone Enviro Affinity?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Aristone Enviro Affinity's builder has filed on MahaRERA, the official one, is 31 December 2028, already 42 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Aristone Enviro Affinity extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "The project experienced a change in the layout plan consequently, additional time was required to prepare and submit the revised layout for approval. The process of obtaining approval from the competent authority involved multiple stages of review and compliance, which contributed to the delay.".

What is the RERA number of Aristone Enviro Affinity?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Aristone Enviro Affinity in Gaurav City, Thane is P51700028265.

Is Aristone Enviro Affinity registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity is registered as P51700028265 and its status is "Registered and active".

What is the current construction status of Aristone Enviro Affinity? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ENVIRO AFFINITY is 33.33% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Aristone Enviro Affinity have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Aristone Enviro Affinity safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity is registered on MahaRERA as P51700028265, its completion date has moved 42 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Aristone Enviro Affinity?

Aristone Enviro Affinity is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Aristone Enviro Affinity?

For a flat in Aristone Enviro Affinity (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Aristone Enviro Affinity received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity is still under construction, with 31 December 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Aristone Enviro Affinity uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Aristone Enviro Affinity was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Aristone Enviro Affinity's possession date changes?

The latest dates are on Aristone Enviro Affinity's MahaRERA page (P51700028265). GharKundli's Kundli Watch sends a free WhatsApp update on Aristone Enviro Affinity every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Aristone Enviro Affinity have?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity has one building filed: ENVIRO AFFINITY with 24 floors and 161 units.

How big is the land of Aristone Enviro Affinity?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity stands on 475 sq m of land (about 0.1 acres), with 6,818 sq m of sanctioned built-up area.

What is the track record of Aristone Enviro Affinity's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Developers has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 8 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Aristone Enviro Affinity?

Google Maps has reviews of Aristone Enviro Affinity written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Aristone Enviro Affinity?

Aristone Enviro Affinity by Aristone Developers is in Gaurav City, Thane, pincode 401107 (near Bhayander West), Maharashtra, and is registered on MahaRERA as P51700028265, per GharKundli's check of MahaRERA records. Its land is filed as S NO 429 1 AND 430 PT. GharKundli lists all 323 MahaRERA projects in Mira Road East (401107).

How many flats are in Aristone Enviro Affinity, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity has 141 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Aristone Enviro Affinity registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Aristone Enviro Affinity was registered on MahaRERA on 18 February 2021. GharKundli did not find a title report on the land on file there.

Does Aristone Enviro Affinity have any legal issues or court cases?

No court cases are listed for Aristone Enviro Affinity on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Aristone Enviro Affinity?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aristone Developers, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Thane

All 323 projects in Mira Road East (401107) →

Other projects by Aristone Developers

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.