Mahavir Breeze Phase 1
by Damji Shamji Realty Pvt. Ltd. (Vinayak) · Kasarvadavali, Thane 400615Also near Owale, Kavesar, Near Kanchan Pushpa
What’s in the report? →Possession date of Mahavir Breeze Phase 1 (MahaRERA P51700030915): 30 April 2032, moved from 31 December 2024 (84 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700030915, and currently active. Its completion date has moved from December 2024 to April 2032: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700030915, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Mahavir Breeze Phase 1?
1 court case MahaRERA par listed. Kya jaanna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Mahavir Breeze Phase 1 has moved
31 December 2024
Completion date given when the project was registered
31 December 2031
Extended at the builder's request (MahaRERA application EA10072621712)
Reason the builder gave MahaRERA:
“One of the affected promoters Sheth Developers, approached the Hon'ble Bombay High Court, which, after reviewing all relevant facts, directed the TMC to process their applications for further approvals. As our matter was similar to that of…” Read the full reason
“One of the affected promoters Sheth Developers, approached the Hon'ble Bombay High Court, which, after reviewing all relevant facts, directed the TMC to process their applications for further approvals. As our matter was similar to that of Sheth Developers, we also filed a Writ Petition No. 11698 in the year 2025 against the TMC in the Hon'ble Bombay High Court and relied upon the order passed in the matter of Sheth Developers. The Bombay High Court by its order dated 23 September 2025 directed the TMC to process our application for the grant of development permissions with the terms of the…”30 April 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Mahavir Breeze Phase 1’s extension records on MahaRERA (P51700030915), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mahavir Breeze Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 court case, and how it ended
- Construction pace against the April 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700030915
- Status
- Registered and active
- Builder
- Damji Shamji Realty Pvt. Ltd.
- Location
- Kasarvadavali, Thane · 400615
- Project type
- Others
- Registered on
- 29 Sep 2021
- Completion date at registration
- December 2024
- Latest completion date
- April 2032
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 43%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 1
- Title report on file
- Not found
Construction progress of Mahavir Breeze Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Mahavir Breeze Phase 1 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Mahavir Breeze Phase 1: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mahavir Breeze Phase 1 every 1–2 months.
Mahavir Breeze Phase 1: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| Office Space | 30 – 350 | 4 |
| Shops | 103 – 122 | 3 |
- Buildings: Mahavir Breeze Phase 1 (3 floors, 7 units)
- Land: 499 sq m (about 0.1 acres) · sanctioned built-up 1,082 sq m
- Land, as filed: 86/1A 2 3A 3C 84/1A 2 1C 1E 1F 4C 4B 1Z 1D 87/1B 3 4A 1D 4D 87 4D 86/3B 77/1 86/3/2
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Vinayak Developers (a group of 11 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 22 months); 14 still being built, 5 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 7 projects.
Read Google reviews of Mahavir Breeze Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mahavir Breeze Phase 1: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Mahavir Breeze Phase 1
What is the possession date of Mahavir Breeze Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mahavir Breeze Phase 1 in Kasarvadavali, Thane is 30 April 2032 — 84 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 84 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Mahavir Breeze Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mahavir Breeze Phase 1's builder has filed on MahaRERA, the official one, is 30 April 2032, already 84 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mahavir Breeze Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "One of the affected promoters Sheth Developers, approached the Hon'ble Bombay High Court, which, after reviewing all relevant facts, directed the TMC to process their applications for further approvals. As our matter was similar to that of Sheth Developers, we also filed a Writ Petition No. 11698 in the year 2025 against the TMC in the Hon'ble Bombay High Court and relied upon the order passed in the matter of Sheth Developers. The Bombay High Court by its order dated 23 September 2025 directed the TMC to process our application for the grant of development permissions with the terms of the…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Mahavir Breeze Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mahavir Breeze Phase 1 in Kasarvadavali, Thane is P51700030915.
Is Mahavir Breeze Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1 is registered as P51700030915 and its status is "Registered and active".
What is the current construction status of Mahavir Breeze Phase 1? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Mahavir Breeze Phase 1 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Mahavir Breeze Phase 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Mahavir Breeze Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1 is registered on MahaRERA as P51700030915, its completion date has moved 84 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Mahavir Breeze Phase 1?
Mahavir Breeze Phase 1 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Mahavir Breeze Phase 1?
For a flat in Mahavir Breeze Phase 1 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Mahavir Breeze Phase 1 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1 is still under construction, with 30 April 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Mahavir Breeze Phase 1 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mahavir Breeze Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Mahavir Breeze Phase 1's possession date changes?
The latest dates are on Mahavir Breeze Phase 1's MahaRERA page (P51700030915). GharKundli's Kundli Watch sends a free WhatsApp update on Mahavir Breeze Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mahavir Breeze Phase 1 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1 has one building filed: Mahavir Breeze Phase 1 with 3 floors and 7 units.
How big is the land of Mahavir Breeze Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1 stands on 499 sq m of land (about 0.1 acres), with 1,082 sq m of sanctioned built-up area.
What is the track record of Mahavir Breeze Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Developers (a group of 11 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 22 months); 14 still being built, 5 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Mahavir Breeze Phase 1?
Google Maps has reviews of Mahavir Breeze Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Mahavir Breeze Phase 1?
Mahavir Breeze Phase 1 by Damji Shamji Realty Pvt. Ltd. (Vinayak) is in Kasarvadavali, Thane, pincode 400615 (near Owale, Kavesar, Near Kanchan Pushpa), Maharashtra, and is registered on MahaRERA as P51700030915, per GharKundli's check of MahaRERA records. Its land is filed as 86/1A 2 3A 3C 84/1A 2 1C 1E 1F 4C 4B 1Z 1D 87/1B 3 4A 1D 4D 87 4D 86/3B 77/1 86/3/2. GharKundli lists all 158 MahaRERA projects in Kasarvadavali (400615).
How many flats are in Mahavir Breeze Phase 1, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1 has 0 homes in 1 tower registered on MahaRERA, and 43% of them are sold or booked.
When was Mahavir Breeze Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mahavir Breeze Phase 1 was registered on MahaRERA on 29 September 2021. GharKundli did not find a title report on the land on file there.
Does Mahavir Breeze Phase 1 have any legal issues or court cases?
1 court case is listed for Mahavir Breeze Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
A court case can stall a project or tie up the land. See what the case is about →
Who is the builder / developer of Mahavir Breeze Phase 1?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Damji Shamji Realty Pvt. Ltd., the company Vinayak files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Mahavir Breeze Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kasarvadavali (400615)
All 158 projects in Kasarvadavali (400615) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.