DZ CITY BLDG No. 4 and 5

by SKYLINE ENTERPRISES · Mumbra, ThaneAlso near Kausa, Betawade Gaon, Kurla

Possession date of DZ CITY BLDG No. 4 and 5: 31 December 2030, moved from 30 June 2026 (54 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700031434, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about DZ CITY BLDG No. 4 and 5?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of DZ CITY BLDG No. 4 and 5 has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 31 December 2030

    Extended at the builder's request (MahaRERA application EA30062621630)

    Reason the builder gave MahaRERA:
    “Subject: Request for Extension of MahaRERA Project Registration u/s 7(3) Project: DZ CITY BLDG No. 4 and 5 RERA Registration Number: P51700031434. With reference to the above subject, we respectfully submit that the above-mentioned project…” Read the full reason“Subject: Request for Extension of MahaRERA Project Registration u/s 7(3) Project: DZ CITY BLDG No. 4 and 5 RERA Registration Number: P51700031434. With reference to the above subject, we respectfully submit that the above-mentioned project was registered with MahaRERA on 23 October 2021, with the original completion date of 30 June 2026. The project comprises two buildings, namely Building No. 4 and Building No. 5, each proposed to consist of 22 floors. However, the Commencement Certificate (CC) was granted only up to 11 floors for Building No. 4 and 10 floors for Building No. 5, and the RC…”

Source: DZ CITY BLDG No. 4 and 5’s extension records on MahaRERA (P51700031434), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on DZ CITY BLDG No. 4 and 5

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700031434
Status
Registered and active
Builder
SKYLINE ENTERPRISES
Location
Mumbra, Thane · 400612
Project type
Residential / Group Housing
Registered on
23 Oct 2021
Completion date at registration
June 2026
Latest completion date
December 2030
Delay so far
54 months
Homes
148
Sold or booked
81%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
10

Construction progress of DZ CITY BLDG No. 4 and 5, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 4100%100%85%25%
BUILDING NO 5100%100%85%25%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING NO 4: covers 12 floors
  • BUILDING NO 5: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on DZ CITY BLDG No. 4 and 5 every month.

DZ CITY BLDG No. 4 and 5: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 4 (23 floors, 97 units) · BUILDING NO 5 (23 floors, 113 units)
  • Land: 6,495 sq m (about 1.6 acres) · sanctioned built-up 7,656 sq m · recreational space 2,282 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Crown Builders AND Developers (a group of 3 linked companies) has 4 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of DZ CITY BLDG No. 4 and 5 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

DZ CITY BLDG No. 4 and 5: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about DZ CITY BLDG No. 4 and 5

What is the possession date of DZ CITY BLDG No. 4 and 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DZ CITY BLDG No. 4 and 5 in Mumbra, Thane is 31 December 2030 — 54 months later than 30 June 2026, the date given at registration.

Is the builder's possession date different from the MahaRERA date for DZ CITY BLDG No. 4 and 5?

Builders and listing sites often quote an earlier "target" date for handover. The completion date DZ CITY BLDG No. 4 and 5's builder has filed on MahaRERA, the official one, is 31 December 2030, already 54 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of DZ CITY BLDG No. 4 and 5 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), DZ CITY BLDG No. 4 and 5's builder applied to MahaRERA to extend the completion date once: to 31 December 2030, giving the reason "Subject: Request for Extension of MahaRERA Project Registration u/s 7(3) Project: DZ CITY BLDG No. 4 and 5 RERA Registration Number: P51700031434. With reference to the above subject, we respectfully submit that the above-mentioned project was registered with MahaRERA on 23 October 2021, with the original completion date of 30 June 2026. The project comprises two buildings, namely Building No. 4 and Building No. 5, each proposed to consist of 22 floors. However, the Commencement Certificate (CC) was granted only up to 11 floors for Building No. 4 and 10 floors for Building No. 5, and the RC…".

What is the RERA number of DZ CITY BLDG No. 4 and 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DZ CITY BLDG No. 4 and 5 in Mumbra, Thane is P51700031434.

Is DZ CITY BLDG No. 4 and 5 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DZ CITY BLDG No. 4 and 5 is registered as P51700031434 and its status is "Registered and active".

What is the construction status of DZ CITY BLDG No. 4 and 5?

According to GharKundli's check of MahaRERA records (updated October 2026), DZ CITY BLDG No. 4 and 5's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does DZ CITY BLDG No. 4 and 5 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is DZ CITY BLDG No. 4 and 5 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), DZ CITY BLDG No. 4 and 5 is registered on MahaRERA as P51700031434, its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if DZ CITY BLDG No. 4 and 5's possession date changes?

The latest dates are on DZ CITY BLDG No. 4 and 5's MahaRERA page (P51700031434). GharKundli's Kundli Watch sends a free WhatsApp update on DZ CITY BLDG No. 4 and 5 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does DZ CITY BLDG No. 4 and 5 have?

According to GharKundli's check of MahaRERA records (updated October 2026), DZ CITY BLDG No. 4 and 5 has 2 buildings filed: BUILDING NO 4 with 23 floors and 97 units; BUILDING NO 5 with 23 floors and 113 units.

How big is the land of DZ CITY BLDG No. 4 and 5?

According to GharKundli's check of MahaRERA records (updated October 2026), DZ CITY BLDG No. 4 and 5 stands on 6,495 sq m of land (about 1.6 acres), with 7,656 sq m of sanctioned built-up area and 2,282 sq m of recreational open space.

What is the track record of DZ CITY BLDG No. 4 and 5's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Crown Builders AND Developers (a group of 3 linked companies) has 4 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 2 still being built, 1 past the promised date; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of DZ CITY BLDG No. 4 and 5?

Google Maps has reviews of DZ CITY BLDG No. 4 and 5 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is DZ CITY BLDG No. 4 and 5?

DZ CITY BLDG No. 4 and 5 by SKYLINE ENTERPRISES is in Mumbra, Thane (pincode 400612), near Kausa, Betawade Gaon, Kurla, Maharashtra, and is registered on MahaRERA as P51700031434, per GharKundli's check of MahaRERA records.

How many homes are in DZ CITY BLDG No. 4 and 5?

According to GharKundli's check of MahaRERA records (updated October 2026), DZ CITY BLDG No. 4 and 5 has 148 homes in 2 towers registered on MahaRERA, and 81% of them are sold or booked.

When was DZ CITY BLDG No. 4 and 5 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), DZ CITY BLDG No. 4 and 5 was registered on MahaRERA on 23 October 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on DZ CITY BLDG No. 4 and 5?

No court cases are listed for DZ CITY BLDG No. 4 and 5 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of DZ CITY BLDG No. 4 and 5?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SKYLINE ENTERPRISES, which has 10 other projects registered on MahaRERA.

All projects with possession due in 2030 in Thane →

Other projects in pincode 400612

All 225 projects in Mumbra (400612) →

Other projects by SKYLINE ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.