Sagar Odysseus
by Sagar Enterprise · Kolshet, Thane 400607Also near Hiranandani Estate, Patlipada, SandozbaughRegistered on MahaRERA as “Odysseus”
What’s in the report? →Possession date of Sagar Odysseus (MahaRERA P51700050539): 30 January 2027, moved from 31 March 2026 (6 months later). No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700050539, and currently active. Its completion date has moved from March 2026 to January 2027: 6 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700050539, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sagar Odysseus?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sagar Odysseus has moved
31 March 2026
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EA09042620586)
Reason the builder gave MahaRERA:
“Due to certain unforeseen and unavoidable circumstances, including challenges in procurement, financial limitations, and site-related constraints, the progress of the project has been impacted, resulting in a delay in the originally schedul…” Read the full reason
“Due to certain unforeseen and unavoidable circumstances, including challenges in procurement, financial limitations, and site-related constraints, the progress of the project has been impacted, resulting in a delay in the originally scheduled timeline. Notwithstanding these difficulties, the promoter remains committed to the timely completion of the project and has initiated corrective measures to overcome the said constraints. These measures include optimizing the procurement process, securing necessary financial arrangements, and systematically resolving on-site issues. Focused and contin…”30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sagar Odysseus’s extension records on MahaRERA (P51700050539), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sagar Odysseus
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700050539
- Status
- Registered and active
- Builder
- Sagar Enterprise
- Location
- Kolshet, Thane · 400607
- Project type
- Commercial
- Registered on
- 21 Apr 2023
- Completion date at registration
- March 2026
- Latest completion date
- January 2027
- Delay so far
- 6 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 0
- Sold or booked
- 63%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Sagar Odysseus, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Wing A: covers 11 (2 Basements + Ground + 8 Upper Floors)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sagar Odysseus every 1–2 months.
Sagar Odysseus: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A (11 floors, 125 units)
- Car parking: 148 covered
- Land: 3,640 sq m (about 0.9 acres) · sanctioned built-up 9,855 sq m
- Boundaries filed include: New Horizon School, Villa Grand Road
- Land, as filed: Survey No.180, Hissa No.5
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Sagar Enterprise has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 16 months); 1 still being built, 1 past the promised date (typically 3 months late). 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Sagar Odysseus →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sagar Odysseus: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sagar Odysseus
What is the possession date of Sagar Odysseus?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sagar Odysseus in Kolshet, Thane is 30 January 2027 — 6 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 6 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sagar Odysseus?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sagar Odysseus's builder has filed on MahaRERA, the official one, is 30 January 2027, already 6 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sagar Odysseus extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "Due to certain unforeseen and unavoidable circumstances, including challenges in procurement, financial limitations, and site-related constraints, the progress of the project has been impacted, resulting in a delay in the originally scheduled timeline. Notwithstanding these difficulties, the promoter remains committed to the timely completion of the project and has initiated corrective measures to overcome the said constraints. These measures include optimizing the procurement process, securing necessary financial arrangements, and systematically resolving on-site issues. Focused and contin…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sagar Odysseus?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sagar Odysseus in Kolshet, Thane is P51700050539.
Is Sagar Odysseus registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus is registered as P51700050539 and its status is "Registered and active".
What is the current construction status of Sagar Odysseus? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Sagar Odysseus have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sagar Odysseus safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus is registered on MahaRERA as P51700050539, its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sagar Odysseus?
Sagar Odysseus is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sagar Odysseus?
For a flat in Sagar Odysseus (Thane), stamp duty is 7% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess + 1% LBT/Surcharge. A woman buying in her own name pays 6%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹7 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Sagar Odysseus received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus is still under construction, with 30 January 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sagar Odysseus uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sagar Odysseus was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sagar Odysseus's possession date changes?
The latest dates are on Sagar Odysseus's MahaRERA page (P51700050539). GharKundli's Kundli Watch sends a free WhatsApp update on Sagar Odysseus every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sagar Odysseus have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus has one building filed: Wing A with 11 floors and 125 units.
How much parking does Sagar Odysseus have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 148 covered car parking spaces for Sagar Odysseus.
How big is the land of Sagar Odysseus?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus stands on 3,640 sq m of land (about 0.9 acres), with 9,855 sq m of sanctioned built-up area.
What is the track record of Sagar Odysseus's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Enterprise has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 5 finished, 3 within the promised date and 2 needed more time (typically 16 months); 1 still being built, 1 past the promised date (typically 3 months late). 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Sagar Odysseus?
Google Maps has reviews of Sagar Odysseus written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sagar Odysseus?
Sagar Odysseus by Sagar Enterprise is in Kolshet, Thane, pincode 400607 (near Hiranandani Estate, Patlipada, Sandozbaugh), Maharashtra, and is registered on MahaRERA as P51700050539, per GharKundli's check of MahaRERA records. Its boundaries filed there include New Horizon School, Villa Grand Road. Its land is filed as Survey No.180, Hissa No.5. GharKundli lists all 218 MahaRERA projects in Sandozbaugh (400607).
How many flats are in Sagar Odysseus, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus has 0 homes in 1 tower registered on MahaRERA, and 63% of them are sold or booked.
When was Sagar Odysseus registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sagar Odysseus was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.
Does Sagar Odysseus have any legal issues or court cases?
No court cases are listed for Sagar Odysseus on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sagar Odysseus?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sagar Enterprise, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Sagar Odysseus
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Sandozbaugh (400607)
- Marigold B wing
- Lodha Amara Tower 47 and 48
- Lodha Amara Tower 44
- Highland Park Building 2- K25 Wing A Phase 2
- Regency Business Park Phase V
- Lodha Crown Kolshet - Tower 3
- Forestville - Phase 1
- The Helios
Other projects by Sagar Enterprise
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.