by LAABH BUILDWELL · G B Road, ThaneAlso near Kasarvadavli, Near Kanchan Pushpa, owale
Possession date of LAABH GLORIA: 31 December 2025, moved from 30 May 2023 (31 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51700011246. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about LAABH GLORIA?
GharKundli’s full report on LAABH GLORIA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700011246
- Status
- Lapsed (registration period ended)
- Builder
- LAABH BUILDWELL
- Location
- G B Road, Thane · 400615
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- May 2023
- Latest completion date
- December 2025
- Delay so far
- 31 months
- Homes
- 106
- Towers
- 2
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of LAABH GLORIA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 100% | 100% | 97% |
| BUILDING B | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on LAABH GLORIA every month.
LAABH GLORIA: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (18 floors) · BUILDING B (8 floors)
- Land: 2,440 sq m (about 0.6 acres) · sanctioned built-up 2,406 sq m · recreational space 238 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of LAABH GLORIA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
LAABH GLORIA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about LAABH GLORIA
What is the possession date of LAABH GLORIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for LAABH GLORIA in G B Road, Thane is 31 December 2025 — 31 months later than 30 May 2023, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for LAABH GLORIA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date LAABH GLORIA's builder has filed on MahaRERA, the official one, is 31 December 2025, already 31 months later than the 30 May 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of LAABH GLORIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of LAABH GLORIA in G B Road, Thane is P51700011246.
Is LAABH GLORIA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAABH GLORIA is registered as P51700011246 and its status is "Lapsed (registration period ended)".
What is the construction status of LAABH GLORIA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAABH GLORIA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does LAABH GLORIA have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is LAABH GLORIA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), LAABH GLORIA is registered on MahaRERA as P51700011246, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 31 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if LAABH GLORIA's possession date changes?
The latest dates are on LAABH GLORIA's MahaRERA page (P51700011246). GharKundli's Kundli Watch sends a free WhatsApp update on LAABH GLORIA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does LAABH GLORIA have?
According to GharKundli's check of MahaRERA records (updated October 2026), LAABH GLORIA has 2 buildings filed: BUILDING A with 18 floors; BUILDING B with 8 floors.
How big is the land of LAABH GLORIA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAABH GLORIA stands on 2,440 sq m of land (about 0.6 acres), with 2,406 sq m of sanctioned built-up area and 238 sq m of recreational open space.
Where can I read reviews of LAABH GLORIA?
Google Maps has reviews of LAABH GLORIA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is LAABH GLORIA?
LAABH GLORIA by LAABH BUILDWELL is in G B Road, Thane (pincode 400615), near Kasarvadavli, Near Kanchan Pushpa, owale, Maharashtra, and is registered on MahaRERA as P51700011246, per GharKundli's check of MahaRERA records.
How many homes are in LAABH GLORIA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAABH GLORIA has 106 homes in 2 towers registered on MahaRERA.
When was LAABH GLORIA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), LAABH GLORIA was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on LAABH GLORIA?
No court cases are listed for LAABH GLORIA on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of LAABH GLORIA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LAABH BUILDWELL.
Check it yourself on MahaRERA
- How to check the possession date of LAABH GLORIA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400615
- HORIZON EXOTICA
- HORIZON PALMS - III
- Mahavir Breeze Phase 1
- LAKESCAPE
- NIYATI LAKE CROWN
- Tokyo Bay Phase 2B
- ROSA SEPHORA
- OPUS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.