Phatak Wada

by Aditya Associates · Tembhi Naka, ThaneAlso near Naupada, Charai, Chendani

Possession date of Phatak Wada: 15 February 2027, moved from 30 June 2025 (16 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700049073, and currently active. Its completion date has moved from June 2025 to February 2027: 16 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Phatak Wada?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Phatak Wada has moved

  1. 30 June 2025

    Completion date given when the project was registered

  2. 15 October 2026

    Extended at the builder's request (MahaRERA application EA30012619636)

    Reason the builder gave MahaRERA: “Delay in Receiving Occupancy Certificate”
  3. 15 February 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Phatak Wada’s extension records on MahaRERA (P51700049073), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Phatak Wada

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the February 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700049073
Status
Registered and active
Builder
Aditya Associates
Location
Tembhi Naka, Thane · 400601
Project type
Others
Registered on
30 Jan 2023
Completion date at registration
June 2025
Latest completion date
February 2027
Delay so far
16 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
49
Sold or booked
33%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
25

Construction progress of Phatak Wada, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Phatak Wada100%100%15%0%

Commencement certificate (CC), as filed on MahaRERA

  • Phatak Wada: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Phatak Wada every month.

Phatak Wada: buildings, flats and land, as filed on MahaRERA

  • Buildings: Phatak Wada (9 floors, 58 units)
  • Car parking: 48 covered
  • Land: 916 sq m (about 0.2 acres) · sanctioned built-up 3,964 sq m
  • Boundaries filed include: Wadia Hospital, Veer Savarkar Road, B J High School
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Aditya Associates has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 8 finished, 4 within the promised date and 4 needed more time (typically 10 months); 4 still being built, 1 past the promised date (typically 12 months late). No complaints on MahaRERA.

Read Google reviews of Phatak Wada →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Phatak Wada: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Phatak Wada

What is the possession date of Phatak Wada?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Phatak Wada in Tembhi Naka, Thane is 15 February 2027 — 16 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Phatak Wada?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Phatak Wada's builder has filed on MahaRERA, the official one, is 15 February 2027, already 16 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Phatak Wada extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Phatak Wada's builder applied to MahaRERA to extend the completion date once: to 15 October 2026, giving the reason "Delay in Receiving Occupancy Certificate". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Phatak Wada?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Phatak Wada in Tembhi Naka, Thane is P51700049073.

Is Phatak Wada registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Phatak Wada is registered as P51700049073 and its status is "Registered and active".

What is the construction status of Phatak Wada?

According to GharKundli's check of MahaRERA records (updated October 2026), Phatak Wada's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Phatak Wada is 100% done and internal work 15%. GharKundli's full report compares construction progress with the deadline.

Does Phatak Wada have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Phatak Wada safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Phatak Wada is registered on MahaRERA as P51700049073, its completion date has moved 16 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Phatak Wada's possession date changes?

The latest dates are on Phatak Wada's MahaRERA page (P51700049073). GharKundli's Kundli Watch sends a free WhatsApp update on Phatak Wada every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Phatak Wada have?

According to GharKundli's check of MahaRERA records (updated October 2026), Phatak Wada has one building filed: Phatak Wada with 9 floors and 58 units.

How much parking does Phatak Wada have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 48 covered car parking spaces for Phatak Wada.

How big is the land of Phatak Wada?

According to GharKundli's check of MahaRERA records (updated October 2026), Phatak Wada stands on 916 sq m of land (about 0.2 acres), with 3,964 sq m of sanctioned built-up area.

What is the track record of Phatak Wada's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Aditya Associates has 12 projects on MahaRERA since 2017, this one included. Of the 12 GharKundli has checked: 8 finished, 4 within the promised date and 4 needed more time (typically 10 months); 4 still being built, 1 past the promised date (typically 12 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Phatak Wada?

Google Maps has reviews of Phatak Wada written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Phatak Wada?

Phatak Wada by Aditya Associates is in Tembhi Naka, Thane (pincode 400601), near Naupada, Charai, Chendani, Maharashtra, and is registered on MahaRERA as P51700049073, per GharKundli's check of MahaRERA records. Its boundaries filed there include Wadia Hospital, Veer Savarkar Road, B J High School.

How many homes are in Phatak Wada?

According to GharKundli's check of MahaRERA records (updated October 2026), Phatak Wada has 49 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.

When was Phatak Wada registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Phatak Wada was registered on MahaRERA on 30 January 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Phatak Wada?

No court cases are listed for Phatak Wada on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Phatak Wada?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aditya Associates, which has 25 other projects registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Tembhi Naka

All 178 projects in Thane (400601) →

Other projects by Aditya Associates

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.