Possession date of AL-QUDDUS RESIDENCY: 30 June 2027, moved from 30 June 2020 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700009468, and currently active. 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about AL-QUDDUS RESIDENCY?
How the possession date of AL-QUDDUS RESIDENCY has moved
30 June 2020
Completion date given when the project was registered
29 June 2021
Extended at the builder's request (MahaRERA application EXT51700002533)
Reason the builder gave MahaRERA: “Dear Sir/Madam, Work is slow due to some Statutory permissions are to be obtained, which is in the process. Kindly grant us extension we will complete the project in the extended time.”
30 June 2023
Extended at the builder's request (MahaRERA application EXT51700012308)
Reason the builder gave MahaRERA:
“Due to lockdown situation in the country the cash flow was very low from the customer and also Statutory permissions/clearances from various authorities are pending. We seek to apply for these permissions with various statutory departments…” Read the full reason
“Due to lockdown situation in the country the cash flow was very low from the customer and also Statutory permissions/clearances from various authorities are pending. We seek to apply for these permissions with various statutory departments and hence, we request you to kindly grant us an extension upto 30/06/2023.”30 June 2024
Extended at the builder's request (MahaRERA application EXT51700016864)
Reason the builder gave MahaRERA: “Statutory permissions/clearances from various authorities are pending.”
30 June 2027
Extended at the builder's request (MahaRERA application EA15052501131)
Reason the builder gave MahaRERA: “Work is slow due to some Statutory permissions are to be obtained, which is in the process. Kindly grant us extension we will complete the project in the extended time.”
Source: AL-QUDDUS RESIDENCY’s extension records on MahaRERA (P51700009468), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AL-QUDDUS RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the June 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700009468
- Status
- Registered and active
- Builder
- ALLIANCE REALTY
- Location
- Kausa, Thane · 400612
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- June 2020
- Latest completion date
- June 2027
- Delay so far
- 84 months
- Homes
- 61
- Sold or booked
- 41%
- Towers
- 2
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AL-QUDDUS RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AL-QUDDUS RESIDENCY A | 100% | 100% | 65% | 10% |
| AL-QUDDUS RESIDENCY B | 100% | 100% | 65% | 10% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AL-QUDDUS RESIDENCY every month.
AL-QUDDUS RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: AL-QUDDUS RESIDENCY A (9 floors, 21 units) · AL-QUDDUS RESIDENCY B (9 floors, 40 units)
- Car parking: 2 covered
- Land: 1,200 sq m (about 0.3 acres) · sanctioned built-up 1,883 sq m · recreational space 180 sq m
- Boundaries filed include: propery of kalwa masjid trust
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AL-QUDDUS RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AL-QUDDUS RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AL-QUDDUS RESIDENCY
What is the possession date of AL-QUDDUS RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AL-QUDDUS RESIDENCY in Kausa, Thane is 30 June 2027 — 84 months later than 30 June 2020, the date given at registration.
Is the builder's possession date different from the MahaRERA date for AL-QUDDUS RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AL-QUDDUS RESIDENCY's builder has filed on MahaRERA, the official one, is 30 June 2027, already 84 months later than the 30 June 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AL-QUDDUS RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), AL-QUDDUS RESIDENCY's builder applied to MahaRERA to extend the completion date 4 times: to 29 June 2021, giving the reason "Dear Sir/Madam, Work is slow due to some Statutory permissions are to be obtained, which is in the process. Kindly grant us extension we will complete the project in the extended time."; to 30 June 2023, giving the reason "Due to lockdown situation in the country the cash flow was very low from the customer and also Statutory permissions/clearances from various authorities are pending. We seek to apply for these permissions with various statutory departments and hence, we request you to kindly grant us an extension upto 30/06/2023."; to 30 June 2024, giving the reason "Statutory permissions/clearances from various authorities are pending."; to 30 June 2027, giving the reason "Work is slow due to some Statutory permissions are to be obtained, which is in the process. Kindly grant us extension we will complete the project in the extended time.".
What is the RERA number of AL-QUDDUS RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AL-QUDDUS RESIDENCY in Kausa, Thane is P51700009468.
Is AL-QUDDUS RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AL-QUDDUS RESIDENCY is registered as P51700009468 and its status is "Registered and active".
What is the construction status of AL-QUDDUS RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AL-QUDDUS RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does AL-QUDDUS RESIDENCY have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is AL-QUDDUS RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), AL-QUDDUS RESIDENCY is registered on MahaRERA as P51700009468, its completion date has moved 84 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AL-QUDDUS RESIDENCY's possession date changes?
The latest dates are on AL-QUDDUS RESIDENCY's MahaRERA page (P51700009468). GharKundli's Kundli Watch sends a free WhatsApp update on AL-QUDDUS RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AL-QUDDUS RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), AL-QUDDUS RESIDENCY has 2 buildings filed: AL-QUDDUS RESIDENCY A with 9 floors and 21 units; AL-QUDDUS RESIDENCY B with 9 floors and 40 units.
How much parking does AL-QUDDUS RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 2 covered car parking spaces for AL-QUDDUS RESIDENCY.
How big is the land of AL-QUDDUS RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AL-QUDDUS RESIDENCY stands on 1,200 sq m of land (about 0.3 acres), with 1,883 sq m of sanctioned built-up area and 180 sq m of recreational open space.
Where can I read reviews of AL-QUDDUS RESIDENCY?
Google Maps has reviews of AL-QUDDUS RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AL-QUDDUS RESIDENCY?
AL-QUDDUS RESIDENCY by ALLIANCE REALTY is in Kausa, Thane (pincode 400612), near Shil, Mumbra, Maharashtra, and is registered on MahaRERA as P51700009468, per GharKundli's check of MahaRERA records. Its boundaries filed there include propery of kalwa masjid trust.
How many homes are in AL-QUDDUS RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), AL-QUDDUS RESIDENCY has 61 homes in 2 towers registered on MahaRERA, and 41% of them are sold or booked.
When was AL-QUDDUS RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AL-QUDDUS RESIDENCY was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on AL-QUDDUS RESIDENCY?
No court cases are listed for AL-QUDDUS RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of AL-QUDDUS RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ALLIANCE REALTY.
Check it yourself on MahaRERA
- How to check the possession date of AL-QUDDUS RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in pincode 400612
- MARINA
- NICE GARDEN 2
- DZ CITY - BUILDING NO 2
- DZ CITY - BUILDING NO 3
- YES CENTRAL GALLERIA 1
- ZUBAIR ENCLAVE
- SKY VALLEY - PHASE 2
- Kohinoor Imperia
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.