MahaRERA projects in Majiwade, Thane (400610)
According to GharKundli's check of MahaRERA records, 44 housing projects are registered in pincode 400610 (Majiwade, Thane). 24 are still being built, 4 with possession due by the end of 2027. For 27, the completion date on MahaRERA is later than the one first promised. 25 have at least one complaint filed on MahaRERA.
Pincode 400610 also covers: Owale, Anand Nagar, Subhash Nagar, Thane West, Thane West, Apna Bazar.
“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.
| Project | MahaRERA status | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| RAUNAK IMPERIAL RAUNAK AVENUE REALTY | Active | 31 Dec 2026 | same | 0 |
| INFINITY TOWERS T Bhimjyani Realty Pvt.Ltd. | Active | 28 Apr 2027 | 28 Aug 2025 | 19 |
| ZEN NEELKANTH REALTORS PVT LTD | Active | 30 Apr 2027 | 31 Dec 2026 | 1 |
| Serein Phase II ARDENT PROPERTIES PRIVATE LIMITED | Active | 30 Sep 2027 | 31 May 2027 | 0 |
| Courtyard - Asteria A COURTYARD REAL ESTATE PRIVATE LIMITED | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Courtyard - Asteria B COURTYARD REAL ESTATE PRIVATE LIMITED | Active | 30 Apr 2028 | 31 Dec 2027 | 1 |
| Mahavir Spring -Daffodils-P3 Vinayak Developers | Active | 30 Apr 2028 | 30 Dec 2027 | 0 |
| SHETH VASANT LAWNS Sheth Developers Private Limited | Active | 30 Apr 2028 | 30 Dec 2023 | 30 |
| F Neelkanth Greens Neelkanth Mansions and Infrastructure Pvt. Ltd.d | Active | 14 Jul 2028 | 14 Mar 2028 | 0 |
| Shapoorji Pallonji The Impulse- Phase 1 Jaykali Developers Private Limited | Active | 30 Oct 2028 | 30 Jun 2024 | 0 |
| OPULUS S1 S2 R1 R2 and R3 PEER REALTY PRIVATE LIMITED | Active | 30 Jan 2029 | 30 Oct 2025 | 2 |
| Omega - Northern Lights Jaykali Developers Private Limited | Active | 30 Jul 2029 | 30 Mar 2025 | 6 |
| Orion - Northern Lights Jaykali Developers Private Limited | Active | 30 Jul 2029 | 30 Mar 2025 | 11 |
| Shapoorji Pallonji The Impulse- Phase 2 Jaykali Developers Private Limited | Active | 30 Jul 2029 | 30 Mar 2025 | 0 |
| Oyster - Shapoorji Pallonji Northern Lights Jaykali Developers Private Limited | Active | 30 Jan 2030 | 30 Sep 2025 | 5 |
| Krishna Wing C K RUDRAKSH REALTORS LLP | Active | 30 Apr 2030 | 31 Dec 2029 | 0 |
| RAUNAK BLISS B1 UNNATHI ASSOCIATES | Active | 30 Apr 2030 | 31 Dec 2029 | 1 |
| Raunak Bliss B4 UNNATHI ASSOCIATES | Active | 30 Apr 2031 | 31 Dec 2030 | 7 |
| Raunak Bliss B5 UNNATHI ASSOCIATES | Active | 30 Apr 2031 | 31 Dec 2030 | 3 |
| Raunak Bliss B6 UNNATHI ASSOCIATES | Active | 30 Apr 2031 | 31 Dec 2030 | 0 |
| OGC Thane Phase 1 Oberoi Realty Limited | Active | 30 Oct 2031 | 30 Jun 2031 | 1 |
| VERONA A T BHIMJYANI REALTY PRIVATE LIMITED | Active | 30 Oct 2031 | 30 Jun 2031 | 0 |
| VERONA B T Bhimjyani Realty Pvt.Ltd. | Active | 30 Oct 2031 | 30 Jun 2031 | 0 |
| Shapoorji Pallonji Skyraa at Northern Lights Jaykali Developers Private Limited | Active | 30 Apr 2032 | 31 Dec 2027 | 2 |
| Silver Oak at Prestige Residency PRESCON Realtors & Infrastructures Pvt. ltd. | Completed | 30 Dec 2020 | 31 Dec 2019 | 1 |
| No. M - 67 T Bhimjyani Realty Pvt.Ltd. | Completed | 28 Nov 2021 | same | 0 |
| Krishna - B Wing Neelkanth Palm Realty | Completed | 30 May 2022 | same | 6 |
| SUKUR SAPPHIRE PHASE I RAJARAM CONSTRUCTION | Completed | 30 Dec 2022 | same | 0 |
| Bungalow K 53 Rekha Mohanlal Nensi Tanna Bhimjyani | Completed | 10 Jan 2023 | same | 0 |
| Serein Phase 1 ARDENT PROPERTIES PRIVATE LIMITED | Completed | 31 Mar 2023 | 30 Sep 2022 | 19 |
| HYDE PARK RESIDENCY F5 BUILDING PHASE NEXUS BUILDERS AND DEVELOPERS PVT LTD | Completed | 30 Sep 2023 | same | 0 |
| Shapoorji Pallonji The Impulse Jaykali Developers Private Limited | Completed | 30 Dec 2023 | same | 1 |
| SUKUR SAPPHIRE PHASE II RAJARAM CONSTRUCTION | Completed | 30 Jun 2024 | same | 0 |
| Iris Shopping HIRANANDANI PROPERTIES PRIVATE LIMITED | Completed | 18 Oct 2024 | 30 Mar 2023 | 0 |
| Lakeview NEELKANTH REALTORS PVT LTD | Completed | 29 Dec 2024 | 30 Dec 2023 | 1 |
| Mahavir Spring - Daffodils - Phase 2 Vinayak developers | Completed | 30 Dec 2025 | same | 0 |
| Courtyard - Asteria C COURTYARD REAL ESTATE PRIVATE LIMITED | Completed | 31 Dec 2027 | same | 0 |
| Mahavir Spring - Tulip - Phase 1 Vinayak Developers | Lapsed | 30 Dec 2025passed | same | 1 |
| Dosti Imperia - Dosti Majesta DOSTI REALTY LTD | — | — | — | 1 |
| Kalpataru Hills - Building 2A Kalpataru Properties (Thane) Pvt. Ltd. | — | — | — | 2 |
| Neelkanth Woods Bungalow M 66 T Bhimjyani Realty Pvt.Ltd. | — | — | — | 2 |
| Neelkanth Woods Olivia T Bhimjyani Realty Pvt.Ltd. | — | — | — | 63 |
| TRINITY OASIS ANIL thakurdas kursija | — | — | — | 14 |
| TRINITY OASIS PHASE II ANIL thakurdas kursija | — | — | — | 7 |
Other areas in Thane
- Kulgaon · 735
- Kalyan · 510
- Ambernath · 403
- Tilaknagar · 354
- Bhiwandi · 348
- Mira Road East · 277
- Kalyan East · 250
- Manpada · 232
- Naupada · 223
- Vishnunagar · 198
- Mumbra · 188
- Sandozbaugh · 180
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.