RAUNAK 108

by UNNATHI ASSOCIATES (AUM) · Owale Village, ThaneAlso near Near Kanchan Pushpa, Ghodbunder Road, Kasarvadavli

Possession date of RAUNAK 108: 30 October 2027, moved from 30 June 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700028435, and currently active. Its completion date has moved from June 2026 to October 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 6 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about RAUNAK 108?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RAUNAK 108 has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA15052620970)

    Reason the builder gave MahaRERA:
    “1) At the time of project registration in 2021, the construction activities were significantly impacted due to the aftermath of the COVID-19 pandemic, resulting in acute shortage of labour, disruption in supply chains, and non-availability…” Read the full reason“1) At the time of project registration in 2021, the construction activities were significantly impacted due to the aftermath of the COVID-19 pandemic, resulting in acute shortage of labour, disruption in supply chains, and non-availability of construction materials, leading to an overall slowdown in progress. 2) The Project was originally envisaged as a 50-storey tower. However, considering the Floor Space Index (FSI) available at the relevant time, construction was undertaken only up to the 31st floor in accordance with the sanctioned Development Permission and Commencement Certificate dat…”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RAUNAK 108’s extension records on MahaRERA (P51700028435), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RAUNAK 108

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 6 complaints and 2 court cases, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700028435
Status
Registered and active
Builder
UNNATHI ASSOCIATES
Location
Owale Village, Thane · 400615
Project type
Residential / Group Housing
Registered on
2 Mar 2021
Completion date at registration
June 2026
Latest completion date
October 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
738
Sold or booked
86%
Towers
1
Complaints on MahaRERA
6
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
13

Construction progress of RAUNAK 108, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RAUNAK 108100%100%70%40%

Commencement certificate (CC), as filed on MahaRERA

  • RAUNAK 108: covers Lower Gr + Uppar Ground + 44 Floors

Latest CC order on MahaRERA: dated 17/12/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAUNAK 108 every month.

RAUNAK 108: buildings, flats and land, as filed on MahaRERA

  • Buildings: RAUNAK 108 (46 floors, 760 units)
  • Car parking: 456 covered
  • Land: 1,454 sq m (about 0.4 acres) · sanctioned built-up 43,580 sq m · recreational space 2,016 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Raunak Corporation (a group of 19 linked companies) has 60 projects on MahaRERA since 2017, this one included. Of the 60 GharKundli has checked: 29 finished, 28 within the promised date and 1 needed more time (typically 5 months); 30 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 162 complaints on MahaRERA across 27 projects.

Read Google reviews of RAUNAK 108 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RAUNAK 108: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RAUNAK 108

What is the possession date of RAUNAK 108?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RAUNAK 108 in Owale Village, Thane is 30 October 2027 — 12 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for RAUNAK 108?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RAUNAK 108's builder has filed on MahaRERA, the official one, is 30 October 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of RAUNAK 108 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), RAUNAK 108's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "1) At the time of project registration in 2021, the construction activities were significantly impacted due to the aftermath of the COVID-19 pandemic, resulting in acute shortage of labour, disruption in supply chains, and non-availability of construction materials, leading to an overall slowdown in progress. 2) The Project was originally envisaged as a 50-storey tower. However, considering the Floor Space Index (FSI) available at the relevant time, construction was undertaken only up to the 31st floor in accordance with the sanctioned Development Permission and Commencement Certificate dat…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of RAUNAK 108?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RAUNAK 108 in Owale Village, Thane is P51700028435.

Is RAUNAK 108 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAUNAK 108 is registered as P51700028435 and its status is "Registered and active".

What is the construction status of RAUNAK 108?

According to GharKundli's check of MahaRERA records (updated October 2026), RAUNAK 108's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RAUNAK 108 is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does RAUNAK 108 have complaints on MahaRERA?

6 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is RAUNAK 108 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), RAUNAK 108 is registered on MahaRERA as P51700028435, its completion date has moved 12 months since registration and 6 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if RAUNAK 108's possession date changes?

The latest dates are on RAUNAK 108's MahaRERA page (P51700028435). GharKundli's Kundli Watch sends a free WhatsApp update on RAUNAK 108 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RAUNAK 108 have?

According to GharKundli's check of MahaRERA records (updated October 2026), RAUNAK 108 has one building filed: RAUNAK 108 with 46 floors and 760 units.

How much parking does RAUNAK 108 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 456 covered car parking spaces for RAUNAK 108.

How big is the land of RAUNAK 108?

According to GharKundli's check of MahaRERA records (updated October 2026), RAUNAK 108 stands on 1,454 sq m of land (about 0.4 acres), with 43,580 sq m of sanctioned built-up area and 2,016 sq m of recreational open space.

What is the track record of RAUNAK 108's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Raunak Corporation (a group of 19 linked companies) has 60 projects on MahaRERA since 2017, this one included. Of the 60 GharKundli has checked: 29 finished, 28 within the promised date and 1 needed more time (typically 5 months); 30 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 162 complaints on MahaRERA across 27 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of RAUNAK 108?

Google Maps has reviews of RAUNAK 108 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 6 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RAUNAK 108?

RAUNAK 108 by UNNATHI ASSOCIATES (AUM) is in Owale Village, Thane (pincode 400615), near Near Kanchan Pushpa, Ghodbunder Road, Kasarvadavli, Maharashtra, and is registered on MahaRERA as P51700028435, per GharKundli's check of MahaRERA records.

How many homes are in RAUNAK 108?

According to GharKundli's check of MahaRERA records (updated October 2026), RAUNAK 108 has 738 homes in 1 tower registered on MahaRERA, and 86% of them are sold or booked.

When was RAUNAK 108 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAUNAK 108 was registered on MahaRERA on 2 March 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on RAUNAK 108?

2 court cases are listed for RAUNAK 108 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of RAUNAK 108?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UNNATHI ASSOCIATES, the company AUM files this project under, which has 13 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Thane

All 158 projects in Kasarvadavali (400615) →

Other projects by UNNATHI ASSOCIATES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.