MahaRERA projects in Kasarvadavali, Thane (400615)

According to GharKundli's check of MahaRERA records, 126 housing projects are registered in pincode 400615 (Kasarvadavali, Thane). 61 are still being built, 19 with possession due by the end of 2027. For 80, the completion date on MahaRERA is later than the one first promised. 63 have at least one complaint filed on MahaRERA.

Pincode 400615 also covers: Owale, Kasarvadavli, Kavesar, Mogharpada, Owala, Bhaynderpada.

“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.

ProjectMahaRERA statusPossession due (MahaRERA)First promisedComplaints
LARKINS NEST
PRIDE PROPERTY DEVELOPERS
Active30 Oct 2026passed31 Dec 20250
Vihang Plaza - A Commecial
VIHANG ENTERPRISES
Active30 Dec 2026same0
HORIZON EXOTICA
K M REALTY
Active31 Dec 202630 Dec 20250
HORIZON PALMS - III
KM DEVELOPERS
Active31 Dec 202630 Dec 20240
PARKWOODS D5
Aniline Construction Company Private Limited
Active31 Dec 202630 Mar 202619
Sankheshwar Plaza
VNG Enterprises
Active31 Dec 2026same0
ACE ARISTO
GAURAV LAND CORPORATION
Active28 Feb 202731 Oct 20260
Tokyo Bay Phase - 2C
Puranik Tokyo Bay Private Limited
De-registered28 Feb 2027same2
Cascade Avenue Bellagio
Aarsh Construction
Active30 Apr 202731 Dec 20260
COSMOS ENCLAVE BLDG-JASMINE
MONARCH DEVELOPERS
Active30 Apr 202731 Dec 20260
METRO HIVE D-1
VIHANG INFRASTRUCTURE PVT LTD
Active30 Apr 202730 Dec 20260
NOVA D-1
VIHANG ENTERPRISES
Active30 Apr 202731 Dec 20260
SIDDHIVINAYAK
SHREEASHTAVINAYAK ENTERPRISES
Active30 Apr 202731 Dec 20260
vihang woods
VIHANG ENTERPRISES
Active30 Apr 202730 Dec 20261
HORIZON PEARL
KM DEVELOPERS
Active30 Aug 202730 Apr 20270
Snehkiran Tower
SNEHKIRAN BUILDCON PRIVATE LIMITED
Active30 Sep 202730 May 20270
KAVYA PARK
SHREE CONSTRUCTION COMPANY
Active30 Oct 202730 Jun 202110
RAUNAK 108
UNNATHI ASSOCIATES
Active30 Oct 202730 Jun 20266
NIYATI LAKE CROWN
SHREE SWAMI SAMARTH ENTERPRISES
Active31 Dec 2027same1
HORIZON PALMS IV
KM DEVELOPERS
Active30 Apr 202831 Dec 20270
Intelligentia Segment by Haware Properties
Suresh Kashinath Haware
Active30 Apr 202831 Dec 20271
PSK SKYLAR
Gururaj Developers
Active30 Apr 202830 Dec 20235
LAKESCAPE
LAKE SCAPE
Active30 Dec 2028same1
Parkwoods D6
Aniline Construction Company Private Limited
Active31 Dec 2028same0
PUSHPANJALI RESIDENCY PHASE III
SHRIRAAM PIONEER DEVELOPERS PRIVATE LIMITED
Abeyance31 Dec 2028same1
Tropical Bliss
AMAATRA TROPICAL BUILDWELL PVT. LTD.
Active30 Jan 202930 Sep 20281
Horizon Pearl II
KM Developers
Active30 Apr 202931 Dec 20280
Puraniks Unicorn Phase 1
Puranik Builders Limited
Active30 Apr 202931 Dec 20282
PURUSHOTTAMNAYAN
GAURAV ENTERPRISES
Active30 Apr 202930 Dec 20221
Rumah Bali Phase 4
Puranik Builders Limited
Active30 Apr 202931 Dec 20283
Puranik City Reserva Phase 1
Puranik Builders Limited
Active30 Jul 202930 Mar 202919
Ace Parkside
AARTI ESTATES
Active30 Apr 203031 Dec 20290
EVANA D-2
VIHANG INFRASTRUCTURE PVT LTD
Active30 Apr 203031 Dec 20290
Puraniks Unicorn Phase 2
Puranik Builders Limited
Active30 Apr 203031 Dec 20291
RAUNAK BLISS - B1
UNNATHI ASSOCIATES
Active30 Apr 203030 Dec 20290
RAUNAK BLISS - B2
UNNATHI ASSOCIATES
Active30 Apr 203030 Dec 20290
RAUNAK BLISS A4
UNNATHI ASSOCIATES
Active30 Apr 203031 Dec 20292
RAUNAK BLISS B2
UNNATHI ASSOCIATES
Active30 Apr 203031 Dec 20290
RAUNAK BLISS B3
UNNATHI ASSOCIATES
Active30 Apr 203031 Dec 20297
ROSA SEPHORA
AAKASH DARSHAN BUILDCORP LLP
Active30 Apr 203030 Jun 20280
VIHANG MARINA
BALAJI ENTERPRISES
Active30 Apr 203031 Dec 20290
DELTA GREENVILLE - CEDAR
DELTA SYNERGY LLP
Active31 Dec 2030same0
Haware Amber Hills
Haware's Housing Development Finance Corporation Ltd.
Active25 Apr 203125 Dec 20300
ELITA D3
VIHANG INFRASTRUCTURE PVT LTD
Active30 Apr 203131 Dec 20290
IKIGAI Phase 2
Puranik Tokyo Bay Private Limited
Active30 Apr 203131 Dec 20300
DELTA GREENVILLE - ASTER
DELTA SYNERGY LLP
Active31 May 203131 Jan 20310
SHREE NIDHI HEAVEN
Shree Nidhi Heaven
Active23 Aug 2031same0
AVATARA Phase 1
ANANT SQUARE
Active30 Sep 2031same0
NORTH IMPERIAL GREENS -TOWER 2
Skylark Buildspace Private Limited
Active31 Dec 2031same0
ELYSIA D-4
VIHANG INFRASTRUCTURE PVT LTD
Active30 Apr 203231 Dec 20310

76 more projects

  1. IKIGAI - Phase 1 · 30 Apr 2032
  2. Mahavir Breeze Phase 1 · 30 Apr 2032
  3. OPUS · 30 Sep 2032
  4. Rosa Manhattan Phase 3 · 30 Oct 2032
  5. Shree Siena · 30 Mar 2033
  6. Elyra by Puraniks · 30 Apr 2033
  7. NORTH IMPERIAL GREENS - TOWER 1 · 30 Apr 2033
  8. ORIS · 30 Apr 2033
  9. Rumah Bali Phase 5 · 30 Apr 2036
  10. Tokyo Bay Phase 2B · 30 Apr 2036
  11. Rumah Bali Phase 6 · 30 Oct 2036
  12. Rosa Oasis Phase 2 · completed
  13. DAHLIA BLDG A D AND E · completed
  14. PALACIA PHASE-II · completed
  15. Bhoomi Acres M wing · completed
  16. GARDEN COURT TYPE B2 · completed
  17. JVM FLORENCIA · completed
  18. SHANTAI · completed
  19. KIPL Morya · completed
  20. Surendra Villa · completed
  21. SHREE SAKET · completed
  22. Bhoomi Acres L wing · completed
  23. HORIZON CLASSIQUE-2 · completed
  24. Mahavir Estella - Wing E · completed
  25. FLORENCE · completed
  26. Platinum Tower · completed
  27. Anthurium · completed
  28. SUBODH · completed
  29. Ace Courtyard · completed
  30. ACE SQUARE PHASE 2 · completed
  31. UNNATHI WOODS PHASE VII-B · completed
  32. Shree Vaishnavi Heights · completed
  33. VEDA · completed
  34. Intelligentia Spectrum Thane by Haware Properties · completed
  35. RAUNAK BLISS PHASE A · completed
  36. Godrej Emerald Thane · completed
  37. RAUNAK BLISS PHASE A - A3 · completed
  38. Metropolis Bayside · completed
  39. AROMA · completed
  40. TIARA · completed
  41. Ace Enclave · completed
  42. UNNATHI WOODS PHASE VIII · completed
  43. KAVYA RESIDENCY · 30 Dec 2021
  44. ALEXA · 30 Mar 2023
  45. TROPICAL LAGOON - 5 - DI VITA · 31 Jul 2023
  46. GOLDEN HILLS B- 3 · 30 Dec 2024
  47. Mahavir Kalpavruksha Wing J Phase 2 · 30 Dec 2024
  48. Mahavir Kalpavruksha - J Wing · 21 Jan 2025
  49. Manhattan Phase 1 · 31 Mar 2025
  50. Tokyo Bay Phase - 2A · 31 May 2025
  51. Shree Partha · 31 Jul 2025
  52. COMMERCIAL BUILDING 10 · 30 Dec 2025
  53. Intelligentia Vector by Haware Properties · 30 Dec 2025
  54. WHITE HOUSE · 30 Dec 2025
  55. LAABH GLORIA · 31 Dec 2025
  56. PUSHPANJALI RESIDENCY PHASE III · 31 Dec 2025
  57. Manhattan Phase 2 · 31 Mar 2026
  58. Manan Heights - A Wing · 29 Apr 2026
  59. Metropolis - Insignia Towers · 14 Aug 2026
  60. Aarambh - C · —
  61. BHAKTI PEARL - C · —
  62. ELCANTO · —
  63. Mahavir Kalpavruksha - Oak, Tulip, Alcacia, Almond · —
  64. Puranik Home Town - E · —
  65. RAUNAK HEIGHTS · —
  66. Rumah Bali Phase 3 · —
  67. Rumahbali Phase 2 · —
  68. SATGURUS SOLITAIRE · —
  69. SHREE SANKALP · —
  70. SHREE SARVA · —
  71. Tokyo Bay Phase - 1 · —
  72. TRINITY HEIGHTS · —
  73. TROPICAL LAGOON - 4 -JACARANDA · —
  74. UNNATHI WOODS PHASE VI-F1 · —
  75. UNNATHI WOODS PHASE VII A · —
  76. VIHANGS VERMONT · —

Other areas in Thane

All areas in Thane →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.