Skip to content
GharKundli

RUSTOMJEE VERDANT VISTAS WING B

by Kapstone Constructions Private Limited (Rustomjee) · Majiwade, Thane West, ThaneAlso near Balkum, Kalwa

Possession date of RUSTOMJEE VERDANT VISTAS WING B: 20 June 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700077134, and currently active. Its completion date is now June 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about RUSTOMJEE VERDANT VISTAS WING B?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RUSTOMJEE VERDANT VISTAS WING B has moved

  1. 20 February 2030

    Completion date given when the project was registered

  2. 20 June 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: RUSTOMJEE VERDANT VISTAS WING B’s extension records on MahaRERA (P51700077134), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RUSTOMJEE VERDANT VISTAS WING B

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints and 1 court case, and how it ended
  • Construction pace against the June 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700077134
Status
Registered and active
Builder
Kapstone Constructions Private Limited
Location
Majiwade, Thane West, Thane · 400601
Project type
Residential / Group Housing
Registered on
23 Jul 2024
Completion date at registration
February 2030
Latest completion date
June 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
264
Sold or booked
0%
Towers
1
Complaints on MahaRERA
2
Court cases listed
1
Title report on file
Not found
Builder's other MahaRERA projects
19

Construction progress of RUSTOMJEE VERDANT VISTAS WING B, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Wing B0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Wing B: covers 4 B+G/ST.+44 +SERVICE FL. +RECREATION FL.

Latest CC order on MahaRERA: dated 09/10/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RUSTOMJEE VERDANT VISTAS WING B every month.

RUSTOMJEE VERDANT VISTAS WING B: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Kapstone Constructions has 20 projects on MahaRERA since 2017, this one included. Of the 20 GharKundli has checked: 10 finished, all within the promised date; 10 still being built, none past the promised date yet. 28 complaints on MahaRERA across 14 projects.

Read Google reviews of RUSTOMJEE VERDANT VISTAS WING B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RUSTOMJEE VERDANT VISTAS WING B: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RUSTOMJEE VERDANT VISTAS WING B

What is the possession date of RUSTOMJEE VERDANT VISTAS WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RUSTOMJEE VERDANT VISTAS WING B in Majiwade, Thane West, Thane is 20 June 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for RUSTOMJEE VERDANT VISTAS WING B?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RUSTOMJEE VERDANT VISTAS WING B's builder has filed on MahaRERA, the official one, is 20 June 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of RUSTOMJEE VERDANT VISTAS WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RUSTOMJEE VERDANT VISTAS WING B in Majiwade, Thane West, Thane is P51700077134.

Is RUSTOMJEE VERDANT VISTAS WING B registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE VERDANT VISTAS WING B is registered as P51700077134 and its status is "Registered and active".

What is the construction status of RUSTOMJEE VERDANT VISTAS WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE VERDANT VISTAS WING B's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing B is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does RUSTOMJEE VERDANT VISTAS WING B have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is RUSTOMJEE VERDANT VISTAS WING B safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE VERDANT VISTAS WING B is registered on MahaRERA as P51700077134, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does RUSTOMJEE VERDANT VISTAS WING B have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: RUSTOMJEE VERDANT VISTAS WING A (P51700077136, possession 18 Jan 2030). Check that your agreement names the registration of your own wing.

How can I get updates if RUSTOMJEE VERDANT VISTAS WING B's possession date changes?

The latest dates are on RUSTOMJEE VERDANT VISTAS WING B's MahaRERA page (P51700077134). GharKundli's Kundli Watch sends a free WhatsApp update on RUSTOMJEE VERDANT VISTAS WING B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RUSTOMJEE VERDANT VISTAS WING B have?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE VERDANT VISTAS WING B has one building filed: Wing B with 51 floors and 264 units.

How much parking does RUSTOMJEE VERDANT VISTAS WING B have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 500 covered car parking spaces for RUSTOMJEE VERDANT VISTAS WING B.

How big is the land of RUSTOMJEE VERDANT VISTAS WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE VERDANT VISTAS WING B stands on 1,178 sq m of land (about 0.3 acres), with 38,569 sq m of sanctioned built-up area.

What is the track record of RUSTOMJEE VERDANT VISTAS WING B's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Kapstone Constructions has 20 projects on MahaRERA since 2017, this one included. Of the 20 GharKundli has checked: 10 finished, all within the promised date; 10 still being built, none past the promised date yet. 28 complaints on MahaRERA across 14 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of RUSTOMJEE VERDANT VISTAS WING B?

Google Maps has reviews of RUSTOMJEE VERDANT VISTAS WING B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RUSTOMJEE VERDANT VISTAS WING B?

RUSTOMJEE VERDANT VISTAS WING B by Kapstone Constructions Private Limited (Rustomjee) is in Majiwade, Thane West, Thane (pincode 400601), near Balkum, Kalwa, Maharashtra, and is registered on MahaRERA as P51700077134, per GharKundli's check of MahaRERA records.

How many homes are in RUSTOMJEE VERDANT VISTAS WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE VERDANT VISTAS WING B has 264 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was RUSTOMJEE VERDANT VISTAS WING B registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RUSTOMJEE VERDANT VISTAS WING B was registered on MahaRERA on 23 July 2024. GharKundli did not find a title report on the land on file there.

Are there court cases on RUSTOMJEE VERDANT VISTAS WING B?

1 court case is listed for RUSTOMJEE VERDANT VISTAS WING B on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of RUSTOMJEE VERDANT VISTAS WING B?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kapstone Constructions Private Limited, the company Rustomjee files this project under, which has 19 other projects registered on MahaRERA.

All projects with possession due in 2030 in Thane →

Other projects in pincode 400601

All 178 projects in Thane (400601) →

Other projects by Kapstone Constructions Private Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.