Shree Nath Niwas

by M/s. Gaurang Properties Pvt Ltd · Naupada, Thane

Possession date of Shree Nath Niwas: 30 April 2024. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700027462. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (April 2024) has passed.

What do you want to know about Shree Nath Niwas?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Shree Nath Niwas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700027462
Status
Lapsed (registration period ended)
Builder
M/s. Gaurang Properties Pvt Ltd
Location
Naupada, Thane · 400602
Project type
Residential / Group Housing
Registered on
11 Dec 2020
Completion date at registration
April 2024
Latest completion date
April 2024
Homes
13
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of Shree Nath Niwas, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shree Nath Niwas0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Nath Niwas every month.

Shree Nath Niwas: buildings, flats and land, as filed on MahaRERA

  • Buildings: Shree Nath Niwas (9 floors)
  • Land: 472 sq m (about 0.1 acres) · sanctioned built-up 542 sq m
  • Boundaries filed include: Vatvruksha Society, Anmol Society

The builder’s record and reviews

Gaurang Properties has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 82 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of Shree Nath Niwas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shree Nath Niwas: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shree Nath Niwas

What is the possession date of Shree Nath Niwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shree Nath Niwas in Naupada, Thane is 30 April 2024. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Shree Nath Niwas?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Nath Niwas's builder has filed on MahaRERA, the official one, is 30 April 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shree Nath Niwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shree Nath Niwas in Naupada, Thane is P51700027462.

Is Shree Nath Niwas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nath Niwas is registered as P51700027462 and its status is "Lapsed (registration period ended)".

What is the construction status of Shree Nath Niwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nath Niwas's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shree Nath Niwas is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shree Nath Niwas have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Shree Nath Niwas safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nath Niwas is registered on MahaRERA as P51700027462, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Shree Nath Niwas's possession date changes?

The latest dates are on Shree Nath Niwas's MahaRERA page (P51700027462). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Nath Niwas every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shree Nath Niwas have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nath Niwas has one building filed: Shree Nath Niwas with 9 floors.

How big is the land of Shree Nath Niwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nath Niwas stands on 472 sq m of land (about 0.1 acres), with 542 sq m of sanctioned built-up area.

What is the track record of Shree Nath Niwas's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Gaurang Properties has 4 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 82 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Shree Nath Niwas?

Google Maps has reviews of Shree Nath Niwas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shree Nath Niwas?

Shree Nath Niwas by M/s. Gaurang Properties Pvt Ltd is in Naupada, Thane (pincode 400602), Maharashtra, and is registered on MahaRERA as P51700027462, per GharKundli's check of MahaRERA records. Its boundaries filed there include Vatvruksha Society, Anmol Society.

How many homes are in Shree Nath Niwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nath Niwas has 13 homes in 1 tower registered on MahaRERA.

When was Shree Nath Niwas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shree Nath Niwas was registered on MahaRERA on 11 December 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Shree Nath Niwas?

No court cases are listed for Shree Nath Niwas on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Shree Nath Niwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is M/s. Gaurang Properties Pvt Ltd.

Other projects in pincode 400602

All 258 projects in Naupada (400602) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.