URMILA CO-OPERATIVE HOUSING SOCIETY LTD
by Poonam Developers · ThaneAlso near Naupada, Majiwada, Badlapur
Possession date of URMILA CO-OPERATIVE HOUSING SOCIETY LTD: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1330002500774, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
How the possession date of URMILA CO-OPERATIVE HOUSING SOCIETY LTD has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: URMILA CO-OPERATIVE HOUSING SOCIETY LTD’s extension records on MahaRERA (PR1330002500774), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on URMILA CO-OPERATIVE HOUSING SOCIETY LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1330002500774
- Status
- Registered and active
- Builder
- Poonam Developers
- Location
- Thane · 400601
- Project type
- Residential / Group Housing
- Registered on
- 15 Sep 2025
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 18
- Sold or booked
- 30%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of URMILA CO-OPERATIVE HOUSING SOCIETY LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Urmila Co-Operative Housing Society Ltd | 100% | 12.5% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Urmila Co-Operative Housing Society Ltd: covers 8 floors
Latest CC order on MahaRERA: dated 16/06/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on URMILA CO-OPERATIVE HOUSING SOCIETY LTD every month.
URMILA CO-OPERATIVE HOUSING SOCIETY LTD: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 313 – 485 | 20 |
| Shops | 35 – 220 | 8 |
- Buildings: Urmila Co-Operative Housing Society Ltd (8 floors, 28 units)
- Car parking: 12 covered
- Land: 563 sq m (about 0.1 acres) · sanctioned built-up 1,041 sq m
- Boundaries filed include: 30 Meter LBS Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of URMILA CO-OPERATIVE HOUSING SOCIETY LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
URMILA CO-OPERATIVE HOUSING SOCIETY LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about URMILA CO-OPERATIVE HOUSING SOCIETY LTD
What is the possession date of URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for URMILA CO-OPERATIVE HOUSING SOCIETY LTD in Thane is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date URMILA CO-OPERATIVE HOUSING SOCIETY LTD's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of URMILA CO-OPERATIVE HOUSING SOCIETY LTD in Thane is PR1330002500774.
Is URMILA CO-OPERATIVE HOUSING SOCIETY LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), URMILA CO-OPERATIVE HOUSING SOCIETY LTD is registered as PR1330002500774 and its status is "Registered and active".
What is the construction status of URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), URMILA CO-OPERATIVE HOUSING SOCIETY LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Urmila Co-Operative Housing Society Ltd is 12.5% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does URMILA CO-OPERATIVE HOUSING SOCIETY LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is URMILA CO-OPERATIVE HOUSING SOCIETY LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), URMILA CO-OPERATIVE HOUSING SOCIETY LTD is registered on MahaRERA as PR1330002500774, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if URMILA CO-OPERATIVE HOUSING SOCIETY LTD's possession date changes?
The latest dates are on URMILA CO-OPERATIVE HOUSING SOCIETY LTD's MahaRERA page (PR1330002500774). GharKundli's Kundli Watch sends a free WhatsApp update on URMILA CO-OPERATIVE HOUSING SOCIETY LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does URMILA CO-OPERATIVE HOUSING SOCIETY LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), URMILA CO-OPERATIVE HOUSING SOCIETY LTD has one building filed: Urmila Co-Operative Housing Society Ltd with 8 floors and 28 units.
How much parking does URMILA CO-OPERATIVE HOUSING SOCIETY LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for URMILA CO-OPERATIVE HOUSING SOCIETY LTD.
How big is the land of URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), URMILA CO-OPERATIVE HOUSING SOCIETY LTD stands on 563 sq m of land (about 0.1 acres), with 1,041 sq m of sanctioned built-up area.
Where can I read reviews of URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
Google Maps has reviews of URMILA CO-OPERATIVE HOUSING SOCIETY LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
URMILA CO-OPERATIVE HOUSING SOCIETY LTD by Poonam Developers is in Thane (pincode 400601), near Naupada, Majiwada, Badlapur, Maharashtra, and is registered on MahaRERA as PR1330002500774, per GharKundli's check of MahaRERA records. Its boundaries filed there include 30 Meter LBS Road.
How many homes are in URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), URMILA CO-OPERATIVE HOUSING SOCIETY LTD has 18 homes in 1 tower registered on MahaRERA, and 30% of them are sold or booked.
When was URMILA CO-OPERATIVE HOUSING SOCIETY LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), URMILA CO-OPERATIVE HOUSING SOCIETY LTD was registered on MahaRERA on 15 September 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
No court cases are listed for URMILA CO-OPERATIVE HOUSING SOCIETY LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of URMILA CO-OPERATIVE HOUSING SOCIETY LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Poonam Developers.
Check it yourself on MahaRERA
- How to check the possession date of URMILA CO-OPERATIVE HOUSING SOCIETY LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in pincode 400601
- RAJ TATTVA PHASE 1 COMMERCIAL
- Phatak Wada
- SHRIKRISHNA RESIDENCY COOPERATIVE HOUSING SOCIETY LIMITED
- Bliss
- NAV SULOCHANA CO-OPERATIVE HOUSING SOCIETY LIMITED
- SHREE GANGADHAR CHSL
- Panache
- Devshrushti Co-op. Hsg Soc. Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.