RUSTOMJEE LA FAMILIA - WING B

by Kapstone Constructions Private Limited (Rustomjee) · Majiwade, ThaneAlso near Thane west, Balkum, Kalwa

Possession date of RUSTOMJEE LA FAMILIA - WING B: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700032205, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about RUSTOMJEE LA FAMILIA - WING B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RUSTOMJEE LA FAMILIA - WING B has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RUSTOMJEE LA FAMILIA - WING B’s extension records on MahaRERA (P51700032205), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RUSTOMJEE LA FAMILIA - WING B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 3 court cases, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700032205
Status
Registered and active
Builder
Kapstone Constructions Private Limited
Location
Majiwade, Thane · 400601
Project type
Residential / Group Housing
Registered on
15 Dec 2021
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Towers
1
Complaints on MahaRERA
2
Court cases listed
3
Title report on file
Not found
Builder's other MahaRERA projects
19

Construction progress of RUSTOMJEE LA FAMILIA - WING B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RUSTOMJEE LA FAMILIA - WING B100%87%23%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RUSTOMJEE LA FAMILIA - WING B every month.

RUSTOMJEE LA FAMILIA - WING B: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Kapstone Constructions has 20 projects on MahaRERA since 2017, this one included. Of the 20 GharKundli has checked: 10 finished, all within the promised date; 10 still being built, none past the promised date yet. 28 complaints on MahaRERA across 14 projects.

Read Google reviews of RUSTOMJEE LA FAMILIA - WING B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RUSTOMJEE LA FAMILIA - WING B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RUSTOMJEE LA FAMILIA - WING B

What is the possession date of RUSTOMJEE LA FAMILIA - WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RUSTOMJEE LA FAMILIA - WING B in Majiwade, Thane is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for RUSTOMJEE LA FAMILIA - WING B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RUSTOMJEE LA FAMILIA - WING B's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of RUSTOMJEE LA FAMILIA - WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RUSTOMJEE LA FAMILIA - WING B in Majiwade, Thane is P51700032205.

Is RUSTOMJEE LA FAMILIA - WING B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE LA FAMILIA - WING B is registered as P51700032205 and its status is "Registered and active".

What is the construction status of RUSTOMJEE LA FAMILIA - WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE LA FAMILIA - WING B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RUSTOMJEE LA FAMILIA - WING B is 87% done and internal work 23%. GharKundli's full report compares construction progress with the deadline.

Does RUSTOMJEE LA FAMILIA - WING B have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is RUSTOMJEE LA FAMILIA - WING B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE LA FAMILIA - WING B is registered on MahaRERA as P51700032205, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does RUSTOMJEE LA FAMILIA - WING B have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: RUSTOMJEE LA FAMILIA - WING A (P51700032262, possession 30 Apr 2027); RUSTOMJEE LA FAMILIA- WING C (P51700046128, possession 30 Oct 2027). Check that your agreement names the registration of your own wing.

How can I get updates if RUSTOMJEE LA FAMILIA - WING B's possession date changes?

The latest dates are on RUSTOMJEE LA FAMILIA - WING B's MahaRERA page (P51700032205). GharKundli's Kundli Watch sends a free WhatsApp update on RUSTOMJEE LA FAMILIA - WING B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RUSTOMJEE LA FAMILIA - WING B have?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE LA FAMILIA - WING B has one building filed: RUSTOMJEE LA FAMILIA - WING B with 56 floors.

How big is the land of RUSTOMJEE LA FAMILIA - WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE LA FAMILIA - WING B stands on 3,982 sq m of land (about 1.0 acres), with 28,260 sq m of sanctioned built-up area.

What is the track record of RUSTOMJEE LA FAMILIA - WING B's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Kapstone Constructions has 20 projects on MahaRERA since 2017, this one included. Of the 20 GharKundli has checked: 10 finished, all within the promised date; 10 still being built, none past the promised date yet. 28 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of RUSTOMJEE LA FAMILIA - WING B?

Google Maps has reviews of RUSTOMJEE LA FAMILIA - WING B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RUSTOMJEE LA FAMILIA - WING B?

RUSTOMJEE LA FAMILIA - WING B by Kapstone Constructions Private Limited (Rustomjee) is in Majiwade, Thane (pincode 400601), near Thane west, Balkum, Kalwa, Maharashtra, and is registered on MahaRERA as P51700032205, per GharKundli's check of MahaRERA records.

When was RUSTOMJEE LA FAMILIA - WING B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE LA FAMILIA - WING B was registered on MahaRERA on 15 December 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on RUSTOMJEE LA FAMILIA - WING B?

3 court cases are listed for RUSTOMJEE LA FAMILIA - WING B on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of RUSTOMJEE LA FAMILIA - WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kapstone Constructions Private Limited, the company Rustomjee files this project under, which has 19 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Majiwade

All 178 projects in Thane (400601) →

Other projects by Kapstone Constructions Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.