Excellent Shreeji Palazzo
by Excellent Enterprise · Sion, Mumbai 400022Also near Bandra East, Dharavi, VidyanagariRegistered on MahaRERA as “Shreeji Palazzo”
What’s in the report? →Possession date of Excellent Shreeji Palazzo (MahaRERA P51900055071): 30 April 2027, moved from 31 December 2025 (12 months later). It has 22 homes (1 BHK, 2 BHK and 3 BHK, 504–1204 sq ft carpet), 0% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900055071, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51900055071, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Excellent Shreeji Palazzo?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Excellent Shreeji Palazzo has moved
31 December 2025
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA23062501717)
Reason the builder gave MahaRERA:
“We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstan…” Read the full reason
“We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. It may be noted that we have not sold a single unit to any allottee. All the units in the project are unsold. As per the Chartered Accountant Certificate as on 31.03.2025, applicant has expended Rs. 10,42,07,642/- on the project from its own sources. The total amount expended on this project including own and owed fu…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Excellent Shreeji Palazzo’s extension records on MahaRERA (P51900055071), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Excellent Shreeji Palazzo
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900055071
- Status
- Registered and active
- Builder
- Excellent Enterprise
- Location
- Sion, Mumbai · 400022
- Project type
- Others
- Registered on
- 29 Feb 2024
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 22
- Sold or booked
- 0%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Excellent Shreeji Palazzo, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shreeji Palazzo | 100% | 100% | 90% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Shreeji Palazzo: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Excellent Shreeji Palazzo every 1–2 months.
Excellent Shreeji Palazzo: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 504 – 547 | 14 |
| 2 BHK | 661 | 6 |
| 3 BHK | 1,204 | 2 |
| Shops | 1,056 | 1 |
- Buildings: Shreeji Palazzo (19 floors, 23 units)
- Land: 452 sq m (about 0.1 acres) · sanctioned built-up 1,558 sq m
- Land, as filed: 421/6
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Excellent Shreeji Palazzo →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Excellent Shreeji Palazzo: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Excellent Shreeji Palazzo
What is the possession date of Excellent Shreeji Palazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Excellent Shreeji Palazzo in Sion, Mumbai is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Excellent Shreeji Palazzo?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Excellent Shreeji Palazzo's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Excellent Shreeji Palazzo extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. It may be noted that we have not sold a single unit to any allottee. All the units in the project are unsold. As per the Chartered Accountant Certificate as on 31.03.2025, applicant has expended Rs. 10,42,07,642/- on the project from its own sources. The total amount expended on this project including own and owed fu…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Excellent Shreeji Palazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Excellent Shreeji Palazzo in Sion, Mumbai is P51900055071.
Is Excellent Shreeji Palazzo registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo is registered as P51900055071 and its status is "Registered and active".
What is the current construction status of Excellent Shreeji Palazzo? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shreeji Palazzo is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Excellent Shreeji Palazzo have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Excellent Shreeji Palazzo safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo is registered on MahaRERA as P51900055071, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Excellent Shreeji Palazzo?
Excellent Shreeji Palazzo is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Excellent Shreeji Palazzo are 504 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Excellent Shreeji Palazzo?
For a flat in Excellent Shreeji Palazzo (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Excellent Shreeji Palazzo received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Excellent Shreeji Palazzo a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo is a redevelopment: 13 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Excellent Shreeji Palazzo uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Excellent Shreeji Palazzo was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Excellent Shreeji Palazzo's possession date changes?
The latest dates are on Excellent Shreeji Palazzo's MahaRERA page (P51900055071). GharKundli's Kundli Watch sends a free WhatsApp update on Excellent Shreeji Palazzo every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Excellent Shreeji Palazzo have?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo has one building filed: Shreeji Palazzo with 19 floors and 23 units.
What are the flat sizes (carpet area) in Excellent Shreeji Palazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Excellent Shreeji Palazzo: 1 BHK: 504 to 547 sq ft carpet (14 homes); 2 BHK: 661 sq ft carpet (6 homes); 3 BHK: 1204 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Excellent Shreeji Palazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo stands on 452 sq m of land (about 0.1 acres), with 1,558 sq m of sanctioned built-up area.
What are the reviews of Excellent Shreeji Palazzo?
Google Maps has reviews of Excellent Shreeji Palazzo written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Excellent Shreeji Palazzo?
Excellent Shreeji Palazzo by Excellent Enterprise is in Sion, Mumbai, pincode 400022 (near Bandra East, Dharavi, Vidyanagari), Maharashtra, and is registered on MahaRERA as P51900055071, per GharKundli's check of MahaRERA records. Its land is filed as 421/6. GharKundli lists all 98 MahaRERA projects in Sion (400022).
How many flats are in Excellent Shreeji Palazzo, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo has 22 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.
When was Excellent Shreeji Palazzo registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Excellent Shreeji Palazzo was registered on MahaRERA on 29 February 2024. GharKundli did not find a title report on the land on file there.
Does Excellent Shreeji Palazzo have any legal issues or court cases?
No court cases are listed for Excellent Shreeji Palazzo on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Excellent Shreeji Palazzo?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Excellent Enterprise.
Check it yourself on MahaRERA
- How to check the possession date of Excellent Shreeji Palazzo
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai City →
Other projects in Sion (400022)
- DNS Anuutham
- Kings Hill View
- Dosti Mezzo 22
- Privia Navkar
- Dhanishtha
- Shankesh Crown
- Seaplaza
- Shankheshwar Heights
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.