Orion - Northern Lights

by Jaykali Developers Private Limited · Thane West, ThaneAlso near Majiwade, Badlapur, Naupada

Possession date of Orion - Northern Lights: 30 July 2029, moved from 30 March 2025 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700019864, and currently active. Its completion date has moved from March 2025 to July 2029: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. MahaRERA has issued a regulatory order on this project. 11 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Orion - Northern Lights?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Orion - Northern Lights has moved

  1. 30 March 2025

    Completion date given when the project was registered

  2. 30 March 2029

    Extended at the builder's request (MahaRERA application EXT51700028177)

    Reason the builder gave MahaRERA:
    “As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees until 30/03/2029, as due to the prolonged lockdown and various restrictions, there was shortage and unavailability of construction…” Read the full reason“As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees until 30/03/2029, as due to the prolonged lockdown and various restrictions, there was shortage and unavailability of construction materials and labour due to which the project could not progress at the required pace to meet the completion date. The above operational challenges in addition to the change in UDCPR and delay in obtaining environmental clearance from the competent authority have severely disturbed the timelines for scheduled project delivery”
  3. 30 July 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Orion - Northern Lights’s extension records on MahaRERA (P51700019864), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Orion - Northern Lights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 11 complaints, and how it ended
  • Construction pace against the July 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700019864
Status
Registered and active
Builder
Jaykali Developers Private Limited
Location
Thane West, Thane · 400610
Project type
Residential / Group Housing
Registered on
7 Mar 2019
Completion date at registration
March 2025
Latest completion date
July 2029
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
326
Towers
1
Complaints on MahaRERA
11
Court cases listed
0
Appeals at the tribunal
2
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Orion - Northern Lights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Orion100%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Orion - Northern Lights every month.

Orion - Northern Lights: buildings, flats and land, as filed on MahaRERA

  • Buildings: Orion (53 floors)
  • Land: 2,935 sq m (about 0.7 acres) · sanctioned built-up 32,329 sq m · recreational space 2,690 sq m
  • Boundaries filed include: Podium Garden
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects.

Read Google reviews of Orion - Northern Lights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Orion - Northern Lights: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Orion - Northern Lights

What is the possession date of Orion - Northern Lights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Orion - Northern Lights in Thane West, Thane is 30 July 2029 — 48 months later than 30 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Orion - Northern Lights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Orion - Northern Lights's builder has filed on MahaRERA, the official one, is 30 July 2029, already 48 months later than the 30 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Orion - Northern Lights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Orion - Northern Lights's builder applied to MahaRERA to extend the completion date once: to 30 March 2029, giving the reason "As per Order No. 40 Dated 27/12/2022 we are applying for Extension without majority consents of the allottees until 30/03/2029, as due to the prolonged lockdown and various restrictions, there was shortage and unavailability of construction materials and labour due to which the project could not progress at the required pace to meet the completion date. The above operational challenges in addition to the change in UDCPR and delay in obtaining environmental clearance from the competent authority have severely disturbed the timelines for scheduled project delivery". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Orion - Northern Lights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Orion - Northern Lights in Thane West, Thane is P51700019864.

Is Orion - Northern Lights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Orion - Northern Lights is registered as P51700019864 and its status is "Registered and active".

What is the construction status of Orion - Northern Lights?

According to GharKundli's check of MahaRERA records (updated October 2026), Orion - Northern Lights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Orion is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Orion - Northern Lights have complaints on MahaRERA?

11 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Orion - Northern Lights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Orion - Northern Lights is registered on MahaRERA as P51700019864, its completion date has moved 48 months since registration and 11 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Orion - Northern Lights's possession date changes?

The latest dates are on Orion - Northern Lights's MahaRERA page (P51700019864). GharKundli's Kundli Watch sends a free WhatsApp update on Orion - Northern Lights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Orion - Northern Lights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Orion - Northern Lights has one building filed: Orion with 53 floors.

How big is the land of Orion - Northern Lights?

According to GharKundli's check of MahaRERA records (updated October 2026), Orion - Northern Lights stands on 2,935 sq m of land (about 0.7 acres), with 32,329 sq m of sanctioned built-up area and 2,690 sq m of recreational open space.

What is the track record of Orion - Northern Lights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Orion - Northern Lights?

Google Maps has reviews of Orion - Northern Lights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 11 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Orion - Northern Lights?

Orion - Northern Lights by Jaykali Developers Private Limited is in Thane West, Thane (pincode 400610), near Majiwade, Badlapur, Naupada, Maharashtra, and is registered on MahaRERA as P51700019864, per GharKundli's check of MahaRERA records. Its boundaries filed there include Podium Garden.

How many homes are in Orion - Northern Lights?

According to GharKundli's check of MahaRERA records (updated October 2026), Orion - Northern Lights has 326 homes in 1 tower registered on MahaRERA.

When was Orion - Northern Lights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Orion - Northern Lights was registered on MahaRERA on 7 March 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Orion - Northern Lights?

No court cases are listed for Orion - Northern Lights on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Orion - Northern Lights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Jaykali Developers Private Limited, which has 6 other projects registered on MahaRERA.

All projects with possession due in 2029 in Thane →

Other projects in Thane

All 56 projects in Majiwade (400610) →

Other projects by Jaykali Developers Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.