by MATRIX ENCLAVES PROJECTS DEV. PVT. LTD (Marathon) · Betawade, ThaneAlso near Mumbra, Kausa, Kurla

Possession: MARATHON NEXWORLD AURA-2 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700000507. Status: Completed. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about MARATHON NEXWORLD AURA-2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MARATHON NEXWORLD AURA-2 has moved

  1. 30 June 2023

    Completion date given when the project was registered

  2. 29 June 2024

    Extended at the builder's request (MahaRERA application EXT51700015241)

    Reason the builder gave MahaRERA:
    “1)Delay of 2 years in receiving High Rise Committee (HRC) NOC from TMC. When the project was launched, there was no HRC in place in Thane. In the midst of the project, HRC was instituted in Thane and our Commencement Certificate (CC) was re…” Read the full reason“1)Delay of 2 years in receiving High Rise Committee (HRC) NOC from TMC. When the project was launched, there was no HRC in place in Thane. In the midst of the project, HRC was instituted in Thane and our Commencement Certificate (CC) was reduced from 30 floors to 22 floors and we were told to apply for HRC to build more than 22 floors. And it took 1.5 years to get this HRC, a timeline we had absolutely not budgeted for when we applied for RERA. 2)Huge increase in costs of basic materials like Steel, Aluminium, glass, paint, electrical cables, tiles etc. due to increase in prices of fuel, ga…”

Source: MARATHON NEXWORLD AURA-2’s extension records on MahaRERA (P51700000507), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MARATHON NEXWORLD AURA-2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the June 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700000507
Status
Completed
Builder
MATRIX ENCLAVES PROJECTS DEV. PVT. LTD
Location
Betawade, Thane · 400612
Project type
Residential / Group Housing
Registered on
18 Jul 2017
Completion date at registration
June 2023
Latest completion date
June 2024
Delay so far
12 months
Homes
351
Towers
2
Complaints on MahaRERA
3
Court cases listed
0
Appeals at the tribunal
3
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of MARATHON NEXWORLD AURA-2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AURA0%100%67%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MARATHON NEXWORLD AURA-2 every month.

MARATHON NEXWORLD AURA-2: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Marathon Realty (a group of 13 linked companies) has 76 projects on MahaRERA since 2017, this one included. Of the 76 GharKundli has checked: 40 finished, 30 within the promised date and 10 needed more time (typically 14 months); 23 still being built, 4 past the promised date (typically 18 months late); 13 lapsed. 214 complaints on MahaRERA across 47 projects.

Read Google reviews of MARATHON NEXWORLD AURA-2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MARATHON NEXWORLD AURA-2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MARATHON NEXWORLD AURA-2

What is the possession date of MARATHON NEXWORLD AURA-2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MARATHON NEXWORLD AURA-2 in Betawade, Thane is 29 June 2024 — 12 months later than 30 June 2023, the date given at registration.

Is the builder's possession date different from the MahaRERA date for MARATHON NEXWORLD AURA-2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MARATHON NEXWORLD AURA-2's builder has filed on MahaRERA, the official one, is 29 June 2024, already 12 months later than the 30 June 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MARATHON NEXWORLD AURA-2 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXWORLD AURA-2's builder applied to MahaRERA to extend the completion date once: to 29 June 2024, giving the reason "1)Delay of 2 years in receiving High Rise Committee (HRC) NOC from TMC. When the project was launched, there was no HRC in place in Thane. In the midst of the project, HRC was instituted in Thane and our Commencement Certificate (CC) was reduced from 30 floors to 22 floors and we were told to apply for HRC to build more than 22 floors. And it took 1.5 years to get this HRC, a timeline we had absolutely not budgeted for when we applied for RERA. 2)Huge increase in costs of basic materials like Steel, Aluminium, glass, paint, electrical cables, tiles etc. due to increase in prices of fuel, ga…".

What is the RERA number of MARATHON NEXWORLD AURA-2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MARATHON NEXWORLD AURA-2 in Betawade, Thane is P51700000507.

Is MARATHON NEXWORLD AURA-2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXWORLD AURA-2 is registered as P51700000507 and its status is "Completed".

What is the construction status of MARATHON NEXWORLD AURA-2?

According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXWORLD AURA-2's status on MahaRERA is "Completed". As filed by the builder, slab work on AURA is 100% done and internal work 67%. GharKundli's full report compares construction progress with the deadline.

Does MARATHON NEXWORLD AURA-2 have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MARATHON NEXWORLD AURA-2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXWORLD AURA-2 is registered on MahaRERA as P51700000507, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does MARATHON NEXWORLD AURA-2 have other wings or phases?

Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: MARATHON NEXWORLD AURA-1 (P51700000652, possession 29 Dec 2023); MARATHON NEXWORLD AURA-3 (P51700022847, possession 31 Dec 2026). Check that your agreement names the registration of your own wing.

How can I get updates if MARATHON NEXWORLD AURA-2's possession date changes?

The latest dates are on MARATHON NEXWORLD AURA-2's MahaRERA page (P51700000507). GharKundli's Kundli Watch sends a free WhatsApp update on MARATHON NEXWORLD AURA-2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MARATHON NEXWORLD AURA-2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXWORLD AURA-2 has 2 buildings filed: AURA with 4 floors; AURA with 27 floors.

How big is the land of MARATHON NEXWORLD AURA-2?

According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXWORLD AURA-2 stands on 1,055 sq m of land (about 0.3 acres), with 2,236 sq m of sanctioned built-up area.

What is the track record of MARATHON NEXWORLD AURA-2's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Marathon Realty (a group of 13 linked companies) has 76 projects on MahaRERA since 2017, this one included. Of the 76 GharKundli has checked: 40 finished, 30 within the promised date and 10 needed more time (typically 14 months); 23 still being built, 4 past the promised date (typically 18 months late); 13 lapsed. 214 complaints on MahaRERA across 47 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of MARATHON NEXWORLD AURA-2?

Google Maps has reviews of MARATHON NEXWORLD AURA-2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MARATHON NEXWORLD AURA-2?

MARATHON NEXWORLD AURA-2 by MATRIX ENCLAVES PROJECTS DEV. PVT. LTD (Marathon) is in Betawade, Thane (pincode 400612), near Mumbra, Kausa, Kurla, Maharashtra, and is registered on MahaRERA as P51700000507, per GharKundli's check of MahaRERA records.

How many homes are in MARATHON NEXWORLD AURA-2?

According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXWORLD AURA-2 has 351 homes in 2 towers registered on MahaRERA.

When was MARATHON NEXWORLD AURA-2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MARATHON NEXWORLD AURA-2 was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on MARATHON NEXWORLD AURA-2?

No court cases are listed for MARATHON NEXWORLD AURA-2 on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of MARATHON NEXWORLD AURA-2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MATRIX ENCLAVES PROJECTS DEV. PVT. LTD, the company Marathon files this project under, which has 4 other projects registered on MahaRERA.

Other projects in Thane

All 225 projects in Mumbra (400612) →

Other projects by MATRIX ENCLAVES PROJECTS DEV. PVT. LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.