HORIZON EXOTICA

by K M REALTY · Borivade, ThaneAlso near owale, Ghodbunder road, Kasarvadavli

Possession date of HORIZON EXOTICA: 31 December 2026, moved from 30 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700024438, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about HORIZON EXOTICA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HORIZON EXOTICA has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA11082622090)

    Reason the builder gave MahaRERA: “The Self Declaration related to reason of delay is uploaded in "Other"”

Source: HORIZON EXOTICA’s extension records on MahaRERA (P51700024438), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HORIZON EXOTICA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700024438
Status
Registered and active
Builder
K M REALTY
Location
Borivade, Thane · 400615
Project type
Others
Registered on
13 Feb 2020
Completion date at registration
December 2025
Latest completion date
December 2026
Delay so far
12 months
Homes
104
Sold or booked
95%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of HORIZON EXOTICA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Horizon Exotica100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Horizon Exotica: covers G+ 1st to 23rd Floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HORIZON EXOTICA every month.

HORIZON EXOTICA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

KM Developers (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 7 still being built, 2 past the promised date (typically 9 months late). No complaints on MahaRERA.

Read Google reviews of HORIZON EXOTICA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HORIZON EXOTICA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HORIZON EXOTICA

What is the possession date of HORIZON EXOTICA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HORIZON EXOTICA in Borivade, Thane is 31 December 2026 — 12 months later than 30 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for HORIZON EXOTICA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HORIZON EXOTICA's builder has filed on MahaRERA, the official one, is 31 December 2026, already 12 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HORIZON EXOTICA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), HORIZON EXOTICA's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The Self Declaration related to reason of delay is uploaded in "Other"".

What is the RERA number of HORIZON EXOTICA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HORIZON EXOTICA in Borivade, Thane is P51700024438.

Is HORIZON EXOTICA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HORIZON EXOTICA is registered as P51700024438 and its status is "Registered and active".

What is the construction status of HORIZON EXOTICA?

According to GharKundli's check of MahaRERA records (updated October 2026), HORIZON EXOTICA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Horizon Exotica is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does HORIZON EXOTICA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is HORIZON EXOTICA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), HORIZON EXOTICA is registered on MahaRERA as P51700024438, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HORIZON EXOTICA's possession date changes?

The latest dates are on HORIZON EXOTICA's MahaRERA page (P51700024438). GharKundli's Kundli Watch sends a free WhatsApp update on HORIZON EXOTICA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HORIZON EXOTICA have?

According to GharKundli's check of MahaRERA records (updated October 2026), HORIZON EXOTICA has one building filed: Horizon Exotica with 24 floors and 119 units.

How much parking does HORIZON EXOTICA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 89 covered car parking spaces for HORIZON EXOTICA.

How big is the land of HORIZON EXOTICA?

According to GharKundli's check of MahaRERA records (updated October 2026), HORIZON EXOTICA stands on 2,300 sq m of land (about 0.6 acres), with 4,284 sq m of sanctioned built-up area.

What is the track record of HORIZON EXOTICA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), KM Developers (a group of 4 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 7 still being built, 2 past the promised date (typically 9 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of HORIZON EXOTICA?

Google Maps has reviews of HORIZON EXOTICA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HORIZON EXOTICA?

HORIZON EXOTICA by K M REALTY is in Borivade, Thane (pincode 400615), near owale, Ghodbunder road, Kasarvadavli, Maharashtra, and is registered on MahaRERA as P51700024438, per GharKundli's check of MahaRERA records.

How many homes are in HORIZON EXOTICA?

According to GharKundli's check of MahaRERA records (updated October 2026), HORIZON EXOTICA has 104 homes in 1 tower registered on MahaRERA, and 95% of them are sold or booked.

When was HORIZON EXOTICA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HORIZON EXOTICA was registered on MahaRERA on 13 February 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on HORIZON EXOTICA?

No court cases are listed for HORIZON EXOTICA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of HORIZON EXOTICA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is K M REALTY.

All projects with possession due in 2026 in Thane →

Other projects in Thane

All 158 projects in Kasarvadavali (400615) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.