INFINITY TOWERS
by T Bhimjyani Realty Pvt.Ltd. · Majiwade, Thane
Possession date of INFINITY TOWERS: 28 April 2027, moved from 28 August 2025 (16 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700021698, and currently active. Its completion date has moved from August 2025 to April 2027: 16 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 19 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about INFINITY TOWERS?
How the possession date of INFINITY TOWERS has moved
28 August 2025
Completion date given when the project was registered
28 December 2026
Extended at the builder's request (MahaRERA application EXT51700018008)
Reason the builder gave MahaRERA:
“Promoter has proposed certain changes in the layout and submitted to corporation.Promoter got approval of Corporation.Because of change in layout area and floors are increased.Promoter need some time to complete the said project.Promoter ob…” Read the full reason
“Promoter has proposed certain changes in the layout and submitted to corporation.Promoter got approval of Corporation.Because of change in layout area and floors are increased.Promoter need some time to complete the said project.Promoter obtained necessary consent for parties.Promoter hereby assure that grant of extension of the project validity shall not affect.”28 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: INFINITY TOWERS’s extension records on MahaRERA (P51700021698), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on INFINITY TOWERS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 19 complaints and 9 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700021698
- Status
- Registered and active
- Builder
- T Bhimjyani Realty Pvt.Ltd.
- Location
- Majiwade, Thane · 400610
- Project type
- Residential / Group Housing
- Registered on
- 19 Jul 2019
- Completion date at registration
- August 2025
- Latest completion date
- April 2027
- Delay so far
- 16 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 443
- Sold or booked
- 95%
- Towers
- 3
- Complaints on MahaRERA
- 19
- Court cases listed
- 9
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of INFINITY TOWERS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| INFINITY A | 100% | 100% | 85% | 50% |
| INFINITY B | 100% | 100% | 90% | 0% |
| INFINITY C | 100% | 70% | 45% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- INFINITY A: covers 41 floors
- INFINITY B: covers 41 floors
- INFINITY C: covers 41 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on INFINITY TOWERS every month.
INFINITY TOWERS: buildings, flats and land, as filed on MahaRERA
- Buildings: INFINITY A (45 floors, 160 units) · INFINITY B (45 floors, 160 units) · INFINITY C (45 floors, 123 units)
- Land: 5,743 sq m (about 1.4 acres) · sanctioned built-up 58,455 sq m · recreational space 1,443 sq m
- Boundaries filed include: NEELKANTH GREENS COMPLEX
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
T Bhimjyani Realty has 9 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 5 finished, all within the promised date; 3 still being built, none past the promised date yet. 84 complaints on MahaRERA across 3 projects.
Read Google reviews of INFINITY TOWERS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
INFINITY TOWERS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about INFINITY TOWERS
What is the possession date of INFINITY TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for INFINITY TOWERS in Majiwade, Thane is 28 April 2027 — 16 months later than 28 August 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for INFINITY TOWERS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date INFINITY TOWERS's builder has filed on MahaRERA, the official one, is 28 April 2027, already 16 months later than the 28 August 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of INFINITY TOWERS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), INFINITY TOWERS's builder applied to MahaRERA to extend the completion date once: to 28 December 2026, giving the reason "Promoter has proposed certain changes in the layout and submitted to corporation.Promoter got approval of Corporation.Because of change in layout area and floors are increased.Promoter need some time to complete the said project.Promoter obtained necessary consent for parties.Promoter hereby assure that grant of extension of the project validity shall not affect.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of INFINITY TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of INFINITY TOWERS in Majiwade, Thane is P51700021698.
Is INFINITY TOWERS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), INFINITY TOWERS is registered as P51700021698 and its status is "Registered and active".
What is the construction status of INFINITY TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), INFINITY TOWERS's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 70% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does INFINITY TOWERS have complaints on MahaRERA?
19 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is INFINITY TOWERS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), INFINITY TOWERS is registered on MahaRERA as P51700021698, its completion date has moved 16 months since registration and 19 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if INFINITY TOWERS's possession date changes?
The latest dates are on INFINITY TOWERS's MahaRERA page (P51700021698). GharKundli's Kundli Watch sends a free WhatsApp update on INFINITY TOWERS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does INFINITY TOWERS have?
According to GharKundli's check of MahaRERA records (updated October 2026), INFINITY TOWERS has 3 buildings filed: INFINITY A with 45 floors and 160 units; INFINITY B with 45 floors and 160 units; INFINITY C with 45 floors and 123 units.
How big is the land of INFINITY TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), INFINITY TOWERS stands on 5,743 sq m of land (about 1.4 acres), with 58,455 sq m of sanctioned built-up area and 1,443 sq m of recreational open space.
What is the track record of INFINITY TOWERS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), T Bhimjyani Realty has 9 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 5 finished, all within the promised date; 3 still being built, none past the promised date yet. 84 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of INFINITY TOWERS?
Google Maps has reviews of INFINITY TOWERS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 19 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is INFINITY TOWERS?
INFINITY TOWERS by T Bhimjyani Realty Pvt.Ltd. is in Majiwade, Thane (pincode 400610), Maharashtra, and is registered on MahaRERA as P51700021698, per GharKundli's check of MahaRERA records. Its boundaries filed there include NEELKANTH GREENS COMPLEX.
How many homes are in INFINITY TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), INFINITY TOWERS has 443 homes in 3 towers registered on MahaRERA, and 95% of them are sold or booked.
When was INFINITY TOWERS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), INFINITY TOWERS was registered on MahaRERA on 19 July 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on INFINITY TOWERS?
9 court cases are listed for INFINITY TOWERS on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of INFINITY TOWERS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is T Bhimjyani Realty Pvt.Ltd., which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of INFINITY TOWERS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Majiwade
- MIRAYA BUSINESS HUB
- VERONA B
- VERONA A
- MIRAYA DIVINE
- RUSTOMJEE LA FAMILIA - WING A
- RUSTOMJEE LA FAMILIA - WING B
- MANGAL HEIGHTS
- ASHAR AXIS
Other projects by T Bhimjyani Realty Pvt.Ltd.
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.