Skip to content
GharKundli

THE HELIOS

by RAJ LAXMI DEVELOPERS (Mayfair) · Kolshet, ThaneAlso near Dhokali, Balkum, Chakala, Andheri East

Possession date of THE HELIOS: 30 April 2032, moved from 31 December 2022 (108 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700001555, and currently active. Its completion date has moved from December 2022 to April 2032: 108 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about THE HELIOS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of THE HELIOS has moved

  1. 31 December 2022

    Completion date given when the project was registered

  2. 31 December 2031

    Extended at the builder's request (MahaRERA application EXT51700023043)

    Reason the builder gave MahaRERA: “We are Re-launching Project as there were approval issues and we have not sold any inventory as such.”
  3. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: THE HELIOS’s extension records on MahaRERA (P51700001555), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on THE HELIOS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700001555
Status
Registered and active
Builder
RAJ LAXMI DEVELOPERS
Location
Kolshet, Thane · 400607
Project type
Residential / Group Housing
Registered on
28 Jul 2017
Completion date at registration
December 2022
Latest completion date
April 2032
Delay so far
108 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
468
Sold or booked
0%
Towers
2
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of THE HELIOS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building 10%0%0%0%
Building No 20%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Building 1: covers 43 floors
  • Building No 2: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE HELIOS every month.

THE HELIOS: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building 1 (43 floors, 468 units) · Building No 2 (6 floors, 5 units)
  • Car parking: 764 covered
  • Land: 7,320 sq m (about 1.8 acres) · sanctioned built-up 32,645 sq m · recreational space 690 sq m
  • Boundaries filed include: Kolshet Road
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Mayfair Housing (a group of 4 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 6 finished, all within the promised date; 7 still being built, 1 past the promised date (typically 30 months late). 13 complaints on MahaRERA across 3 projects.

Read Google reviews of THE HELIOS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

THE HELIOS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about THE HELIOS

What is the possession date of THE HELIOS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE HELIOS in Kolshet, Thane is 30 April 2032 — 108 months later than 31 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for THE HELIOS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date THE HELIOS's builder has filed on MahaRERA, the official one, is 30 April 2032, already 108 months later than the 31 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of THE HELIOS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), THE HELIOS's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "We are Re-launching Project as there were approval issues and we have not sold any inventory as such.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of THE HELIOS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE HELIOS in Kolshet, Thane is P51700001555.

Is THE HELIOS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE HELIOS is registered as P51700001555 and its status is "Registered and active".

What is the construction status of THE HELIOS?

According to GharKundli's check of MahaRERA records (updated October 2026), THE HELIOS's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does THE HELIOS have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is THE HELIOS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), THE HELIOS is registered on MahaRERA as P51700001555, its completion date has moved 108 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if THE HELIOS's possession date changes?

The latest dates are on THE HELIOS's MahaRERA page (P51700001555). GharKundli's Kundli Watch sends a free WhatsApp update on THE HELIOS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does THE HELIOS have?

According to GharKundli's check of MahaRERA records (updated October 2026), THE HELIOS has 2 buildings filed: Building 1 with 43 floors and 468 units; Building No 2 with 6 floors and 5 units.

How much parking does THE HELIOS have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 764 covered car parking spaces for THE HELIOS.

How big is the land of THE HELIOS?

According to GharKundli's check of MahaRERA records (updated October 2026), THE HELIOS stands on 7,320 sq m of land (about 1.8 acres), with 32,645 sq m of sanctioned built-up area and 690 sq m of recreational open space.

What is the track record of THE HELIOS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Mayfair Housing (a group of 4 linked companies) has 15 projects on MahaRERA since 2017, this one included. Of the 13 GharKundli has checked: 6 finished, all within the promised date; 7 still being built, 1 past the promised date (typically 30 months late). 13 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of THE HELIOS?

Google Maps has reviews of THE HELIOS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is THE HELIOS?

THE HELIOS by RAJ LAXMI DEVELOPERS (Mayfair) is in Kolshet, Thane (pincode 400607), near Dhokali, Balkum, Chakala, Andheri East, Maharashtra, and is registered on MahaRERA as P51700001555, per GharKundli's check of MahaRERA records. Its boundaries filed there include Kolshet Road.

How many homes are in THE HELIOS?

According to GharKundli's check of MahaRERA records (updated October 2026), THE HELIOS has 468 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was THE HELIOS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE HELIOS was registered on MahaRERA on 28 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on THE HELIOS?

No court cases are listed for THE HELIOS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of THE HELIOS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJ LAXMI DEVELOPERS, the company Mayfair files this project under, which has 3 other projects registered on MahaRERA.

Other projects in Kolshet

All 218 projects in Sandozbaugh (400607) →

Other projects by RAJ LAXMI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.