Shapoorji Pallonji The Impulse

by Jaykali Developers Private Limited · Apna Bazar, ThaneAlso near Balkum, Jekegram

Possession: Shapoorji Pallonji The Impulse is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700022305. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Shapoorji Pallonji The Impulse?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Shapoorji Pallonji The Impulse

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700022305
Status
Completed
Builder
Jaykali Developers Private Limited
Location
Apna Bazar, Thane · 400610
Project type
Commercial
Registered on
9 Sep 2019
Completion date at registration
December 2023
Latest completion date
December 2023
Homes
20
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Shapoorji Pallonji The Impulse, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shapoorji Pallonji The Impulse0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shapoorji Pallonji The Impulse every month.

Shapoorji Pallonji The Impulse: buildings, flats and land, as filed on MahaRERA

  • Buildings: Shapoorji Pallonji The Impulse (4 floors)
  • Land: 654 sq m (about 0.2 acres) · sanctioned built-up 3,906 sq m

The builder’s record and reviews

Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects.

Read Google reviews of Shapoorji Pallonji The Impulse →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Shapoorji Pallonji The Impulse: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Shapoorji Pallonji The Impulse

What is the possession date of Shapoorji Pallonji The Impulse?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Shapoorji Pallonji The Impulse in Apna Bazar, Thane is 30 December 2023.

Is the builder's possession date different from the MahaRERA date for Shapoorji Pallonji The Impulse?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Shapoorji Pallonji The Impulse's builder has filed on MahaRERA, the official one, is 30 December 2023, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Shapoorji Pallonji The Impulse?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Shapoorji Pallonji The Impulse in Apna Bazar, Thane is P51700022305.

Is Shapoorji Pallonji The Impulse registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shapoorji Pallonji The Impulse is registered as P51700022305 and its status is "Completed".

What is the construction status of Shapoorji Pallonji The Impulse?

According to GharKundli's check of MahaRERA records (updated November 2026), Shapoorji Pallonji The Impulse's status on MahaRERA is "Completed". As filed by the builder, slab work on Shapoorji Pallonji The Impulse is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Shapoorji Pallonji The Impulse have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Shapoorji Pallonji The Impulse safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Shapoorji Pallonji The Impulse is registered on MahaRERA as P51700022305, its MahaRERA status is "Completed", its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Shapoorji Pallonji The Impulse have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Shapoorji Pallonji The Impulse- Phase 1 (P51700027176, possession 30 Oct 2028); Shapoorji Pallonji The Impulse- Phase 2 (P51700027197, possession 30 Jul 2029). Check that your agreement names the registration of your own wing.

How can I get updates if Shapoorji Pallonji The Impulse's possession date changes?

The latest dates are on Shapoorji Pallonji The Impulse's MahaRERA page (P51700022305). GharKundli's Kundli Watch sends a free WhatsApp update on Shapoorji Pallonji The Impulse every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Shapoorji Pallonji The Impulse have?

According to GharKundli's check of MahaRERA records (updated November 2026), Shapoorji Pallonji The Impulse has one building filed: Shapoorji Pallonji The Impulse with 4 floors.

How big is the land of Shapoorji Pallonji The Impulse?

According to GharKundli's check of MahaRERA records (updated November 2026), Shapoorji Pallonji The Impulse stands on 654 sq m of land (about 0.2 acres), with 3,906 sq m of sanctioned built-up area.

What is the track record of Shapoorji Pallonji The Impulse's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vakratunda Buildcon (a group of 10 linked companies) has 51 projects on MahaRERA since 2017, this one included. Of the 50 GharKundli has checked: 7 finished, 6 within the promised date and 1 needed more time (typically 16 months); 38 still being built, 15 past the promised date (typically 6 months late); 5 lapsed. 454 complaints on MahaRERA across 32 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Shapoorji Pallonji The Impulse?

Google Maps has reviews of Shapoorji Pallonji The Impulse written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Shapoorji Pallonji The Impulse?

Shapoorji Pallonji The Impulse by Jaykali Developers Private Limited is in Apna Bazar, Thane (pincode 400610), near Balkum, Jekegram, Maharashtra, and is registered on MahaRERA as P51700022305, per GharKundli's check of MahaRERA records.

How many homes are in Shapoorji Pallonji The Impulse?

According to GharKundli's check of MahaRERA records (updated November 2026), Shapoorji Pallonji The Impulse has 20 homes in 1 tower registered on MahaRERA.

When was Shapoorji Pallonji The Impulse registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Shapoorji Pallonji The Impulse was registered on MahaRERA on 9 September 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Shapoorji Pallonji The Impulse?

No court cases are listed for Shapoorji Pallonji The Impulse on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Shapoorji Pallonji The Impulse?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Jaykali Developers Private Limited, which has 6 other projects registered on MahaRERA.

Other projects in pincode 400610

All 56 projects in Majiwade (400610) →

Other projects by Jaykali Developers Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.