Narayan Shiv Shriditya Heights

by SHREE NARAYAN ENTERPRISES · Mumbra, Thane 400612Also near Village Shil, Daighar Village, Tembhi NakaRegistered on MahaRERA as “SHIV SHRIDITYA HEIGHTS”

What’s in the report? →

Possession date of Narayan Shiv Shriditya Heights (MahaRERA PM1330002601057): 30 April 2031. It has 195 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1330002601057, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PM1330002601057, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Narayan Shiv Shriditya Heights?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Narayan Shiv Shriditya Heights has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Narayan Shiv Shriditya Heights’s extension records on MahaRERA (PM1330002601057), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Narayan Shiv Shriditya Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1330002601057
Status
Registered and active
Builder
SHREE NARAYAN ENTERPRISES
Location
Mumbra, Thane · 400612
Project type
Mixed
Registered on
6 Jul 2026
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
195
Sold or booked
0%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Narayan Shiv Shriditya Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHIV SHRIDITYA HEIGHTS0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • SHIV SHRIDITYA HEIGHTS: covers 23 floors

Latest CC order on MahaRERA: dated 29/04/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Narayan Shiv Shriditya Heights every 1–2 months.

Narayan Shiv Shriditya Heights: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Shree Narayan Enterprises has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of Narayan Shiv Shriditya Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Narayan Shiv Shriditya Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Narayan Shiv Shriditya Heights

What is the possession date of Narayan Shiv Shriditya Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Narayan Shiv Shriditya Heights in Mumbra, Thane is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Narayan Shiv Shriditya Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Narayan Shiv Shriditya Heights's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Narayan Shiv Shriditya Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Narayan Shiv Shriditya Heights in Mumbra, Thane is PM1330002601057.

Is Narayan Shiv Shriditya Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights is registered as PM1330002601057 and its status is "Registered and active".

What is the current construction status of Narayan Shiv Shriditya Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHIV SHRIDITYA HEIGHTS is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Narayan Shiv Shriditya Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Narayan Shiv Shriditya Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights is registered on MahaRERA as PM1330002601057, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Narayan Shiv Shriditya Heights?

Narayan Shiv Shriditya Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Narayan Shiv Shriditya Heights?

For a flat in Narayan Shiv Shriditya Heights (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Narayan Shiv Shriditya Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights is still under construction, with 30 April 2031 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Narayan Shiv Shriditya Heights a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights's planning authority on MahaRERA is TMCB-26-28382, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.

Has Narayan Shiv Shriditya Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Narayan Shiv Shriditya Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Narayan Shiv Shriditya Heights's possession date changes?

The latest dates are on Narayan Shiv Shriditya Heights's MahaRERA page (PM1330002601057). GharKundli's Kundli Watch sends a free WhatsApp update on Narayan Shiv Shriditya Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Narayan Shiv Shriditya Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights has one building filed: SHIV SHRIDITYA HEIGHTS with 23 floors and 213 units.

How much parking does Narayan Shiv Shriditya Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 48 covered car parking spaces for Narayan Shiv Shriditya Heights.

How big is the land of Narayan Shiv Shriditya Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights stands on 3,320 sq m of land (about 0.8 acres), with 10,646 sq m of sanctioned built-up area.

What is the track record of Narayan Shiv Shriditya Heights's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Shree Narayan Enterprises has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 2 finished, all within the promised date; 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Narayan Shiv Shriditya Heights?

Google Maps has reviews of Narayan Shiv Shriditya Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Narayan Shiv Shriditya Heights?

Narayan Shiv Shriditya Heights by SHREE NARAYAN ENTERPRISES is in Mumbra, Thane, pincode 400612 (near Village Shil, Daighar Village, Tembhi Naka), Maharashtra, and is registered on MahaRERA as PM1330002601057, per GharKundli's check of MahaRERA records. GharKundli lists all 225 MahaRERA projects in Mumbra (400612).

How many flats are in Narayan Shiv Shriditya Heights, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights has 195 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Narayan Shiv Shriditya Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Narayan Shiv Shriditya Heights was registered on MahaRERA on 6 July 2026. GharKundli did not find a title report on the land on file there.

Does Narayan Shiv Shriditya Heights have any legal issues or court cases?

No court cases are listed for Narayan Shiv Shriditya Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Narayan Shiv Shriditya Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE NARAYAN ENTERPRISES, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2031 in Thane →

Other projects in Mumbra (400612)

All 225 projects in Mumbra (400612) →

Other projects by SHREE NARAYAN ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.