Safa Complex
by SAFA ENTERPRISES · Shill, Thane 400612Also near Shil Phata, Shilphata, Daighar Village
What’s in the report? →Possession date of Safa Complex (MahaRERA P51700018832): 30 December 2027, moved from 30 December 2025 (24 months later). It has 136 homes, 49% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700018832, and currently active.
Source: MahaRERA website — records for P51700018832, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Safa Complex?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Safa Complex has moved
30 December 2025
Completion date given when the project was registered
30 December 2027
Extended at the builder's request (MahaRERA application EA24012619576)
Reason the builder gave MahaRERA:
“CC granted for additional floors in Building D of the project Safa Complex comprising of 6 Buildings (A,B,C,D,E&F). The additional floors CC uptill 7th floor of D Wing will require time for completion. Additionally the CC has been granted t…” Read the full reason
“CC granted for additional floors in Building D of the project Safa Complex comprising of 6 Buildings (A,B,C,D,E&F). The additional floors CC uptill 7th floor of D Wing will require time for completion. Additionally the CC has been granted to us by the Thane Municipal Corporation. We have also acquired 53% percentage of consent obtained from Allottees .”
Source: Safa Complex’s extension records on MahaRERA (P51700018832), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Safa Complex
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700018832
- Status
- Registered and active
- Builder
- SAFA ENTERPRISES
- Location
- Shill, Thane · 400612
- Project type
- Residential / Group Housing
- Registered on
- 6 Dec 2018
- Completion date at registration
- December 2025
- Latest completion date
- December 2027
- Delay so far
- 24 months
- Homes
- 136
- Sold or booked
- 49%
- Towers
- 6
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Safa Complex, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAFA COMPLEX A WING | 100% | 100% | 100% | 100% |
| SAFA COMPLEX B WING | 100% | 100% | 100% | 100% |
| SAFA COMPLEX C WING | 100% | 100% | 100% | 100% |
| SAFA COMPLEX D WING | 100% | 100% | 60% | 0% |
| SAFA COMPLEX E WING | 100% | 100% | 100% | 100% |
| SAFA COMPLEX F WING | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SAFA COMPLEX A WING: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Safa Complex every 1–2 months.
Safa Complex: buildings, flats and land, as filed on MahaRERA
- Buildings: SAFA COMPLEX A WING (9 floors, 21 units) · SAFA COMPLEX B WING (9 floors, 21 units) · SAFA COMPLEX C WING (9 floors, 28 units) · SAFA COMPLEX D WING (2 floors, 4 units) · SAFA COMPLEX E WING (6 floors, 20 units) · SAFA COMPLEX F WING (8 floors, 42 units)
- Car parking: 6 covered
- Land: 3,740 sq m (about 0.9 acres) · sanctioned built-up 7,885 sq m · recreational space 286 sq m
- Land, as filed: 51/1A,214/3
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Safa Complex →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Safa Complex: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Safa Complex
What is the possession date of Safa Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Safa Complex in Shill, Thane is 30 December 2027 — 24 months later than 30 December 2025, the date given at registration.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Safa Complex?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Safa Complex's builder has filed on MahaRERA, the official one, is 30 December 2027, already 24 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Safa Complex extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex's builder applied to MahaRERA to extend the completion date once: to 30 December 2027, giving the reason "CC granted for additional floors in Building D of the project Safa Complex comprising of 6 Buildings (A,B,C,D,E&F). The additional floors CC uptill 7th floor of D Wing will require time for completion. Additionally the CC has been granted to us by the Thane Municipal Corporation. We have also acquired 53% percentage of consent obtained from Allottees .".
What is the RERA number of Safa Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Safa Complex in Shill, Thane is P51700018832.
Is Safa Complex registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex is registered as P51700018832 and its status is "Registered and active".
What is the current construction status of Safa Complex? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 6 towers. GharKundli's full report compares construction progress with the deadline.
Does Safa Complex have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Safa Complex safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex is registered on MahaRERA as P51700018832, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Safa Complex?
Safa Complex is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Safa Complex?
For a flat in Safa Complex (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Safa Complex received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex is still under construction, with 30 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Safa Complex uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Safa Complex was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Safa Complex's possession date changes?
The latest dates are on Safa Complex's MahaRERA page (P51700018832). GharKundli's Kundli Watch sends a free WhatsApp update on Safa Complex every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Safa Complex have?
According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex has 6 buildings filed: SAFA COMPLEX A WING with 9 floors and 21 units; SAFA COMPLEX B WING with 9 floors and 21 units; SAFA COMPLEX C WING with 9 floors and 28 units; SAFA COMPLEX D WING with 2 floors and 4 units; SAFA COMPLEX E WING with 6 floors and 20 units; SAFA COMPLEX F WING with 8 floors and 42 units.
How much parking does Safa Complex have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 6 covered car parking spaces for Safa Complex.
How big is the land of Safa Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex stands on 3,740 sq m of land (about 0.9 acres), with 7,885 sq m of sanctioned built-up area and 286 sq m of recreational open space.
What are the reviews of Safa Complex?
Google Maps has reviews of Safa Complex written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Safa Complex?
Safa Complex by SAFA ENTERPRISES is in Shill, Thane, pincode 400612 (near Shil Phata, Shilphata, Daighar Village), Maharashtra, and is registered on MahaRERA as P51700018832, per GharKundli's check of MahaRERA records. Its land is filed as 51/1A,214/3. GharKundli lists all 225 MahaRERA projects in Mumbra (400612).
How many flats are in Safa Complex, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex has 136 homes in 6 towers registered on MahaRERA, and 49% of them are sold or booked.
When was Safa Complex registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Safa Complex was registered on MahaRERA on 6 December 2018. GharKundli did not find a title report on the land on file there.
Does Safa Complex have any legal issues or court cases?
No court cases are listed for Safa Complex on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Safa Complex?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAFA ENTERPRISES.
Check it yourself on MahaRERA
- How to check the possession date of Safa Complex
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Thane
- S K Valley
- Dosti Planet North- Phase 4 - Dosti Opal
- Nice Garden 1
- Veer Square (Thane)
- Raj Tattva Phase 1 Commercial
- Gurukrupa Nityam
- Mauli Krupa
- Panache
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.