VIHANG LUXURIA

by REYANSHP REALTY LLP (Vihang) · Mire Village, Thane

Possession date of VIHANG LUXURIA: 31 December 2031, moved from 31 December 2027 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700049126, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about VIHANG LUXURIA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VIHANG LUXURIA has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    Extended at the builder's request

  3. 31 December 2031

    Extended at the builder's request (MahaRERA application EA23092638974)

    Reason the builder gave MahaRERA:
    “We have added new CC for using available FSI.. and the building 2A which was existing as parking building is now changed as commercial building of G+30 floor. we will not able to complete the said building specifically 2A till April 2028 as…” Read the full reason“We have added new CC for using available FSI.. and the building 2A which was existing as parking building is now changed as commercial building of G+30 floor. we will not able to complete the said building specifically 2A till April 2028 as per present completion date. so for FSA with allottees of 2A we need to change the completion date till Dec 2031.so we need to extend the project completion date”

Source: VIHANG LUXURIA’s extension records on MahaRERA (P51700049126), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VIHANG LUXURIA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 court case, and how it ended
  • Construction pace against the December 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700049126
Status
Registered and active
Builder
REYANSHP REALTY LLP
Location
Mire Village, Thane · 401105
Project type
Others
Registered on
1 Feb 2023
Completion date at registration
December 2027
Latest completion date
December 2031
Delay so far
48 months
Homes
530
Sold or booked
53%
Towers
4
Complaints on MahaRERA
0
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of VIHANG LUXURIA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Reyansh Ventura Building no 1100%100%100%100%
Reyansh Ventura Building no 2 / Ventura Building no. 2100%35%0%0%
Reyansh Ventura Building no 2 / Ventura Building No. 2A0%0%0%0%
Luxuria / Building 3A and Building 3B100%85%40%0%

Commencement certificate (CC), as filed on MahaRERA

  • Reyansh Ventura Building no 1: covers G+6
  • Reyansh Ventura Building no 2: covers G+31
  • Luxuria: covers G + 39
  • Reyansh Ventura Building no 2: covers G+30

Latest CC order on MahaRERA: dated 06/07/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VIHANG LUXURIA every month.

VIHANG LUXURIA: buildings, flats and land, as filed on MahaRERA

  • Buildings: Reyansh Ventura Building no 1 (7 floors, 7 units) · Reyansh Ventura Building no 2 (32 floors, 207 units) · Luxuria (40 floors, 530 units) · Reyansh Ventura Building no 2 (31 floors, 404 units)
  • Car parking: 1,476 covered
  • Land: 12,340 sq m (about 3.0 acres) · sanctioned built-up 82,361 sq m · recreational space 1,478 sq m
  • Boundaries filed include: 12 METR ROAD SHASHWAT BUILDING

The builder’s record and reviews

Vihang Enterprises (a group of 4 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 3 finished, all within the promised date; 13 still being built, none past the promised date yet; 2 lapsed. 59 complaints on MahaRERA across 5 projects.

Read Google reviews of VIHANG LUXURIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VIHANG LUXURIA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VIHANG LUXURIA

What is the possession date of VIHANG LUXURIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VIHANG LUXURIA in Mire Village, Thane is 31 December 2031 — 48 months later than 31 December 2027, the date given at registration.

Is the builder's possession date different from the MahaRERA date for VIHANG LUXURIA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VIHANG LUXURIA's builder has filed on MahaRERA, the official one, is 31 December 2031, already 48 months later than the 31 December 2027 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VIHANG LUXURIA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), VIHANG LUXURIA's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2028; to 31 December 2031, giving the reason "We have added new CC for using available FSI.. and the building 2A which was existing as parking building is now changed as commercial building of G+30 floor. we will not able to complete the said building specifically 2A till April 2028 as per present completion date. so for FSA with allottees of 2A we need to change the completion date till Dec 2031.so we need to extend the project completion date".

What is the RERA number of VIHANG LUXURIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VIHANG LUXURIA in Mire Village, Thane is P51700049126.

Is VIHANG LUXURIA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIHANG LUXURIA is registered as P51700049126 and its status is "Registered and active".

What is the construction status of VIHANG LUXURIA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIHANG LUXURIA's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does VIHANG LUXURIA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is VIHANG LUXURIA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), VIHANG LUXURIA is registered on MahaRERA as P51700049126, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VIHANG LUXURIA's possession date changes?

The latest dates are on VIHANG LUXURIA's MahaRERA page (P51700049126). GharKundli's Kundli Watch sends a free WhatsApp update on VIHANG LUXURIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VIHANG LUXURIA have?

According to GharKundli's check of MahaRERA records (updated October 2026), VIHANG LUXURIA has 4 buildings filed: Reyansh Ventura Building no 1 with 7 floors and 7 units; Reyansh Ventura Building no 2 with 32 floors and 207 units; Luxuria with 40 floors and 530 units; Reyansh Ventura Building no 2 with 31 floors and 404 units.

How much parking does VIHANG LUXURIA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1,476 covered car parking spaces for VIHANG LUXURIA.

How big is the land of VIHANG LUXURIA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIHANG LUXURIA stands on 12,340 sq m of land (about 3.0 acres), with 82,361 sq m of sanctioned built-up area and 1,478 sq m of recreational open space.

What is the track record of VIHANG LUXURIA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vihang Enterprises (a group of 4 linked companies) has 18 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 3 finished, all within the promised date; 13 still being built, none past the promised date yet; 2 lapsed. 59 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of VIHANG LUXURIA?

Google Maps has reviews of VIHANG LUXURIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VIHANG LUXURIA?

VIHANG LUXURIA by REYANSHP REALTY LLP (Vihang) is in Mire Village, Thane (pincode 401105), Maharashtra, and is registered on MahaRERA as P51700049126, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 METR ROAD SHASHWAT BUILDING.

How many homes are in VIHANG LUXURIA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIHANG LUXURIA has 530 homes in 4 towers registered on MahaRERA, and 53% of them are sold or booked.

When was VIHANG LUXURIA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), VIHANG LUXURIA was registered on MahaRERA on 1 February 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on VIHANG LUXURIA?

1 court case is listed for VIHANG LUXURIA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of VIHANG LUXURIA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is REYANSHP REALTY LLP, the company Vihang files this project under, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2031 in Palghar →

Other projects in Thane

All 99 projects in Bhayander East (401105) →

Other projects by REYANSHP REALTY LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.