RAUNAK BLISS PHASE A
by UNNATHI ASSOCIATES (AUM) · owale, ThaneAlso near Ghodbunder road, Kasarvadavli
Possession: RAUNAK BLISS PHASE A is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700005363. Status: Completed. 17 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about RAUNAK BLISS PHASE A?
GharKundli’s full report on RAUNAK BLISS PHASE A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 17 complaints and 5 court cases, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- RAUNAK BLISS A4P51700046674 · possession 30 Apr 2030
- RAUNAK BLISS - B1P51700020204 · possession 30 Apr 2030
- RAUNAK BLISS B1P51700046534 · possession 30 Apr 2030
- RAUNAK BLISS B2P51700046565 · possession 30 Apr 2030
- RAUNAK BLISS - B2P51700020244 · possession 30 Apr 2030
- RAUNAK BLISS B3P51700046564 · possession 30 Apr 2030
- Raunak Bliss B4P51700050829 · possession 30 Apr 2031
- Raunak Bliss B5P51700050828 · possession 30 Apr 2031
- Raunak Bliss B6P51700050827 · possession 30 Apr 2031
- RAUNAK BLISS PHASE A - A3P51700007033 · possession 30 Jun 2026
- MahaRERA registration
- P51700005363
- Status
- Completed
- Builder
- UNNATHI ASSOCIATES
- Location
- owale, Thane · 400615
- Project type
- Residential / Group Housing
- Registered on
- 11 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- December 2024
- Homes
- 422
- Towers
- 2
- Complaints on MahaRERA
- 17
- Court cases listed
- 5
- Appeals at the tribunal
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 13
Construction progress of RAUNAK BLISS PHASE A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A1 | 100% | 100% | 100% | 100% |
| A2 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAUNAK BLISS PHASE A every month.
RAUNAK BLISS PHASE A: buildings, flats and land, as filed on MahaRERA
- Buildings: A1 (37 floors) · A2 (35 floors)
- Land: 5,000 sq m (about 1.2 acres) · sanctioned built-up 14,434 sq m · recreational space 1,000 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Raunak Corporation (a group of 19 linked companies) has 60 projects on MahaRERA since 2017, this one included. Of the 60 GharKundli has checked: 29 finished, 28 within the promised date and 1 needed more time (typically 5 months); 30 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 162 complaints on MahaRERA across 27 projects.
Read Google reviews of RAUNAK BLISS PHASE A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RAUNAK BLISS PHASE A: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RAUNAK BLISS PHASE A
What is the possession date of RAUNAK BLISS PHASE A?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for RAUNAK BLISS PHASE A in owale, Thane is 30 December 2024.
Is the builder's possession date different from the MahaRERA date for RAUNAK BLISS PHASE A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RAUNAK BLISS PHASE A's builder has filed on MahaRERA, the official one, is 30 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of RAUNAK BLISS PHASE A?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of RAUNAK BLISS PHASE A in owale, Thane is P51700005363.
Is RAUNAK BLISS PHASE A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAUNAK BLISS PHASE A is registered as P51700005363 and its status is "Completed".
What is the construction status of RAUNAK BLISS PHASE A?
According to GharKundli's check of MahaRERA records (updated November 2026), RAUNAK BLISS PHASE A's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does RAUNAK BLISS PHASE A have complaints on MahaRERA?
17 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is RAUNAK BLISS PHASE A safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), RAUNAK BLISS PHASE A is registered on MahaRERA as P51700005363, its MahaRERA status is "Completed", its completion date has not been moved by the builder and 17 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does RAUNAK BLISS PHASE A have other wings or phases?
Yes. MahaRERA lists 10 other registrations of the same project, each with its own possession date: RAUNAK BLISS A4 (P51700046674, possession 30 Apr 2030); RAUNAK BLISS - B1 (P51700020204, possession 30 Apr 2030); RAUNAK BLISS B1 (P51700046534, possession 30 Apr 2030); RAUNAK BLISS B2 (P51700046565, possession 30 Apr 2030); RAUNAK BLISS - B2 (P51700020244, possession 30 Apr 2030); RAUNAK BLISS B3 (P51700046564, possession 30 Apr 2030); and 4 more. Check that your agreement names the registration of your own wing.
How can I get updates if RAUNAK BLISS PHASE A's possession date changes?
The latest dates are on RAUNAK BLISS PHASE A's MahaRERA page (P51700005363). GharKundli's Kundli Watch sends a free WhatsApp update on RAUNAK BLISS PHASE A every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RAUNAK BLISS PHASE A have?
According to GharKundli's check of MahaRERA records (updated November 2026), RAUNAK BLISS PHASE A has 2 buildings filed: A1 with 37 floors; A2 with 35 floors.
How big is the land of RAUNAK BLISS PHASE A?
According to GharKundli's check of MahaRERA records (updated November 2026), RAUNAK BLISS PHASE A stands on 5,000 sq m of land (about 1.2 acres), with 14,434 sq m of sanctioned built-up area and 1,000 sq m of recreational open space.
What is the track record of RAUNAK BLISS PHASE A's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Corporation (a group of 19 linked companies) has 60 projects on MahaRERA since 2017, this one included. Of the 60 GharKundli has checked: 29 finished, 28 within the promised date and 1 needed more time (typically 5 months); 30 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 162 complaints on MahaRERA across 27 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RAUNAK BLISS PHASE A?
Google Maps has reviews of RAUNAK BLISS PHASE A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 17 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RAUNAK BLISS PHASE A?
RAUNAK BLISS PHASE A by UNNATHI ASSOCIATES (AUM) is in owale, Thane (pincode 400615), near Ghodbunder road, Kasarvadavli, Maharashtra, and is registered on MahaRERA as P51700005363, per GharKundli's check of MahaRERA records.
How many homes are in RAUNAK BLISS PHASE A?
According to GharKundli's check of MahaRERA records (updated November 2026), RAUNAK BLISS PHASE A has 422 homes in 2 towers registered on MahaRERA.
When was RAUNAK BLISS PHASE A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), RAUNAK BLISS PHASE A was registered on MahaRERA on 11 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on RAUNAK BLISS PHASE A?
5 court cases are listed for RAUNAK BLISS PHASE A on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RAUNAK BLISS PHASE A?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is UNNATHI ASSOCIATES, the company AUM files this project under, which has 13 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of RAUNAK BLISS PHASE A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in owale
All 158 projects in Kasarvadavali (400615) →Other projects by UNNATHI ASSOCIATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.