by Sagar Enterprise · Owala, Thane

Possession: TIARA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700020733. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about TIARA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TIARA has moved

  1. 30 March 2024

    Completion date given when the project was registered

  2. 30 March 2025

    Extended at the builder's request (MahaRERA application EXT51700019120)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 30 November 2026

    Extended at the builder's request (MahaRERA application EA16072621773)

    Reason the builder gave MahaRERA:
    “The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 06/06/2024 and we have also initiated the process for…” Read the full reason“The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 06/06/2024 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, sanctioned number of floors and total parking. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provide assurance…”

Source: TIARA’s extension records on MahaRERA (P51700020733), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TIARA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700020733
Status
Completed
Builder
Sagar Enterprise
Location
Owala, Thane · 400615
Project type
Others
Registered on
7 May 2019
Completion date at registration
March 2024
Latest completion date
November 2026
Delay so far
32 months
Homes
221
Sold or booked
71%
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of TIARA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TIARA A WING100%100%100%100%
TIARA B WING100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • TIARA A WING: covers 22 floors
  • TIARA B WING: covers 22 floors

Latest CC order on MahaRERA: dated 06/06/2024.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TIARA every month.

TIARA: buildings, flats and land, as filed on MahaRERA

  • Buildings: TIARA A WING (22 floors, 109 units) · TIARA B WING (22 floors, 112 units)
  • Car parking: 148 covered
  • Land: 4,078 sq m (about 1.0 acres) · sanctioned built-up 11,686 sq m · recreational space 1,286 sq m

The builder’s record and reviews

Sagar Enterprise has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 16 months); 1 still being built, 1 past the promised date (typically 3 months late). 2 complaints on MahaRERA across 2 projects.

Read Google reviews of TIARA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TIARA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TIARA

What is the possession date of TIARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TIARA in Owala, Thane is 30 November 2026 — 32 months later than 30 March 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for TIARA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TIARA's builder has filed on MahaRERA, the official one, is 30 November 2026, already 32 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TIARA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TIARA's builder applied to MahaRERA to extend the completion date 2 times: to 30 March 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 30 November 2026, giving the reason "The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Occupation Certificate (OC) on 06/06/2024 and we have also initiated the process for the possession as well. However, there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, sanctioned number of floors and total parking. In view of this as the said project obtained full OC uploading consents from allottees will not be required. To provide assurance…".

What is the RERA number of TIARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TIARA in Owala, Thane is P51700020733.

Is TIARA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TIARA is registered as P51700020733 and its status is "Completed".

What is the construction status of TIARA?

According to GharKundli's check of MahaRERA records (updated October 2026), TIARA's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does TIARA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is TIARA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TIARA is registered on MahaRERA as P51700020733, its MahaRERA status is "Completed", its completion date has moved 32 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TIARA's possession date changes?

The latest dates are on TIARA's MahaRERA page (P51700020733). GharKundli's Kundli Watch sends a free WhatsApp update on TIARA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TIARA have?

According to GharKundli's check of MahaRERA records (updated October 2026), TIARA has 2 buildings filed: TIARA A WING with 22 floors and 109 units; TIARA B WING with 22 floors and 112 units.

How much parking does TIARA have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 148 covered car parking spaces for TIARA.

How big is the land of TIARA?

According to GharKundli's check of MahaRERA records (updated October 2026), TIARA stands on 4,078 sq m of land (about 1.0 acres), with 11,686 sq m of sanctioned built-up area and 1,286 sq m of recreational open space.

What is the track record of TIARA's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Enterprise has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 16 months); 1 still being built, 1 past the promised date (typically 3 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of TIARA?

Google Maps has reviews of TIARA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TIARA?

TIARA by Sagar Enterprise is in Owala, Thane (pincode 400615), Maharashtra, and is registered on MahaRERA as P51700020733, per GharKundli's check of MahaRERA records.

How many homes are in TIARA?

According to GharKundli's check of MahaRERA records (updated October 2026), TIARA has 221 homes in 2 towers registered on MahaRERA, and 71% of them are sold or booked.

When was TIARA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TIARA was registered on MahaRERA on 7 May 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on TIARA?

No court cases are listed for TIARA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of TIARA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sagar Enterprise, which has 5 other projects registered on MahaRERA.