Mera Ghar
by Parshwa Gruh Nirman LLP · Old Mumbai -Pune Highway Dist, Thane
Possession: Mera Ghar is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700006760. Status: Completed. 10 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Mera Ghar?
How the possession date of Mera Ghar has moved
30 June 2018
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT51700000434)
Reason the builder gave MahaRERA:
“Our project “Mera Ghar is Registered under MAha RERA. We would not be able to submit Occupancy Certificate by June 2018 due to Last mile infrastructure is left out. Since Oc application will be given in another 2 months. Kindly allow extens…” Read the full reason
“Our project “Mera Ghar is Registered under MAha RERA. We would not be able to submit Occupancy Certificate by June 2018 due to Last mile infrastructure is left out. Since Oc application will be given in another 2 months. Kindly allow extension of project till June 2019. Requisite fee for extension of timeline is also paid herewith.”30 April 2020
Extended at the builder's request (MahaRERA application EXT51700005338)
Reason the builder gave MahaRERA:
“Our project "Mera Ghar" work is completed in all respect and request for Occupancy Certificate has been made to NAINA CIDCO vide request letter dated 23-09-2019. Occupancy Certificate is getting delayed from concerned Authority. Further the…” Read the full reason
“Our project "Mera Ghar" work is completed in all respect and request for Occupancy Certificate has been made to NAINA CIDCO vide request letter dated 23-09-2019. Occupancy Certificate is getting delayed from concerned Authority. Further there is change in approval authority from NAINA CIDCO to MMRDA.”30 October 2020
Revised completion date on MahaRERA
Source: Mera Ghar’s extension records on MahaRERA (P51700006760), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mera Ghar
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 10 complaints, and how it ended
- Construction pace against the October 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700006760
- Status
- Completed
- Builder
- Parshwa Gruh Nirman LLP
- Location
- Old Mumbai -Pune Highway Dist, Thane · 400612
- Project type
- Residential / Group Housing
- Registered on
- 16 Aug 2017
- Completion date at registration
- June 2018
- Latest completion date
- October 2020
- Delay so far
- 28 months
- Homes
- 98
- Towers
- 2
- Complaints on MahaRERA
- 10
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of Mera Ghar, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A and D | 100% | 100% | 100% | 100% |
| Wing B and C | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mera Ghar every month.
Mera Ghar: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A and D (6 floors) · Wing B and C (6 floors)
- Land: 3,340 sq m (about 0.8 acres) · sanctioned built-up 2,961 sq m · recreational space 334 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Mera Ghar →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mera Ghar: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mera Ghar
What is the possession date of Mera Ghar?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mera Ghar in Old Mumbai -Pune Highway Dist, Thane is 30 October 2020 — 28 months later than 30 June 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Mera Ghar?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mera Ghar's builder has filed on MahaRERA, the official one, is 30 October 2020, already 28 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mera Ghar extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Mera Ghar's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2020, giving the reason "Our project “Mera Ghar is Registered under MAha RERA. We would not be able to submit Occupancy Certificate by June 2018 due to Last mile infrastructure is left out. Since Oc application will be given in another 2 months. Kindly allow extension of project till June 2019. Requisite fee for extension of timeline is also paid herewith."; to 30 April 2020, giving the reason "Our project "Mera Ghar" work is completed in all respect and request for Occupancy Certificate has been made to NAINA CIDCO vide request letter dated 23-09-2019. Occupancy Certificate is getting delayed from concerned Authority. Further there is change in approval authority from NAINA CIDCO to MMRDA.".
What is the RERA number of Mera Ghar?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mera Ghar in Old Mumbai -Pune Highway Dist, Thane is P51700006760.
Is Mera Ghar registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mera Ghar is registered as P51700006760 and its status is "Completed".
What is the construction status of Mera Ghar?
According to GharKundli's check of MahaRERA records (updated November 2026), Mera Ghar's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Mera Ghar have complaints on MahaRERA?
10 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Mera Ghar safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Mera Ghar is registered on MahaRERA as P51700006760, its MahaRERA status is "Completed", its completion date has moved 28 months since registration and 10 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Mera Ghar's possession date changes?
The latest dates are on Mera Ghar's MahaRERA page (P51700006760). GharKundli's Kundli Watch sends a free WhatsApp update on Mera Ghar every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mera Ghar have?
According to GharKundli's check of MahaRERA records (updated November 2026), Mera Ghar has 2 buildings filed: Wing A and D with 6 floors; Wing B and C with 6 floors.
How big is the land of Mera Ghar?
According to GharKundli's check of MahaRERA records (updated November 2026), Mera Ghar stands on 3,340 sq m of land (about 0.8 acres), with 2,961 sq m of sanctioned built-up area and 334 sq m of recreational open space.
Where can I read reviews of Mera Ghar?
Google Maps has reviews of Mera Ghar written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 10 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mera Ghar?
Mera Ghar by Parshwa Gruh Nirman LLP is in Old Mumbai -Pune Highway Dist, Thane (pincode 400612), Maharashtra, and is registered on MahaRERA as P51700006760, per GharKundli's check of MahaRERA records.
How many homes are in Mera Ghar?
According to GharKundli's check of MahaRERA records (updated November 2026), Mera Ghar has 98 homes in 2 towers registered on MahaRERA.
When was Mera Ghar registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mera Ghar was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Mera Ghar?
No court cases are listed for Mera Ghar on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Mera Ghar?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Parshwa Gruh Nirman LLP.
Check it yourself on MahaRERA
- How to check the possession date of Mera Ghar
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- RAJ TATTVA PHASE 1 COMMERCIAL
- Veer Square (Thane)
- MAULI KRUPA
- GURUKRUPA NITYAM
- Mahavir Breeze Phase 1
- LOTUS
- ASAVARI CO OP HSG SOC LTD
- Panache
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.