Raunak Bliss B4

by UNNATHI ASSOCIATES (AUM) · Owale, ThaneAlso near Ghodbunder road, Kasarvadavli, Borivali West

Possession date of Raunak Bliss B4: 30 April 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700050829, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Raunak Bliss B4?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Raunak Bliss B4 has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Raunak Bliss B4’s extension records on MahaRERA (P51700050829), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Raunak Bliss B4

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints and 6 court cases, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700050829
Status
Registered and active
Builder
UNNATHI ASSOCIATES
Location
Owale, Thane · 400610
Project type
Residential / Group Housing
Registered on
9 May 2023
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
273
Sold or booked
100%
Towers
1
Complaints on MahaRERA
7
Court cases listed
6
Title report on file
Not found
Builder's other MahaRERA projects
13

Construction progress of Raunak Bliss B4, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B4100%75%35%0%

Commencement certificate (CC), as filed on MahaRERA

  • B4: covers 35 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Raunak Bliss B4 every month.

Raunak Bliss B4: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Raunak Corporation (a group of 19 linked companies) has 60 projects on MahaRERA since 2017, this one included. Of the 60 GharKundli has checked: 29 finished, 28 within the promised date and 1 needed more time (typically 5 months); 30 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 162 complaints on MahaRERA across 27 projects.

Read Google reviews of Raunak Bliss B4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Raunak Bliss B4: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Raunak Bliss B4

What is the possession date of Raunak Bliss B4?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Raunak Bliss B4 in Owale, Thane is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Raunak Bliss B4?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Raunak Bliss B4's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Raunak Bliss B4?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Raunak Bliss B4 in Owale, Thane is P51700050829.

Is Raunak Bliss B4 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Bliss B4 is registered as P51700050829 and its status is "Registered and active".

What is the construction status of Raunak Bliss B4?

According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Bliss B4's status on MahaRERA is "Registered and active". As filed by the builder, slab work on B4 is 75% done and internal work 35%. GharKundli's full report compares construction progress with the deadline.

Does Raunak Bliss B4 have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Raunak Bliss B4 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Bliss B4 is registered on MahaRERA as P51700050829, its completion date has not been moved by the builder and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Raunak Bliss B4 have other wings or phases?

Yes. MahaRERA lists 10 other registrations of the same project, each with its own possession date: RAUNAK BLISS A4 (P51700046674, possession 30 Apr 2030); RAUNAK BLISS - B1 (P51700020204, possession 30 Apr 2030); RAUNAK BLISS B1 (P51700046534, possession 30 Apr 2030); RAUNAK BLISS B2 (P51700046565, possession 30 Apr 2030); RAUNAK BLISS - B2 (P51700020244, possession 30 Apr 2030); RAUNAK BLISS B3 (P51700046564, possession 30 Apr 2030); and 4 more. Check that your agreement names the registration of your own wing.

How can I get updates if Raunak Bliss B4's possession date changes?

The latest dates are on Raunak Bliss B4's MahaRERA page (P51700050829). GharKundli's Kundli Watch sends a free WhatsApp update on Raunak Bliss B4 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Raunak Bliss B4 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Bliss B4 has one building filed: B4 with 38 floors and 273 units.

How much parking does Raunak Bliss B4 have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 1 covered car parking spaces for Raunak Bliss B4.

How big is the land of Raunak Bliss B4?

According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Bliss B4 stands on 5,881 sq m of land (about 1.5 acres), with 17,127 sq m of sanctioned built-up area and 1,175 sq m of recreational open space.

What is the track record of Raunak Bliss B4's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Corporation (a group of 19 linked companies) has 60 projects on MahaRERA since 2017, this one included. Of the 60 GharKundli has checked: 29 finished, 28 within the promised date and 1 needed more time (typically 5 months); 30 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 162 complaints on MahaRERA across 27 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Raunak Bliss B4?

Google Maps has reviews of Raunak Bliss B4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Raunak Bliss B4?

Raunak Bliss B4 by UNNATHI ASSOCIATES (AUM) is in Owale, Thane (pincode 400610), near Ghodbunder road, Kasarvadavli, Borivali West, Maharashtra, and is registered on MahaRERA as P51700050829, per GharKundli's check of MahaRERA records.

How many homes are in Raunak Bliss B4?

According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Bliss B4 has 273 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was Raunak Bliss B4 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Raunak Bliss B4 was registered on MahaRERA on 9 May 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Raunak Bliss B4?

6 court cases are listed for Raunak Bliss B4 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Raunak Bliss B4?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is UNNATHI ASSOCIATES, the company AUM files this project under, which has 13 other projects registered on MahaRERA.

All projects with possession due in 2031 in Thane →

Other projects in Owale

All 56 projects in Majiwade (400610) →

Other projects by UNNATHI ASSOCIATES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.