Samrin Changuna Aangan
by SAMRIN DREAMSPACES PRIVATE LTD · Mumbra, Thane 400612Registered on MahaRERA as “CHANGUNA AANGAN”
What’s in the report? →Possession date of Samrin Changuna Aangan (MahaRERA P51700051386): 30 October 2027, moved from 31 December 2025 (18 months later). It has 337 homes, 36% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700051386, and currently active. Its completion date has moved from December 2025 to October 2027: 18 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700051386, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Samrin Changuna Aangan?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Samrin Changuna Aangan has moved
31 December 2025
Completion date given when the project was registered
30 June 2027
Extended at the builder's request (MahaRERA application EXT51700024796)
Reason the builder gave MahaRERA:
“The Promoter respectfully submits the following reasons for delay in completion of the captioned project: Landowner’s Family Dispute and Settlement Delay: A delay occurred on account of internal disputes among the legal heirs and relatives…” Read the full reason
“The Promoter respectfully submits the following reasons for delay in completion of the captioned project: Landowner’s Family Dispute and Settlement Delay: A delay occurred on account of internal disputes among the legal heirs and relatives of the landowner concerning their respective shares and rights in the property. The said disputes and subsequent settlement process took considerable time to resolve, resulting in unavoidable interruption in project progress and execution of related documentation. Financial Constraints and Cash Flow Challenges: During the period of delay, the project also…”30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Samrin Changuna Aangan’s extension records on MahaRERA (P51700051386), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Samrin Changuna Aangan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700051386
- Status
- Registered and active
- Builder
- SAMRIN DREAMSPACES PRIVATE LTD
- Location
- Mumbra, Thane · 400612
- Project type
- Mixed
- Registered on
- 8 Jun 2023
- Completion date at registration
- December 2025
- Latest completion date
- October 2027
- Delay so far
- 18 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 337
- Sold or booked
- 36%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Samrin Changuna Aangan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CHANGUNA AANGAN | 100% | 13% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- CHANGUNA AANGAN: covers 20 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Samrin Changuna Aangan every 1–2 months.
Samrin Changuna Aangan: buildings, flats and land, as filed on MahaRERA
- Buildings: CHANGUNA AANGAN (20 floors, 353 units)
- Car parking: 72 covered, 53 open
- Land: 4,450 sq m (about 1.1 acres) · sanctioned built-up 18,885 sq m
- Land, as filed: S. NO. 162 & 167 H. NO. 4
- Map: Get directions
The builder’s record and reviews
Samrin Dreamspaces (a group of 7 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 4 past the promised date (typically 12 months late); 3 lapsed. 37 complaints on MahaRERA across 6 projects.
Read Google reviews of Samrin Changuna Aangan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Samrin Changuna Aangan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Samrin Changuna Aangan
What is the possession date of Samrin Changuna Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Samrin Changuna Aangan in Mumbra, Thane is 30 October 2027 — 18 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Samrin Changuna Aangan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Samrin Changuna Aangan's builder has filed on MahaRERA, the official one, is 30 October 2027, already 18 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Samrin Changuna Aangan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "The Promoter respectfully submits the following reasons for delay in completion of the captioned project: Landowner’s Family Dispute and Settlement Delay: A delay occurred on account of internal disputes among the legal heirs and relatives of the landowner concerning their respective shares and rights in the property. The said disputes and subsequent settlement process took considerable time to resolve, resulting in unavoidable interruption in project progress and execution of related documentation. Financial Constraints and Cash Flow Challenges: During the period of delay, the project also…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Samrin Changuna Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Samrin Changuna Aangan in Mumbra, Thane is P51700051386.
Is Samrin Changuna Aangan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan is registered as P51700051386 and its status is "Registered and active".
What is the current construction status of Samrin Changuna Aangan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CHANGUNA AANGAN is 13% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Samrin Changuna Aangan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Samrin Changuna Aangan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan is registered on MahaRERA as P51700051386, its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Samrin Changuna Aangan?
Samrin Changuna Aangan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Samrin Changuna Aangan?
For a flat in Samrin Changuna Aangan (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Samrin Changuna Aangan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Samrin Changuna Aangan a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan's planning authority on MahaRERA is Thane Municipal Corporation, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Samrin Changuna Aangan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Samrin Changuna Aangan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Samrin Changuna Aangan's possession date changes?
The latest dates are on Samrin Changuna Aangan's MahaRERA page (P51700051386). GharKundli's Kundli Watch sends a free WhatsApp update on Samrin Changuna Aangan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Samrin Changuna Aangan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan has one building filed: CHANGUNA AANGAN with 20 floors and 353 units.
How much parking does Samrin Changuna Aangan have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 72 covered and 53 open car parking spaces for Samrin Changuna Aangan.
How big is the land of Samrin Changuna Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan stands on 4,450 sq m of land (about 1.1 acres), with 18,885 sq m of sanctioned built-up area.
What is the track record of Samrin Changuna Aangan's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Dreamspaces (a group of 7 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 4 past the promised date (typically 12 months late); 3 lapsed. 37 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Samrin Changuna Aangan?
Google Maps has reviews of Samrin Changuna Aangan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Samrin Changuna Aangan?
Samrin Changuna Aangan by SAMRIN DREAMSPACES PRIVATE LTD is in Mumbra, Thane, pincode 400612, Maharashtra, and is registered on MahaRERA as P51700051386, per GharKundli's check of MahaRERA records. Its land is filed as S. NO. 162 & 167 H. NO. 4. GharKundli lists all 225 MahaRERA projects in Mumbra (400612).
How many flats are in Samrin Changuna Aangan, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan has 337 homes in 1 tower registered on MahaRERA, and 36% of them are sold or booked.
When was Samrin Changuna Aangan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Samrin Changuna Aangan was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.
Does Samrin Changuna Aangan have any legal issues or court cases?
No court cases are listed for Samrin Changuna Aangan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Samrin Changuna Aangan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAMRIN DREAMSPACES PRIVATE LTD.
Check it yourself on MahaRERA
- How to check the possession date of Samrin Changuna Aangan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Mumbra (400612)
- Kohinoor Imperia
- Marina
- Sky Valley - Phase 2
- DZ City - Building No 1
- Yes Central Galleria 1
- Zubair Enclave
- DZ City - Building No 2
- Nice Garden 2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.