SHREE ANAND
by SHREE ADESHWAR HOMES · Bhayander East, Thane
Possession: SHREE ANAND is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700028020. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SHREE ANAND?
How the possession date of SHREE ANAND has moved
30 June 2025
Completion date given when the project was registered
29 June 2026
Extended at the builder's request (MahaRERA application EA31072502272)
Reason the builder gave MahaRERA: “Building work has been completed 100% but the work for Rotary Car Parking is under progress. Hence OC is awaited.”
28 June 2027
Extended at the builder's request (MahaRERA application EA24062621510)
Reason the builder gave MahaRERA: “Building work has been completed 100% but the work for Rotary Car Parking is under progress and PERT chart uploaded below. Hence OC is awaited.”
Source: SHREE ANAND’s extension records on MahaRERA (P51700028020), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHREE ANAND
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700028020
- Status
- Completed
- Builder
- SHREE ADESHWAR HOMES
- Location
- Bhayander East, Thane · 401105
- Project type
- Residential / Group Housing
- Registered on
- 26 Jan 2021
- Completion date at registration
- June 2025
- Latest completion date
- June 2027
- Delay so far
- 24 months
- Homes
- 68
- Sold or booked
- 95%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHREE ANAND, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE ANAND | 100% | 100% | 100% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- SHREE ANAND: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE ANAND every month.
SHREE ANAND: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE ANAND (15 floors, 80 units)
- Car parking: 32 covered
- Land: 1,470 sq m (about 0.4 acres) · sanctioned built-up 4,978 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHREE ANAND →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREE ANAND: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREE ANAND
What is the possession date of SHREE ANAND?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHREE ANAND in Bhayander East, Thane is 28 June 2027 — 24 months later than 30 June 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SHREE ANAND?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE ANAND's builder has filed on MahaRERA, the official one, is 28 June 2027, already 24 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHREE ANAND extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE ANAND's builder applied to MahaRERA to extend the completion date 2 times: to 29 June 2026, giving the reason "Building work has been completed 100% but the work for Rotary Car Parking is under progress. Hence OC is awaited."; to 28 June 2027, giving the reason "Building work has been completed 100% but the work for Rotary Car Parking is under progress and PERT chart uploaded below. Hence OC is awaited.".
What is the RERA number of SHREE ANAND?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHREE ANAND in Bhayander East, Thane is P51700028020.
Is SHREE ANAND registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE ANAND is registered as P51700028020 and its status is "Completed".
What is the construction status of SHREE ANAND?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE ANAND's status on MahaRERA is "Completed". As filed by the builder, slab work on SHREE ANAND is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does SHREE ANAND have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is SHREE ANAND safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE ANAND is registered on MahaRERA as P51700028020, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREE ANAND's possession date changes?
The latest dates are on SHREE ANAND's MahaRERA page (P51700028020). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE ANAND every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREE ANAND have?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE ANAND has one building filed: SHREE ANAND with 15 floors and 80 units.
How much parking does SHREE ANAND have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 32 covered car parking spaces for SHREE ANAND.
How big is the land of SHREE ANAND?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE ANAND stands on 1,470 sq m of land (about 0.4 acres), with 4,978 sq m of sanctioned built-up area.
Where can I read reviews of SHREE ANAND?
Google Maps has reviews of SHREE ANAND written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREE ANAND?
SHREE ANAND by SHREE ADESHWAR HOMES is in Bhayander East, Thane (pincode 401105), Maharashtra, and is registered on MahaRERA as P51700028020, per GharKundli's check of MahaRERA records.
How many homes are in SHREE ANAND?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE ANAND has 68 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.
When was SHREE ANAND registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SHREE ANAND was registered on MahaRERA on 26 January 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREE ANAND?
No court cases are listed for SHREE ANAND on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SHREE ANAND?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE ADESHWAR HOMES.
Check it yourself on MahaRERA
- How to check the possession date of SHREE ANAND
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401105
- SAI Plaza
- N G GRAND EMPIRE PHASE II
- VIHANG LUXURIA
- SHREEJI ANGARIKA
- ELANZA WING A
- OSTWAL AKAASHA
- SWASTIK SKY
- Mini Market
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.