Alfa MM Valley D1 D2
by ALFA ENTERPRISES · Kausa-Mumbra-Thane, Thane 400612Registered on MahaRERA as “MM VALLEY D1 D2”
What’s in the report? →Possession date of Alfa MM Valley D1 D2 (MahaRERA P51700049697): 30 April 2032, moved from 31 December 2028 (36 months later). It has 108 homes, 3% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700049697, and currently active. Its completion date has moved from December 2028 to April 2032: 36 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700049697, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Alfa MM Valley D1 D2?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Alfa MM Valley D1 D2 has moved
31 December 2028
Completion date given when the project was registered
31 December 2031
Extended at the builder's request (MahaRERA application EA20032620305)
Reason the builder gave MahaRERA:
“The project falls under the Environmental Clearance (EC) regime and processing of certain approvals in the past year has taken longer than anticipated. Amendment to Environmental Clearance required additional procedural time beyond the init…” Read the full reason
“The project falls under the Environmental Clearance (EC) regime and processing of certain approvals in the past year has taken longer than anticipated. Amendment to Environmental Clearance required additional procedural time beyond the initially estimated schedule.As a result, the construction schedule has been delayed by approximately two years from the originally estimated timeline.”30 April 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Alfa MM Valley D1 D2’s extension records on MahaRERA (P51700049697), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Alfa MM Valley D1 D2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- MM VALLEY A-1P51700024240 · possession 30 Dec 2025
- MahaRERA registration
- P51700049697
- Status
- Registered and active
- Builder
- ALFA ENTERPRISES
- Location
- Kausa-Mumbra-Thane, Thane · 400612
- Project type
- Others
- Registered on
- 22 Feb 2023
- Completion date at registration
- December 2028
- Latest completion date
- April 2032
- Delay so far
- 36 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 108
- Sold or booked
- 3%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Alfa MM Valley D1 D2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MM VALLEY D1 | 100% | 26% | 10% | 17% |
| MM VALLEY D2 | 100% | 15% | 9% | 17% |
Commencement certificate (CC), as filed on MahaRERA
- MM VALLEY D1: covers Stilt + Podium/ 1st Floor (Comm.) + 2nd Floor to 8th Floor + 9th Floor (pt.) to 11 th (pt.) Floor
- MM VALLEY D2: covers Stilt + Podium/ 1st Floor (Comm.) + 2nd Floor to 8th Floor + 9th Floor (pt.) to 11 th (pt.) Floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Alfa MM Valley D1 D2 every 1–2 months.
Alfa MM Valley D1 D2: buildings, flats and land, as filed on MahaRERA
- Buildings: MM VALLEY D1 (12 floors, 60 units) · MM VALLEY D2 (12 floors, 58 units)
- Car parking: 62 covered
- Land: 20,062 sq m (about 5.0 acres) · sanctioned built-up 11,984 sq m
- Land, as filed: 55/1,2, 56, 57/1
- Map: Get directions
The builder’s record and reviews
Alfa Enterprises (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 11 months); 1 still being built, none past the promised date yet. 16 complaints on MahaRERA across 4 projects.
Read Google reviews of Alfa MM Valley D1 D2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Alfa MM Valley D1 D2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Alfa MM Valley D1 D2
What is the possession date of Alfa MM Valley D1 D2?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Alfa MM Valley D1 D2 in Kausa-Mumbra-Thane, Thane is 30 April 2032 — 36 months later than 31 December 2028, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 36 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Alfa MM Valley D1 D2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Alfa MM Valley D1 D2's builder has filed on MahaRERA, the official one, is 30 April 2032, already 36 months later than the 31 December 2028 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Alfa MM Valley D1 D2 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "The project falls under the Environmental Clearance (EC) regime and processing of certain approvals in the past year has taken longer than anticipated. Amendment to Environmental Clearance required additional procedural time beyond the initially estimated schedule.As a result, the construction schedule has been delayed by approximately two years from the originally estimated timeline.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Alfa MM Valley D1 D2?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Alfa MM Valley D1 D2 in Kausa-Mumbra-Thane, Thane is P51700049697.
Is Alfa MM Valley D1 D2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2 is registered as P51700049697 and its status is "Registered and active".
What is the current construction status of Alfa MM Valley D1 D2? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 15% to 26% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Alfa MM Valley D1 D2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Alfa MM Valley D1 D2 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2 is registered on MahaRERA as P51700049697, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Alfa MM Valley D1 D2?
Alfa MM Valley D1 D2 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Alfa MM Valley D1 D2?
For a flat in Alfa MM Valley D1 D2 (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Alfa MM Valley D1 D2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2 is still under construction, with 30 April 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Alfa MM Valley D1 D2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Alfa MM Valley D1 D2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Alfa MM Valley D1 D2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: MM VALLEY A-1 (P51700024240, possession 30 Dec 2025). Check that your agreement names the registration of your own wing.
How can I get updates if Alfa MM Valley D1 D2's possession date changes?
The latest dates are on Alfa MM Valley D1 D2's MahaRERA page (P51700049697). GharKundli's Kundli Watch sends a free WhatsApp update on Alfa MM Valley D1 D2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Alfa MM Valley D1 D2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2 has 2 buildings filed: MM VALLEY D1 with 12 floors and 60 units; MM VALLEY D2 with 12 floors and 58 units.
How much parking does Alfa MM Valley D1 D2 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 62 covered car parking spaces for Alfa MM Valley D1 D2.
How big is the land of Alfa MM Valley D1 D2?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2 stands on 20,062 sq m of land (about 5.0 acres), with 11,984 sq m of sanctioned built-up area.
What is the track record of Alfa MM Valley D1 D2's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa Enterprises (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 11 months); 1 still being built, none past the promised date yet. 16 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Alfa MM Valley D1 D2?
Google Maps has reviews of Alfa MM Valley D1 D2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Alfa MM Valley D1 D2?
Alfa MM Valley D1 D2 by ALFA ENTERPRISES is in Kausa-Mumbra-Thane, Thane, pincode 400612, Maharashtra, and is registered on MahaRERA as P51700049697, per GharKundli's check of MahaRERA records. Its land is filed as 55/1,2, 56, 57/1. GharKundli lists all 225 MahaRERA projects in Mumbra (400612).
How many flats are in Alfa MM Valley D1 D2, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2 has 108 homes in 2 towers registered on MahaRERA, and 3% of them are sold or booked.
When was Alfa MM Valley D1 D2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Alfa MM Valley D1 D2 was registered on MahaRERA on 22 February 2023. GharKundli did not find a title report on the land on file there.
Does Alfa MM Valley D1 D2 have any legal issues or court cases?
No court cases are listed for Alfa MM Valley D1 D2 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Alfa MM Valley D1 D2?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ALFA ENTERPRISES, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Alfa MM Valley D1 D2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mumbra (400612)
- Kohinoor Imperia
- Marina
- Sky Valley - Phase 2
- DZ City - Building No 1
- Yes Central Galleria 1
- Zubair Enclave
- DZ City - Building No 2
- DZ CITY BLDG No. 4 and 5
Other projects by ALFA ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.