Manhattan Phase 1

by SAI UMA CONSTRUCTION PRIVATE LIMITED · Patlipada, ThaneAlso near Kavesar, Borivali West

Possession date of Manhattan Phase 1: 31 March 2025, moved from 30 June 2022 (33 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700001707. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (March 2025) has passed.

What do you want to know about Manhattan Phase 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Manhattan Phase 1 has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51700011926)

    Reason the builder gave MahaRERA:
    “A small portion of the layout was originally sanctioned for development under the amenity buy back and development policy sanctioned by Thane Municipal Corporation. However, after the introduction of UDCPR 2020, the amenity buyback policy h…” Read the full reason“A small portion of the layout was originally sanctioned for development under the amenity buy back and development policy sanctioned by Thane Municipal Corporation. However, after the introduction of UDCPR 2020, the amenity buyback policy has been withdrawn and clarification in that regard has been issued by the government of Maharashtra after the lapse of almost a year. We have complied with the revised requirements and we are in a process of submitting revised plans. The construction of manhattan phase I is on the verge of completion. We are seeking an extension to avoid any possible brea…”
  3. 31 March 2024

    Extended at the builder's request (MahaRERA application EXT51700017077)

    Reason the builder gave MahaRERA:
    “As per the provisions of UDCPR 2020, construction amenity policy of Thane Municipal Corporation has been scrapped and the TMC had instructed us to revise the layout plan and to provide amenity space on open land. We have therefore purchased…” Read the full reason“As per the provisions of UDCPR 2020, construction amenity policy of Thane Municipal Corporation has been scrapped and the TMC had instructed us to revise the layout plan and to provide amenity space on open land. We have therefore purchased the land adjacent to the layout and submitted revised proposal. In the meanwhile, we have completed the construction of residential building known as Bronx and commercial building known as Fifth Avenue having shop no. 17 to 40, office no. 1 to 17 (Manhattan phase I). The Architect of the project has certified the status of the construction. The TMC has a…”
  4. 31 March 2025

    Extended at the builder's request (MahaRERA application EXT51700025419)

    Reason the builder gave MahaRERA:
    “The construction of the captioned project is complete in all respect, however, considering the amendment in the development control regulation after implementation of UDCPR, we are constrained to amend the layout and the building plan to pr…” Read the full reason“The construction of the captioned project is complete in all respect, however, considering the amendment in the development control regulation after implementation of UDCPR, we are constrained to amend the layout and the building plan to provide ground amenity instead of originally sanctioned constructed amenity to be provided to the Thane Municipal Corporation. In order to facilitate the required compliance, we had to purchase adjacent land and completely revise the upcoming phases in the complex known as ‘Manhattan’. 2. We have already completed construction of Phase I of the housing comp…”

Source: Manhattan Phase 1’s extension records on MahaRERA (P51700001707), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Manhattan Phase 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 7 court cases, and how it ended
  • Construction pace against the March 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700001707
Status
Lapsed (registration period ended)
Builder
SAI UMA CONSTRUCTION PRIVATE LIMITED
Location
Patlipada, Thane · 400615
Project type
Others
Registered on
29 Jul 2017
Completion date at registration
June 2022
Latest completion date
March 2025
Delay so far
33 months
Homes
186
Sold or booked
90%
Towers
2
Complaints on MahaRERA
1
Court cases listed
7
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Manhattan Phase 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BRONX100%100%100%100%
FIFTH AVENUE100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Manhattan Phase 1 every month.

Manhattan Phase 1: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Manhattan Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Manhattan Phase 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Manhattan Phase 1

What is the possession date of Manhattan Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Manhattan Phase 1 in Patlipada, Thane is 31 March 2025 — 33 months later than 30 June 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Manhattan Phase 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Manhattan Phase 1's builder has filed on MahaRERA, the official one, is 31 March 2025, already 33 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Manhattan Phase 1 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Phase 1's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2023, giving the reason "A small portion of the layout was originally sanctioned for development under the amenity buy back and development policy sanctioned by Thane Municipal Corporation. However, after the introduction of UDCPR 2020, the amenity buyback policy has been withdrawn and clarification in that regard has been issued by the government of Maharashtra after the lapse of almost a year. We have complied with the revised requirements and we are in a process of submitting revised plans. The construction of manhattan phase I is on the verge of completion. We are seeking an extension to avoid any possible brea…"; to 31 March 2024, giving the reason "As per the provisions of UDCPR 2020, construction amenity policy of Thane Municipal Corporation has been scrapped and the TMC had instructed us to revise the layout plan and to provide amenity space on open land. We have therefore purchased the land adjacent to the layout and submitted revised proposal. In the meanwhile, we have completed the construction of residential building known as Bronx and commercial building known as Fifth Avenue having shop no. 17 to 40, office no. 1 to 17 (Manhattan phase I). The Architect of the project has certified the status of the construction. The TMC has a…"; to 31 March 2025, giving the reason "The construction of the captioned project is complete in all respect, however, considering the amendment in the development control regulation after implementation of UDCPR, we are constrained to amend the layout and the building plan to provide ground amenity instead of originally sanctioned constructed amenity to be provided to the Thane Municipal Corporation. In order to facilitate the required compliance, we had to purchase adjacent land and completely revise the upcoming phases in the complex known as ‘Manhattan’. 2. We have already completed construction of Phase I of the housing comp…".

What is the RERA number of Manhattan Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Manhattan Phase 1 in Patlipada, Thane is P51700001707.

Is Manhattan Phase 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Phase 1 is registered as P51700001707 and its status is "Lapsed (registration period ended)".

What is the construction status of Manhattan Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Phase 1's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Manhattan Phase 1 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Manhattan Phase 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Phase 1 is registered on MahaRERA as P51700001707, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 33 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Manhattan Phase 1 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Manhattan Phase 2 (P51700013323, possession 31 Mar 2026). Check that your agreement names the registration of your own wing.

How can I get updates if Manhattan Phase 1's possession date changes?

The latest dates are on Manhattan Phase 1's MahaRERA page (P51700001707). GharKundli's Kundli Watch sends a free WhatsApp update on Manhattan Phase 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Manhattan Phase 1 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Phase 1 has 2 buildings filed: BRONX with 38 floors; FIFTH AVENUE with 3 floors.

How big is the land of Manhattan Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Phase 1 stands on 12,785 sq m of land (about 3.2 acres), with 21,292 sq m of sanctioned built-up area and 3,093 sq m of recreational open space.

Where can I read reviews of Manhattan Phase 1?

Google Maps has reviews of Manhattan Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Manhattan Phase 1?

Manhattan Phase 1 by SAI UMA CONSTRUCTION PRIVATE LIMITED is in Patlipada, Thane (pincode 400615), near Kavesar, Borivali West, Maharashtra, and is registered on MahaRERA as P51700001707, per GharKundli's check of MahaRERA records.

How many homes are in Manhattan Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Phase 1 has 186 homes in 2 towers registered on MahaRERA, and 90% of them are sold or booked.

When was Manhattan Phase 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Manhattan Phase 1 was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Manhattan Phase 1?

7 court cases are listed for Manhattan Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Manhattan Phase 1?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAI UMA CONSTRUCTION PRIVATE LIMITED, which has 2 other projects registered on MahaRERA.

Other projects in Patlipada

All 158 projects in Kasarvadavali (400615) →

Other projects by SAI UMA CONSTRUCTION PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.