KIPL Morya
by khade Infrastructre Pvt. Ltd. · Vadawali, ThaneAlso near owale, Kasarvadavli, Near Kanchan Pushpa
Possession: KIPL Morya is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900010004. Status: Completed. 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about KIPL Morya?
How the possession date of KIPL Morya has moved
30 June 2021
Completion date given when the project was registered
31 December 2021
Extended at the builder's request (MahaRERA application EXT51700010356)
Reason the builder gave MahaRERA:
“Due to Covid second wave Lockdown our work suffered tremendously, as it was extremely difficult to get required labour and material at the site. Understanding our plea we hope you give us an extension of six month. Our current possession da…” Read the full reason
“Due to Covid second wave Lockdown our work suffered tremendously, as it was extremely difficult to get required labour and material at the site. Understanding our plea we hope you give us an extension of six month. Our current possession date is 30th June 2021 pls extend it to 31st December 2021.”30 June 2022
Revised completion date on MahaRERA
Source: KIPL Morya’s extension records on MahaRERA (P51900010004), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KIPL Morya
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900010004
- Status
- Completed
- Builder
- khade Infrastructre Pvt. Ltd.
- Location
- Vadawali, Thane · 400615
- Project type
- Residential / Group Housing
- Registered on
- 23 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- June 2022
- Delay so far
- 12 months
- Homes
- 206
- Towers
- 2
- Complaints on MahaRERA
- 5
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of KIPL Morya, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KIPL Morya - A | 100% | 100% | 100% | 95% |
| KIPL Morya - B | 0% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KIPL Morya every month.
KIPL Morya: buildings, flats and land, as filed on MahaRERA
- Buildings: KIPL Morya - A (19 floors) · KIPL Morya - B (16 floors)
- Land: 5,210 sq m (about 1.3 acres) · sanctioned built-up 5,030 sq m · recreational space 895 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of KIPL Morya →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KIPL Morya: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KIPL Morya
What is the possession date of KIPL Morya?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for KIPL Morya in Vadawali, Thane is 30 June 2022 — 12 months later than 30 June 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for KIPL Morya?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KIPL Morya's builder has filed on MahaRERA, the official one, is 30 June 2022, already 12 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KIPL Morya extended?
According to GharKundli's check of MahaRERA records (updated November 2026), KIPL Morya's builder applied to MahaRERA to extend the completion date once: to 31 December 2021, giving the reason "Due to Covid second wave Lockdown our work suffered tremendously, as it was extremely difficult to get required labour and material at the site. Understanding our plea we hope you give us an extension of six month. Our current possession date is 30th June 2021 pls extend it to 31st December 2021.".
What is the RERA number of KIPL Morya?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of KIPL Morya in Vadawali, Thane is P51900010004.
Is KIPL Morya registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KIPL Morya is registered as P51900010004 and its status is "Completed".
What is the construction status of KIPL Morya?
According to GharKundli's check of MahaRERA records (updated November 2026), KIPL Morya's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does KIPL Morya have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KIPL Morya safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), KIPL Morya is registered on MahaRERA as P51900010004, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 5 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KIPL Morya's possession date changes?
The latest dates are on KIPL Morya's MahaRERA page (P51900010004). GharKundli's Kundli Watch sends a free WhatsApp update on KIPL Morya every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KIPL Morya have?
According to GharKundli's check of MahaRERA records (updated November 2026), KIPL Morya has 2 buildings filed: KIPL Morya - A with 19 floors; KIPL Morya - B with 16 floors.
How big is the land of KIPL Morya?
According to GharKundli's check of MahaRERA records (updated November 2026), KIPL Morya stands on 5,210 sq m of land (about 1.3 acres), with 5,030 sq m of sanctioned built-up area and 895 sq m of recreational open space.
Where can I read reviews of KIPL Morya?
Google Maps has reviews of KIPL Morya written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KIPL Morya?
KIPL Morya by khade Infrastructre Pvt. Ltd. is in Vadawali, Thane (pincode 400615), near owale, Kasarvadavli, Near Kanchan Pushpa, Maharashtra, and is registered on MahaRERA as P51900010004, per GharKundli's check of MahaRERA records.
How many homes are in KIPL Morya?
According to GharKundli's check of MahaRERA records (updated November 2026), KIPL Morya has 206 homes in 2 towers registered on MahaRERA.
When was KIPL Morya registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), KIPL Morya was registered on MahaRERA on 23 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KIPL Morya?
No court cases are listed for KIPL Morya on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KIPL Morya?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is khade Infrastructre Pvt. Ltd..
Check it yourself on MahaRERA
- How to check the possession date of KIPL Morya
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Thane
- RAJ TATTVA PHASE 1 COMMERCIAL
- Veer Square (Thane)
- GURUKRUPA NITYAM
- MAULI KRUPA
- ASAVARI CO OP HSG SOC LTD
- LOTUS
- Panache
- Mahavir Breeze Phase 1
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.