MahaRERA projects in Mumbra, Thane (400612)
According to GharKundli's check of MahaRERA records, 188 housing projects are registered in pincode 400612 (Mumbra, Thane). 102 are still being built, 31 with possession due by the end of 2027. For 132, the completion date on MahaRERA is later than the one first promised. 35 have at least one complaint filed on MahaRERA.
Pincode 400612 also covers: Kausa, Dawale, Shil, Kausa Mumbra, Kausa, Mumbra, Betawade Gaon.
“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.
| Project | MahaRERA status | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| Sai Shrushti Valley - Phase II / Ramchandra Complex SAI SHRUSHTI ENTERPRISES | Abeyance | 30 Jun 2024passed | same | 0 |
| NICE GARDEN 2 ABHA BUILDERS | Active | 31 Oct 2026passed | 30 Dec 2025 | 0 |
| YES CENTRAL GALLERIA 1 YES ENTERPRISES | Active | 31 Oct 2026passed | same | 0 |
| Nasam Darul Amaan Wing A and B NEW INDIA CONSTRUCTION | Active | 30 Dec 2026 | 30 Jun 2024 | 18 |
| ASHA KIRAN ASHAPURA DEVELOPERS | Active | 31 Dec 2026 | 31 Dec 2023 | 0 |
| JAGJEET ENCLAVE JAGJEET SHRUSTI REALTORS | Active | 31 Dec 2026 | 4 May 2024 | 14 |
| MARINA VIRANI CONSTRUCTION COMPANY | Active | 31 Dec 2026 | 1 Apr 2026 | 0 |
| CELOSIA AVENUE PRATIMA CONSTRUCTION | Active | 30 Jan 2027 | 30 Sep 2025 | 0 |
| FATIMA ENCLAVE- A & B RAIS AZIZ QURESHI | Active | 31 Mar 2027 | 30 Dec 2023 | 0 |
| SAGAR ENCLAVE KANCHAN BUILDERS & DEVELOPERS | Active | 25 Apr 2027 | 25 Dec 2025 | 0 |
| CHANDRANGAN RESIDENCY PHASE-IV EKVEERA ENTERPRISES | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| ELITE RESIDENCE - C ELITE REALTY | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| MARATHON NEXWORLD NOVA Sunset Spaces Pvt. Ltd. | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| PLANET HOMES I G BUILDERS | Active | 30 Apr 2027 | 30 Dec 2021 | 1 |
| RAMESHWAR PARK - DAFFODIL C RAMESHAWAR BUILDERS & DEVELOPERS | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| SHIVA AMRUT ESTATE D WING SHIVA AMRUT ENTERPERISES | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| SHREE SIDDHGANESH TAPOVAN SHREE SIDDHGANESH ENTERPRISES | Active | 30 Apr 2027 | 30 Jun 2022 | 0 |
| SILVER LIFESTYLE SILVERLINE BUILDHEIGHT LLP | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| SWASTIK FLORESTA D P HOMES INFRAPROJECTS PRIVATE LIMITED | Active | 30 Apr 2027 | 30 Mar 2023 | 6 |
| AL-QUDDUS RESIDENCY ALLIANCE REALTY | Active | 30 Jun 2027 | 30 Jun 2020 | 3 |
| NEXUS PARK NEXUS GROUP | Active | 30 Jun 2027 | 30 Jun 2026 | 0 |
| ALISHAN ARCADE - BUILDING NO. B1 PATANGWALA ASSOCIATES | Active | 31 Jul 2027 | 31 Mar 2027 | 0 |
| FATIMA ENCLAVE- C WING RAIS AZIZ QURESHI | Active | 31 Jul 2027 | 31 Dec 2025 | 0 |
| FATIMA ENCLAVE- D WING RAIS AZIZ QURESHI | Active | 31 Jul 2027 | 31 Dec 2024 | 1 |
| LAXMI AANGAN - MAHANADI, KRISHNA AND GANGA Kanji Murji Mange | Active | 31 Jul 2027 | 31 Mar 2027 | 0 |
| LAXMI MAJESTIC Kanji Murji Mange | Active | 31 Jul 2027 | 31 Mar 2027 | 0 |
| SK HEIGHTS ITTEHAD REALTIES | Active | 31 Jul 2027 | 31 Mar 2027 | 0 |
| CHANGUNA AANGAN SAMRIN DREAMSPACES PRIVATE LTD | Active | 30 Oct 2027 | 31 Dec 2025 | 0 |
| YES CENTRAL GALLERIA NOBLE ENTERPRISES | Active | 31 Oct 2027 | 31 Oct 2026 | 0 |
| JNP RESIDENCY AL-SIRAJ BUILDERS & DEVELOPERS | Active | 30 Nov 2027 | 31 Jul 2027 | 0 |
| SAFA COMPLEX SAFA ENTERPRISES | Active | 30 Dec 2027 | 30 Dec 2025 | 0 |
| The Heavens Palace Phase II GAYASUDDIN RIYAZUDDIN KHAN | Active | 1 Apr 2028 | 1 Dec 2027 | 0 |
| The Heavens Palace Phase III GAYASUDDIN RIYAZUDDIN KHAN | Active | 1 Apr 2028 | 1 Dec 2027 | 0 |
| AMBER ELLANCE A-2 AAKASH CORPORATION | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Celeste 612 Hiralal Ramnarayan Gupta | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| CENTRAL MEADOWS HONOUR REALTY | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| CENTRAL PARK HARMAIN ENTERPRISES | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| CHANDRANGAN RESIDENCY PHASE-V EKVEERA ENTERPRISES | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| MARATHON NEXWORLD FLORA Sunset Spaces Pvt. Ltd. | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| MUKTA AVENUE MATOSHREE SPACE BUILDERS AND DEVELOPERS | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| RAMESHWAR PARK - A1 AND A2 RAMESHAWAR BUILDERS & DEVELOPERS | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| DOSTI PLANET NORTH - DOSTI CROWN CHALAMA INFRAPROPERTIES PRIVATE LIMITED (Dosti) | Active | 31 Jul 2028 | 31 Mar 2028 | 0 |
| Samruddhi Residency SHREE SAI GANESH DEVELOPERS | Active | 30 Oct 2028 | 30 Jun 2025 | 0 |
| AL BALAD RESIDENCY UNITY INFRA | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Al- Maqaam Eminent Constructions | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| AMBER ELITE AMBER REALTY | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| ATLANTAA ENCLAVE - II ATLANTAA LIMITED | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| AVENUE BUILDBRICK BUILDERS AND DEVELOPERS | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| BARKAT MANZIL YES REDEVELOPMENT CONSTRUCTIONS | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| DOSTI PLANET NORTH - SECTOR 3 CHALAMA INFRAPROPERTIES PRIVATE LIMITED (Dosti) | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
138 more projects
- Karnika Galaxy Phase 2 · 30 Apr 2029
- Mustafa Empire · 30 Apr 2029
- ROSE PALACE · 30 Apr 2029
- Sky Heights Tower No. 4 · 30 Apr 2029
- SKY VALLEY - PHASE 1 · 30 Apr 2029
- ZUBAIR ENCLAVE · 30 Apr 2029
- A1 · 31 Jul 2029
- LAXMI AANGAN - KAVERI · 31 Jul 2029
- SOLITAIRE HEIGHTS · 31 Jul 2029
- AL BALAD RESIDENCY II · 30 Oct 2029
- Dream land · 30 Oct 2029
- KANHA KALINDI · 30 Oct 2029
- ASIM RESIDENCY · 31 Dec 2029
- KASHAF RESIDENCY · 31 Dec 2029
- VITHAI RESIDENCY · 31 Dec 2029
- STAR LIVINGS · 28 Feb 2030
- Kohinoor Imperia · 31 Mar 2030
- Al-Taiba Tower · 30 Apr 2030
- CENTRAL PLAZA · 30 Apr 2030
- Grace Square D1 and D2 · 30 Apr 2030
- Prince Tower · 30 Apr 2030
- DZ CITY - BUILDING NO 1 · 30 Jun 2030
- DZ CITY - BUILDING NO 2 · 30 Jun 2030
- Trinity Phase 2 · 31 Jul 2030
- Sahyadri Lifespaces · 14 Oct 2030
- ARENA SQUARE · 30 Oct 2030
- DZ CITY - BUILDING NO 3 · 30 Oct 2030
- DZ CITY BLDG No. 4 and 5 · 31 Dec 2030
- Radha Krishna Homes · 31 Dec 2030
- SKY VALLEY - PHASE 2 · 31 Dec 2030
- AL MAWADAH RESIDENCY · 30 Apr 2031
- HIRA RESIDENCY PHASE II · 30 Apr 2031
- Narayan Residency · 30 Apr 2031
- Ocean Green · 30 Apr 2031
- SHIV SHRIDITYA HEIGHTS · 30 Apr 2031
- Sky Heights Tower No. 3 · 30 Apr 2031
- Harmain Tower · 31 Jul 2031
- AHS TOWER · 7 Aug 2031
- FBKA Jewels · 27 Oct 2031
- Signature · 31 Dec 2031
- Sky Heights Tower No 2 · 1 Apr 2032
- Balaji Classica - NOVA · 30 Apr 2032
- ELITE TOWER · 30 Apr 2032
- GRAND MERIDIAN CITY · 30 Apr 2032
- MEK GRAND CENTRAL · 30 Apr 2032
- MM VALLEY D1 D2 · 30 Apr 2032
- NICE WORLD 1 · 30 Apr 2032
- VASANI DREAM CITY · 30 Apr 2032
- The Aura · 30 Apr 2033
- NOBLE SKY · 30 Apr 2034
- Palm Riveria · 30 Apr 2034
- NICE WORLD 2 · 30 Apr 2035
- MY CITY - PHASE I - PART II · completed
- QUALITY HEIGHTS I · completed
- RAMESHWAR PARK (ORCHID, IRIS & ROSE) · completed
- SAPPHIRE B · completed
- Mera Ghar · completed
- Ewar Complex · completed
- MUKATA LAKE CITY · completed
- OM RESIDENCY · completed
- Heena enterprises · completed
- SAFFRON ENCLAVES · completed
- SAI SHRUSHTI SAPPHIRE · completed
- Sai Shrushti Sapphire B-1 · completed
- SHIV AMRUT · completed
- RAMESHWAR PARK - LILAC · completed
- S K RESIDENCY · completed
- BELLAMONTE · completed
- KOYNA · completed
- AND LILY · completed
- Mukta Lake City · completed
- MY CITY - PHASE I - PART I · completed
- RAMESHWAR PARK - DAFFODIL A · completed
- SAI SHRUSHTI SAPPHIRE PLOT A-1 · completed
- SAI SHRUSHTI ANNEX · completed
- BLUEBELLS · completed
- MARATHON NEXWORLD AURA-1 · completed
- KARNIKA GALAXY · completed
- LAXMI GALAXY · completed
- SAI SHRUSHTI VALLEY - PHASE 1/RAMCHANDRA COMPLEX · completed
- The Universe - Mercury · completed
- MARATHON NEXWORLD AURA-2 · completed
- AND ROSE · completed
- The Universe Neptune - B · completed
- SAI SHRUSHTI HERITAGE · completed
- RADHE KRISHNA RESIDENCY · completed
- DOSTI PLANET NORTH - PHASE 3 -DOSTI ONYX · completed
- DOSTI PLANET NORTH- PHASE 4 - DOSTI OPAL · completed
- HUDA PARK · completed
- MM VALLEY A-1 · completed
- KABINI · completed
- M M CITY · completed
- NICE GARDEN 1 · completed
- GRACE SQUARE TYPE D3 · completed
- CHANDRANGAN RESIDENCY PHASE-III · completed
- ELITE RESIDENCE - A · completed
- ELITE RESIDENCE - B · completed
- KANISHKA PLAZA · completed
- MARATHON NEXWORLD AURA-3 · completed
- DIAMOND PARK · 31 Dec 2019
- MAGNUS MARYAM · 30 Mar 2022
- RAMSAI APARTMENT - B WING · 30 Jun 2022
- Silver Enclave · 30 Mar 2023
- IMPERIAL TOWER A2 · 30 Dec 2023
- NEPTUNE · 30 Dec 2023
- SHREE VIGNAHARTA RESIDENCY BUILDING NO B3, B4, B5 AND B6 · 31 Dec 2023
- MARATHON NEXWORLD ELARA-1 · 29 Jun 2024
- ROSE NAGAR · 30 Jun 2024
- RAMCHANDRA RESIDENCY · 31 Aug 2024
- SUDAMA REGENCY BUILDING NO 2,3,4 · 29 Dec 2024
- DIVINE HEIGHTS · 30 Dec 2024
- IMPERIAL TOWER A1 · 30 Dec 2024
- MARATHON NEXWORLD ELARA-2 · 30 Dec 2024
- SIDDIQUEE ENCLAVE · 31 Dec 2024
- RAMESHWAR PARK - DAFFODIL B · 30 Mar 2025
- CENTRAL HEIGHTS · 1 Apr 2025
- GREEN VALLEY PHASE I · 1 Apr 2025
- SAI KANISHK PHASE II · 30 Jun 2025
- SD EMPIRE · 30 Jun 2025
- SIDDIQUEE COMPLEX · 30 Jun 2025
- AL HADI RESIDENTIAL COMPLEX PHASE II · 30 Sep 2025
- PIYUSH MAJESTIC -NX · 30 Sep 2025
- SILVER RESIDENCY · 29 Oct 2025
- MUKTA GHARONDA · 29 Dec 2025
- Archit Jewel · 31 Dec 2025
- BELLAVISTA · 31 Dec 2025
- Sai Shrushti Vatika Gajanan Alimkar · 31 Dec 2025
- Trinity Paradise Phase 1 · 31 Mar 2026
- CROWN RESIDENCY · 31 Jul 2026
- CENTRAL EMPIRE · 30 Oct 2026
- AMMAR MEADOWS PHASE 2 · —
- AND SUNFLOWER · —
- M M VALEY A2 · —
- M M VALLEY C1 · —
- MY CITY - PHASE I - PART III · —
- NIRMAL NAGARI · —
- SAI KANISHK PHASE I · —
- SUDAMA REGENCY BUILDING NO 1, 5 · —
Other areas in Thane
- Kulgaon · 735
- Kalyan · 510
- Ambernath · 403
- Tilaknagar · 354
- Bhiwandi · 348
- Mira Road East · 277
- Kalyan East · 250
- Manpada · 232
- Naupada · 223
- Vishnunagar · 198
- Sandozbaugh · 180
- Thane · 161
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.